Schuylkill Township
Anti-Data Center Policies
Schuylkill Township’s enacted ordinance requires technical studies and utility checks, noise limits and testing, and setbacks from homes and other protected places. Data centers may still be approved, but these requirements add review and compliance costs.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Schuylkill TownshipThe standards in new Section 1698 were set by joint Ordinance No.Schuylkill Township, Schuylkill County — data-center ordinance (No. ESRP 2026-1)
What this means
The measure imposes technical studies and utility checks, noise limits and sound testing and setbacks from homes or other protected places. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements18
Conditional use before the governing body, Sec. 1105; no approval expiration
50 ft maximum height, Sec. 1698.A.6
Environmental impact study required, Sec. 1698.D.20
75 dBA day and 57 dBA night at property line, Sec. 1698.D.15
Sound study with application and as-built study six months after occupancy, Sec. 1698.D.15 and D.16
Water needs analysis; hydrogeologist water feasibility study for on-site wells, Sec. 1698.D.21
Cooling system must be described, Sec. 1698.D.13
Water quantity and frequency must be disclosed, Sec. 1698.D.21.a
Adequate wastewater treatment including cooling water shown, Sec. 1698.D.18
Known electric rate impacts must be noted, Sec. 1698.D.14
50 ft planted buffer yard, Sec. 1698.B
Security fence required; equipment screening not addressed, Sec. 1698.D.10
Emergency response plan reviewed by fire department, Sec. 1698.D.4
Annual fire safety inspections paid by operator, Sec. 1698.D.4
Section 1698.D.19 requires every applicant to prepare a traffic impact study under PennDOT Publication 282 identifying projected vehicular and truck traffic during construction and operation.
Arterial street access required, Sec. 1698.D.5
Section 201 defines a data center to include cryptocurrency mining, artificial intelligence uses, blockchain transaction processing, and server farms, and excludes computer equipment that is secondary and customarily incidental to another permitted use.
One as-built sound study after occupancy, Sec. 1698.D.16
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the new I Industrial District
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data