Scott Township

This restriction takes precedence for the map color while in effect.

Anti-Data Center Policies

Scott township’s enacted measure pauses covered data-center applications or development for 180 days, temporarily stopping affected projects without permanently banning them.

Rating from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Scott Township.

Incentives

Financial Incentive
2

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Scott Township
The supervisors adopted Resolution 5-20-26B, a 180-day moratorium on data center development.Scott Township, Columbia County — data-center resolution 5-20-26B

What this means

The measure pauses covered data-center applications or development for 180 day. That stops affected projects from moving ahead during the pause, even though it is not a permanent ban.

Timing

Ends
180-day; exact operative ending date not independently verified.

The supervisors adopted Resolution 5-20-26B, a 180-day moratorium on data center development.

Sources

pending · Scott Township
The supervisors released the unnumbered draft on August 19, 2026, scheduled a public hearing on it for October 6, 2026, and listed the data center ordinance on the agenda of their October 21, 2026 meeting, and no hearing outcome or adoption vote had been posted as of October 29, 2026.Scott Township, Columbia County — proposed data-center ordinance (None Adopted)

What this means

The proposal would impose setbacks from homes or other protected places, minimum site-size requirements and cooling and water-use rules. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements31
  • Barred within farmland preservation easements; agricultural security areas not addressed, §135-49.8(F)(1)

  • 500 feet from the tract boundary and 750 feet from developed property with a sensitive receptor, including residential uses, §135-49.8(E)(3)

  • 750 feet from schools, day care centers, and parks; hospitals not listed among sensitive receptors, §135-49.8(E)(3) and definitions

  • 65 feet including rooftop equipment, §135-49.8(E)(4)

  • Impervious surfaces 500 feet from stream banks, wetlands, and the 100-year floodplain; steep slopes not addressed, §135-49.8(F)(2)-(4)

  • 55 dBA daytime and 45 dBA nighttime and weekend at the tract boundary, §135-49.8(L)(B)(1)

  • Section 135-49.8(L)(3) requires a predictive model with the application and an as-built field test within 90 days of occupancy, measured as LAeq (10-minute) with ANSI S1.4 meters.

  • Vibration study required; no vibration perceptible beyond the tract boundary, §135-49.8 vibration section.

  • Section 135-49.8 water items 1, 3, and 5 bar wells and surface withdrawals for cooling, require trucked cooling water, and require a feasibility study with drawdown and recovery testing for any groundwater withdrawal.

  • Closed-loop non-evaporative cooling required and open-loop water cooling prohibited, §135-49.8 water section items 3 and 7

  • Section 135-49.8 water items 8 and 10 require an annual water consumption report and a drought contingency plan only when the Township declares a water shortage.

  • Section 135-49.8 water items 3 and 9 require DEP approval of cooling water disposal and a showing that domestic and process wastewater go to facilities approved by the Sewage Enforcement Officer or DEP.

  • Township stormwater ordinance and state permitting stated as applying, with long-term BMP maintenance, §135-49.8(E)(6)

  • Diesel generators must be EPA Tier 4 and meet state and federal air rules; no annual emissions testing or reports, §135-49.8(C)(A)-(B)

  • Decommissioning plan covers disposal or recycling of materials and disposal of batteries and refrigerants under state and federal law; recycling not required, §135-49.8(S)(1) and (4)

  • Utility documentation of service feasibility (230 kV) required for conditional use; no third-party electrical inspection before occupancy, §135-49.8(A)(2) and energy section item 1.

  • Certified energy usage plan required; renewables only encouraged and roofs must be solar ready, §135-49.8 energy section items 1, 4, and 6

  • On-site generation for normal operations is a separate principal use with its own approvals, §135-49.8(C)(D) and energy section item 2.

  • Substations screened by opaque landscaping or an 8-foot wall; placement and line burial not addressed, §135-49.8 energy section item 3

  • Known or anticipated impacts on electric rates or availability must be noted; cost of upgrades not assigned, §135-49.8 energy section item 1

  • 100-foot planted buffer next to residential districts and developed property with sensitive receptors, §135-49.8(H)(1)-(2).

  • Full-cutoff shielded fixtures and no light source visible from adjacent properties; light trespass at the property line not limited, §135-49.8 lighting section

  • Equipment within 500 feet of sensitive receptors, residential districts, or roads enclosed or screened; no 12-foot minimum or acoustic screening on all sides, §135-49.8(I)

  • Architectural elevations of all sides required; no visual impact study, §135-49.8 building design item 5

  • Emergency response plan reviewed by the fire department; no annual updates, radio coverage, or posted contacts, §135-49.8(Q)(1)(A)

  • Annual fire and life-safety inspections; no third-party electrical inspection before occupancy, §135-49.8(Q)(1)(E)

  • Security of at least 100 percent of cost, removal within 18 months after a start within one year of cessation; no 110 percent security or closure notice, §135-49.8(S)(2)-(3)

  • Annual reports on water and electricity use, §135-49.8 water item 10 and energy item 7

  • Noise noncompliance is a violation requiring correction and retesting; no specific penalties or revocation, §135-49.8(L)(B)(3)(c)

  • Township may require third-party noise testing, paid by the operator only if an exceedance is confirmed, §135-49.8(L)(B)(3)(d)

  • Applicant or developer submits the Developer's Agreement and site control documents with the application; end user not required, definitions G and N

Benefits & exceptionsHide benefits & exceptions1
  • Proposed approval pathway: Proposed: conditional use in the I Industrial and LI Light Industrial Districts