Ridgway Township
Slightly Anti-Data Center Policies
Elk County: St. Marys allows data centers in certain districts only with conditional-use approval and substantial requirements; separate rules may constrain onsite power plants, not data centers themselves.
Rating and summary from Elk County as there are no scored current or future laws outside temporary restrictions for Ridgway Township.
Incentives
Financial Incentive2
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
pending · Ridgway TownshipThe draft amends Zoning Ordinance No. 116 under the municipal curative amendment the supervisors started with Resolution No. 5-2026 on April 28, 2026, and after an October 6, 2026 public meeting the supervisors listed the data center ordinance as new business for their October 20, 2026 meeting, with no adoption confirmed in a posted record.Ridgway Township, Elk County — proposed data-center ordinance (None Adopted)
What this means
The proposal would impose setbacks from homes or other protected places, minimum site-size requirements and cooling and water-use rules. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements31
Section 5(2) and (3) cap principal buildings and freestanding accessory uses at 35 feet including rooftop equipment, but the Industrial District height limit for other principal buildings is not in the amending text.
Phases evaluated together and expansions may require amended conditional use approval, Sections 3 and 21(4)
Single 45 dBA limit at the receiving property line, Section 9(5)
Section 9(5)(a) bars operating sound above the existing ambient background level at dwellings and Sensitive Receptors, or 45 dBA at the property line if more protective, but the background is not defined as L90 and no floor is stated below which the cap does not apply.
Low-frequency and tonal components studied; no dBC limit, Section 9(4)(c)
Section 9(6) requires a preliminary study with the conditional use application, a final design study at building permit, and a post-construction study within six months after occupancy, with Type 1 or Type 2 ANSI meters under Section 9(3), but the post-construction study is not required at full operating load.
Testing 9 a.m. to 3 p.m. weekdays, capped at 100 hours per generator per year, Section 11(4)-(5)
Vibration study showing none perceptible at or beyond the property line, Section 9(12).
Provider capacity letter or water feasibility study with safe yield; no pump tests or well limits, Section 12(4)-(5)
Closed-loop cooling required unless an alternative uses less water and energy, Section 12(3).
Water plan with projected demand and drought-response measures; no cap or reporting, Section 12(2)
Section 13 requires the applicant to identify cooling, blowdown, and other wastewater streams and to obtain approval from the sewage enforcement officer, municipal authority, and DEP, but the approvals are not required before the zoning permit.
Tier 4 diesel generators with annual testing records on request; no emissions reports, Section 11(1)-(2)
Plan for servers, batteries, and refrigerants, Section 16.
Provider confirms intent to serve and studies underway; no capacity confirmation or electrical inspection, Section 10(2)
Energy Use and Infrastructure Plan required; no on-site renewables, Section 10(1)
Primary generation is a separate principal use with separate zoning approval, Sections 1 and 10(4).
Electrical equipment enclosed or screened; substation placement and line burial not addressed, Section 7(6)
50-ft buffer next to homes, residential districts, and roads, Section 7(2)
Visible equipment enclosed or fully screened; no 12-ft or acoustic screening standard, Section 7(6)
Plan reviewed by fire and emergency services, radio coverage, 24-hour contact signs; no annual updates, Section 15
Generator areas set back 250 ft with secondary containment and spill prevention, Sections 5(5) and 11(7).
Annual fire safety inspections; no third-party electrical inspection, Section 15(8)
Section 4(3) requires a transportation impact study in every case covering construction traffic, deliveries, oversized vehicles, and haul routes, but no study area reaching the nearest arterial or interchange is stated.
Haul routes studied and Board may require a construction traffic plan; no work hours or road bond, Section 4
110% security and closure notice; removal begins within 1 year and ends within 18 months, Sections 19 and 20
Section 20(7) requires the decommissioning estimate to be updated within one year after commercial operation begins and at least every three years after, and requires the security to be increased within sixty days when an updated estimate exceeds it.
Post-construction sound study and records on request; no ongoing reports, Sections 9(6) and 21(2)
Failure to maintain security is a violation; no specific penalties, Section 20(7)(e)
Section 22 requires the applicant to reimburse reasonable and necessary professional review expenses to the extent authorized by the MPC, Section 9(7) lets the Township retain its own acoustic consultant on that basis, and Section 2 requires the conditional use application to be filed concurrently with the preliminary land development application.
Applicant public information meeting and project webpage kept through final approval, Section 18
Benefits & exceptionsHide benefits & exceptions1
Proposed approval pathway: Proposed: conditional use in the Industrial District
Sources
expired · Ridgway TownshipThe supervisors adopted Resolution No. 5-2026, a municipal curative amendment on data centers that gives the township 180 days to adopt a data center ordinance.Ridgway Township, Elk County — data-center resolution 5-2026
What this means
When in force, the measure started a protected period for local officials to fix gaps in their zoning rules. This can delay developers who need to challenge the old rules, but it does not by itself prohibit every data-center project.
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data