Shamokin Township
Anti-Data Center Policies
Shamokin Township’s enacted rules require setbacks from protected places, noise limits and testing, and money set aside for eventual removal. Data centers can still seek approval, but siting and operating limits narrow where projects can proceed.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Shamokin TownshipThe current rules are in Ordinance 2026-1, which the Board of Supervisors adopted on March 11, 2026.Shamokin Township, Northumberland County — data-center ordinance (No. 2026-1)
What this means
The measure imposes setbacks from homes or other protected places, noise limits and sound testing and money set aside for eventual removal. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements23
Township permit with public hearing before Supervisors, Sec. 6(d)-(e); no expiration
Section 13(b) requires the data center and its accessories to be at least 1,000 ft from any existing residential or occupied structure, and the Data Center Accessory Use definition in Section 3 includes generators, substations, and cooling equipment.
Environmental impact study required, Sec. 11(c)
Section 4(c) requires a permit modification for any physical modification that alters the size of the data center or its equipment, but no exemption is stated for like-for-like replacement and added electrical demand is not named as a trigger.
60 dBA day, 55 dBA night at property line, Sec. 14(a)
Section 14(a)(i) to (iii) require preliminary, interim, and as-built sound studies, with the as-built study six months after the certificate of occupancy, but the as-built study is not required at full operating load.
Water feasibility study for nonpublic sources, Sec. 7(b)
Projected water needs disclosed, Sec. 7(a)-(b)
Study must identify how water is recycled or released, Sec. 7(b)
County stormwater, E&S, and NPDES approvals required, Sec. 18
Heat not perceptible at property line, Sec. 11(d); no disclosure or plan
Decommissioning plan must address e-waste removal, Sec. 16(e)
Utility capacity certification, Sec. 8(c); third-party electrical inspection before occupancy, Sec. 8(d)
On-site generation is a separate use under its own regulations, Sec. 8(b); no setbacks stated
Screening from adjoining homes, Sec. 13(a); equipment not in front yard, Sec. 10(a)
Emergency plan reviewed by fire department and 24-hour contact sign, Sec. 12(a), 12(d); no radio coverage or annual update
Section 12(a) requires the emergency response plan to provide for annual fire safety inspections by a qualified professional on behalf of the data center, but no report to the municipal fire official and no deadline to correct deficiencies are required.
Section 11(a) states only that a traffic impact study shall be provided by the applicant, with no requirement to cover construction traffic or to reach the nearest arterial or interchange.
Section 16(a) to (c) require immediate notice on cessation, removal of the data center and accessory equipment within six months, and security of 110 percent of decommissioning cost posted at permit issuance, but the obligations are not in a recorded agreement.
Section 16(d) requires an independent engineer's decommissioning estimate, updated after the first year of operation and every fifth year thereafter, with the financial security updated every five years throughout the life of the project.
One as-built sound study after opening, Sec. 14(a)(iii)
Section 21(b) and (c) require a notice of violation with an opportunity to comply, followed by fines of $500 to $1,000 per day on summary conviction, and Section 14(a)(iii) allows the permit to be revoked for noise violations, but revocation is not preceded by a hearing and Sections 616.1 and 617.2 of the Municipalities Planning Code are not cited.
Township experts at applicant expense only for radiological survey and decommissioning estimate, Sec. 9, Sec. 16(d)