Pro-Data Center Policies

Salem Township allows phased data-center campuses by right in designated overlay areas, with expanded eligible land; yard, height, noise, and master-plan conditions still apply.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Salem Township
The overlay text is in Ordinance No. 1 of 2025, enacted on September 29, 2025, and the overlay map was enlarged by Ordinance No. 3 of 2025 and then by Ordinances No. 3 and No. 4 of 2026, which the Board of Supervisors enacted at a special meeting on October 27, 2026 and which news reports tie to the Salem 3 campus of 4-3 Glennbrook Group and the roughly 185-acre Salem 4 request of Moores 109 LLC, an expansion of more than 3,000 acres.Salem Township, Luzerne County — data-center ordinance (No. 1 Of 2025 (Map Amended By Ords. 3 And 4 Of 2026))

What this means

The measure allows phased data-center campuses by right within designated overlay land and expands the eligible development area. Yard, height, noise and master-plan conditions remain, but the approval route and expanded land availability provide a substantial overall benefit.

Restrictions & requirementsHide restrictions & requirements8
  • Sections 2 to 4 add the SDC-O Special Data Center Overlay District and map it on Exhibit B to the Official Zoning Map, and Section 511.1 lists data centers and data center campuses as permitted uses in the overlay, but the ordinance does not expressly exclude data centers from all other districts.

  • Permitted by right in the SDC-O, Section 511.1

  • Environmental Impact Statement for a campus master plan, Section 511.5.G

  • Data center campus defined and developed under one master plan, Sections 202 and 511.5.A

  • Phases under the master plan need no further approval for 5 years; major modifications need new review, Section 511.5.E and F

  • 70 dBA single limit on receiving properties outside the overlay, Section 511.5.J

  • Generator testing exempt from noise limits, Section 511.5.J

  • Stormwater plan referenced only to classify master plan changes, Section 511.5.F

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Permitted by right in the SDC-O Special Data Center Overlay District

Sources