Sandycreek Township
Anti-Data Center Policies
Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.
Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Sandycreek Township.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
pending · Sandycreek TownshipThe township secretary provided the second revised draft (a new Section 430) by email on October 19, 2026, and said the Planning Commission hoped to review it that evening, with much discussion still to come before any hearing.Sandycreek Township, Venango County — proposed data-center ordinance (None Adopted)
What this means
The proposal would impose money set aside for eventual removal, noise limits and sound testing and limits on backup generators or on-site power. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements22
I District height and dimensional requirements stated as applying, § 430.3.A
Section 430.10.B requires any approval required by law before a material change, defined as a 20 percent or greater increase in planned maximum electric demand or cooling capacity, a materially different generation, battery, or water system, or a change likely to increase off-site sound or water impacts, with the Zoning Officer deciding whether an application is needed.
55 dBA day and 45 dBA night at sensitive properties; 60 and 55 dBA elsewhere, § 430.4.A
Only a 5 dBA penalty when the C-weighted level exceeds the A-weighted level by 20 dB; no dBC limit or study, § 430.4.C
Section 430.2 requires a sound assessment modeled at full planned operation with the application, and Section 430.4.B and D require a post-startup compliance test within 60 days at the highest reasonably expected load, measured as 15-minute Leq with a Type 1 meter under applicable ANSI methods.
Section 430.4.E limits routine generator testing to weekdays from 9:00 a.m. to 5:00 p.m. and to two hours per generator per month, except for additional testing required by law or a documented manufacturer safety requirement.
Hydrogeologic study for surface withdrawals or groundwater use of 50,000 gpd or more; no pump test or well restriction, § 430.6.B and C
Cooling method must be identified in the application, § 430.6.A
Annual water use summary; no use cap or drought plan, § 430.6.E
Wastewater and blowdown discharge and treatment must be identified, § 430.6.A
Decommissioning plan covers removal of computing, battery, and regulated materials; no recycling plan, § 430.9.A
Utility statement on demand and capacity before approval; no electrical inspection, § 430.5.A.
On-site generation must be described, § 430.5.B
Utility statement identifies system upgrades and cost responsibility; no payment requirement, § 430.5.A and C
Screening and buffer yards per Section 510 stated as applying; no width set, § 430.3.B
Emergency plan coordinated with the fire company, updated annually, with a 24-hour contact; no radio coverage requirement, § 430.7
Applicant must consult the fire company on site-specific training and equipment, § 430.7.B
Fuel storage and special hazards must be shown and disclosed, § 430.2 and § 430.7.A
Construction hours and routes set and road condition documented; road bond left to a separate process, § 430.4.F and § 430.8
Security of 110% of removal cost; removal schedule left to the approval, § 430.9.B and C
Estimate and security updated at least every five years; no first-year update, § 430.9.B
Annual compliance certification on demand, noise testing, and water use, § 430.10.A
Benefits & exceptionsHide benefits & exceptions1
Proposed approval pathway: Proposed: conditional use in the I Industrial District
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data