Sewickley Township

Neutral Data Center Policies

Sewickley Township allows data centers in designated districts through special or conditional-use review, providing a clear approval path but adding a step that may cause delay or uncertainty.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Sewickley Township
The current rules are in Ordinance No. 6-2026, which the Board of Supervisors adopted on July 15, 2026.Sewickley Township, Westmoreland County — data-center ordinance (No. 6-2026)

What this means

The measure provides a route for data centers through a special permit or conditional-use review in designated districts. That offers legal certainty, but the extra approval step can add time and uncertainty.

Restrictions & requirementsHide restrictions & requirements32
  • M-T district only, Table of Permitted Uses and Section 4

  • Conditional use with hearing before the Board of Supervisors; no approval expiration, Section 5

  • Base district setbacks only, Section 4.C

  • District height limits stated as applying, Section 4.B

  • 100-ft riparian forest buffer each side, wider on slopes and at wetlands, Section 4.Q

  • Day 90 dBA and night 55 dBA at the property line; 45 dBA night at sensitive receptors, Section 4.G

  • Low-frequency design measures only; no dBC limit or study, Section 4.G

  • Section 4.G.6 of Ordinance 6-2026 requires preliminary, interim, and as-built sound studies using ANSI S1.4-2014 sound level meters, with the as-built study six months after the certificate of occupancy, but the limits apply to normal operations and no study is required at full operating load.

  • Vibration study showing none perceptible past the property line, Section 4.I.

  • Closed-loop cooling required; evaporative cooling not restricted, Section 4.N.3

  • Projected demand and drought plan compliance; no cap or ongoing reporting, Section 4.N

  • Section 4.N.9 requires the applicant to demonstrate that disposal of domestic, cooling, and industrial wastewater has been provided and approved by the Sewage Enforcement Officer, Municipal Authority, basin commission, or DEP, but does not state that the approval must be in hand before the zoning permit.

  • Stormwater plan under the local ordinance and DEP rules, Section 4.O.6

  • Tier 4 generators required; no annual emissions testing, Section 4.L

  • Heat not perceptible at the property line; no thermal plan or disclosure, Section 4.I

  • E-waste, batteries, and refrigerants disposed of under law; no recycling plan, Section 4.R

  • Utility capacity certification and third-party electrical inspection before occupancy, Section 4.K

  • Section 4.L requires a Solar Energy Plan with projected annual electricity use and rooftop solar on 50 to 80 percent of unused roof space, and Section 4.K calls for LEED BD+C or equivalent efficiency design, but no plan states peak demand by phase.

  • Power generation treated as a separate use with its own approval, Section 4.K.2.

  • Substations screened, side or rear, lines of 34.5 kV or less buried, Section 4.M

  • Section 4.K.3 requires documentation from the electric service provider, an interconnection agreement, proof of adequate capacity, and payment of the full cost of any infrastructure upgrades, but does not require the required upgrades to be listed with their estimated cost or the tariff terms that assign that cost.

  • 20-ft buffer strip and berm next to residential districts and sensitive receptors, Section 4.P

  • Only substations screened

  • Plan accepted by the fire department, radio coverage, 24-hour contact signs; no annual update, Section 4.J

  • Materials stored must be described; no storage setbacks or containment, Section 4.O.1

  • Third-party electrical inspection before occupancy; no annual fire inspections, Section 4.K.4

  • Section 4.O.4 requires a traffic impact study in every case covering both construction and operation, but limits the study area to roadways and interchanges within one-half mile of the site rather than the nearest arterial or interchange the trucks will use.

  • Section 4.R requires a decommissioning plan, 110 percent financial security, and removal within six months after 12 months of non-operation, but does not require the agreement to be recorded and lets facilities with an ongoing purpose remain without a two-year lawful reuse limit.

  • Section 4.R requires updated decommissioning cost estimates after the first year of operation and every fifth year thereafter, and states that the financial security shall be updated every five years throughout the life of the project.

  • One as-built sound study after opening, Section 4.G.6

  • Fine of up to $1,000 plus costs and attorney fees, Enforcement.

  • Section 5.B requires the applicant to pay all application, escrow, subdivision and land development, and engineering review fees before any approval, Section 4.N.4 lets the Township retain an independent hydrologist at the applicant's sole cost, and Section 4.R has the Township engineer estimate decommissioning cost at the owner's expense during conditional use and land development review.

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the M-T district

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data