Richland Township
Anti-Data Center Policies
Pennsylvania requires data centers over 25 MW to obtain local approvals, secure power for their full demand, cover project-related grid costs, and meet added community, jobs, environmental, and reporting obligations. These rules may raise costs and delay or prevent covered projects, but do not ban them.
Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Richland Township.
current law · Richland TownshipLists Pennsylvania Richland Township Ordinance No. 313 as a non-codified ordinance of Richland Township, Bucks County, with the township providing the text as Ordinance 313.Pennsylvania Richland Township Ordinance No. 313 (2026)
People behind it
- Richland Township
Municipality responsible for proposing, adopting, and administering the measure
- Board of Supervisors of Richland Township, Bucks County, Pennsylvania
Responsible for holding the public hearing and considering enactment of the proposed ordinances
Restrictions & requirementsHide restrictions & requirements7
Data centers may be built, expanded, or operated only after obtaining required zoning and land-development approvals.
Data centers are allowed only in the zoning districts and use classifications specified by the ordinance, rather than throughout the township as an unrestricted use.
Applicants must submit additional plans and technical information addressing site design, utilities, traffic, stormwater, noise, lighting, emergency access, and environmental impacts.
Data centers must meet site-design requirements, including specified setbacks, screening or buffering, landscaping, lighting, building placement, and other dimensional standards.
Data-center operations must comply with standards governing noise, vibration, lighting, emissions, equipment, and backup generators.
Applicants or operators must address water, wastewater, electrical, stormwater, and other infrastructure demands through the approval process.
Applicants or operators must provide financial security or other assurances for obligations such as infrastructure work, site restoration, or decommissioning.
Benefits & exceptionsHide benefits & exceptions3
Data centers are expressly recognized as a zoning use and may be developed in the districts identified by the ordinance, subject to the required approvals and development standards.
Related facilities and infrastructure needed to operate a data center—including electrical equipment, backup power facilities, cooling systems, utility improvements, and similar accessory facilities—are allowed as part of the data-center use, subject to the ordinance’s limits.
An approved data-center use may continue and may be enlarged or modified under the ordinance, provided it complies with applicable site, dimensional, utility, and other requirements.