Reading Township

Anti-Data Center Policies

Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.

Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Reading Township.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

pending · Reading Township
The draft is an unnumbered amendment to the Zoning Ordinance with several standards still shown as bracketed options, and the Supervisors' October 19, 2026 agenda listed it for consideration and the setting of a public hearing date, but no hearing notice had been posted as of October 28, 2026.Reading Township, Adams County — proposed data-center ordinance (None Adopted)

What this means

The proposal would impose cooling and water-use rules, noise limits and sound testing and setbacks from homes or other protected places. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements36
  • Special exception; approval expires only if milestones are missed or the use is not substantially completed within four years, § 27-13__ F.8

  • Minimum lot area of 25 acres, with the Planning Commission proposing 10 acres, § 27-13__ D.1

  • 35-ft maximum building height; screened rooftop equipment may exceed the height limit with no 10-ft cap, § 27-13__ D.4 and E.2.b(2)

  • Riparian forest buffer of at least 100 ft on each side, widened on slopes over 10% and by 25 ft at wetlands and vernal ponds, § 27-13__ E.8.c

  • Sound may not exceed baseline ambient levels at lots with sensitive receptors; no separate numeric day and night dBA limits, § 27-13__ F.2.a

  • Section 27-13__ F.2.a and b bar any increase over baseline ambient at sensitive receptor lots and more than 10 percent over baseline at other lots, with the baseline set by a study using ANSI S1.4-2014 meters in AM and PM periods on all days (B.6), but the baseline is not defined as L90 and no floor is set below which the cap does not apply.

  • Noise and vibration study must establish dB(C) and octave band baselines; no numeric dBC limit, § 27-13__ B.6.b

  • Noise study with the application and as-built study 1 to 12 months after the first certificate of occupancy; no study at building permit, § 27-13__ B.6-B.7

  • Generator testing limited to 9 a.m. to 3 p.m. Monday through Friday and capped at 100 hours per year, § 27-13__ F.4.i.iii

  • Vibration may not be measurable beyond the property line, with a sealed noise and vibration assessment study, § 27-13__ B.6 and F.2.g.

  • Dry coolers with closed-loop circulation required unless an alternative uses less water and energy; evaporative cooling not expressly restricted, § 27-13__ F.3.a

  • Projected water needs disclosed and a drought response plan required; no daily cap or ongoing usage reporting, § 27-13__ B.4.f and F.3.e

  • Section 27-13__ F.3.f requires the applicant to demonstrate that disposal of domestic, cooling, and industrial wastewater has been provided and approved by the Sewage Enforcement Officer or DEP, with an analysis of the public or private disposal route and certification from the municipal authority (F.3.g), as part of the special exception showing that precedes the zoning permit.

  • Stormwater plan must comply with the Stormwater Management Ordinance, § 27-13__ B.2.f and C.2

  • Generators must meet EPA Tier 4, with annual testing and reports to the Township, § 27-13__ F.4.i.i-ii

  • Thermal Impact Mitigation Plan including evaluation of waste heat reuse, § 27-13__ B.13.

  • Electronic waste plan for removal and recycling of servers, batteries and hazardous materials, and refrigerant disposal at decommissioning, § 27-13__ F.6.a and F.7.d.

  • Utility approval of service at land development and capacity verification and third-party electrical inspection before occupancy; capacity is not confirmed before approval, § 27-13__ C.3 and F.4.c

  • Solar Energy Plan with projected annual consumption and on-site solar offsetting at least 25% of annual use, § 27-13__ F.4.d.

  • Energy generation systems defined and excluded from accessory uses, and on-site generation must meet interconnection standards; no separate approval or setbacks, § 27-13__ A and F.4.b

  • Substations at the side or rear and screened by 8-ft walls and landscaping where visible from arterial or collector roads; on-site lines of 34.5 kV and below buried, § 27-13__ F.4.e-g

  • Buffer yards of 100 to 200 ft by building footprint and 200 ft next to sensitive receptors, including residences, § 27-13__ E.2.c(1).

  • Fully shielded fixtures with a 0.1 footcandle limit on adjacent properties; some light may cross the line, § 27-13__ E.4

  • Screens built of materials compatible with the principal building and LEED design required; no facade standards, § 27-13__ E.2.b and E.7.c

  • Ground equipment enclosed or behind a visually solid screen and rooftop equipment screened on all four sides; no 12-ft or acoustic screening standard, § 27-13__ E.2.b

  • Scaled exterior building plan and line-of-sight study for service area screening; no visual impact study from roads or historic sites, § 27-13__ B.11 and E.2.a

  • Emergency Response Plan reviewed by the fire department, in-building radio coverage and 24-hour contact signs; no annual plan updates, § 27-13__ F.5.a-c

  • Hazardous materials storage must meet DEP standards with spill containment; no storage setbacks, § 27-13__ F.6.b

  • Section 27-13__ F.4.c.v requires the emergency response plan to provide for annual fire safety inspections by a qualified professional, and F.5.a.vi requires a third-party final electrical inspection, but no report to the municipal fire official and no correction deadline are required.

  • Section 27-13__ B.5 requires a traffic impact study with every application after a pre-study consultation to identify the roads and intersections to be studied, but the study is not required to cover construction traffic or to reach the nearest arterial or interchange.

  • Pre- and post-construction road condition surveys and road repair at the applicant's cost; no work hours, haul routes or bond, § 27-13__ E.6

  • Notice of cessation and performance security set by a professional, but removal may take up to 18 months after a one-year start; no 110% amount, § 27-13__ F.7

  • Decommissioning cost estimate updated every five years; no update after the first year, § 27-13__ F.7.f

  • As-built noise study after opening and annual backup power operation reports; no ongoing noise, water or power use reports, § 27-13__ B.7 and F.4.i.iii(d)

  • Alternative cooling reviewed by an engineer engaged by the Township; review cost not assigned to the applicant, § 27-13__ F.3.a

  • Applicant must name all owners, operators and managers; end user not required, § 27-13__ B.1.d-f

Benefits & exceptionsHide benefits & exceptions1
  • Proposed approval pathway: Proposed: special exception in the Commercial/Industrial District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data