City of Reading
This restriction takes precedence for the map color while in effect.
Anti-Data Center Policies
Reading has enacted a temporary 180-day pause on considering data-center zoning applications and related requests while it prepares new rules, delaying development but not permanently banning it.
Rating from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for City of Reading.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · City of ReadingThis temporary measure establishes a six-month pause on data-center development or applications in the City of Reading while the city considers permanent zoning controls.Reading City Data Center Moratorium (2026)
What this means
The measure creates a 180-day pause on considering permits or other zoning requests for data centers and similar uses while the City prepares new rules. It is not a permanent ban, but the temporary halt would substantially delay development during that period (180-day period).
Timing
- Ends
- 180 days after adoption
The moratorium applies to zoning permit applications, zoning approvals, and landowner curative amendments for data centers, data center accessory uses, or similar uses. During the 180-day period, the City is not required to consider those applications. The City Council and Planning Commission must initiate and enact a curative amendment within that period.
People behind it
- City Engineer
Drafted and sponsored or referred the resolution appointing the Sewage Enforcement Officer and the ordinance opening Kings Way and Queens Court.
- Public Works Director
Co-sponsored or co-referred the Sewage Enforcement Officer resolution and sponsored or referred the Cornerstone sewage planning resolution.
- Managing Director
Sponsored or referred the Cornerstone sewage planning resolution and the Fair Housing Outreach and Education Coordinator salary ordinance.
Show 23 more peopleShow fewer people
- Finance Department
Drafted and proposed the Byrne Justice Assistance Grant resolution.
- City Arborist
Proposed the change order expanding the City-Wide Tree Master Plan.
- Grant Office
Co-proposed the change order expanding the City-Wide Tree Master Plan.
- Chief of Police
Recommended the Axon body-camera and conducted-electrical-weapons contract payment and the Motorola Flex system maintenance contract.
- Planning Commission
Sponsored or referred the ordinance opening Kings Way and Queens Court.
- Code and License Appeals Board
Sponsored or referred the ordinance adding nuisance-abatement appeals and extending appeal-decision deadlines.
- Board Solicitor
Co-sponsored or co-referred the Code and License Appeals Board appeals ordinance.
- Public Art Review Committee
Sponsored or referred the banner-installation-fee ordinance.
- Police and Public Works Departments
Proposed and administered the review process for existing no-parking zones under the no-parking ordinance.
- Council President
Sponsored or referred the ordinance requiring no-parking zones, including loading zones, to be approved by ordinance.
- City Solicitor’s Office
Drafted the Fair Housing Outreach and Education Coordinator salary ordinance.
- Law Department
Drafted the ordinance allowing director salary ranges to be adjusted by resolution.
- Community Development Department
Sponsored or referred the ordinance removing a portion of 730 North 3rd Street from the Centre Park Historic District.
- Historical Solicitor
Drafted the Centre Park Historic District boundary ordinance.
- Council Solicitor
Co-drafted the ordinances restricting Penn Street parking, extending the parking moratorium, and amending the Agency Fund budget, and co-drafted the data-center curative-amendment resolution.
- City Clerk
Co-drafted the ordinance restricting Penn Street parking.
- Councilor Miller
Sponsored or referred the ordinance restricting parking on the south side of the 700 block of Penn Street.
- Councilor Baker
Co-sponsored or co-referred the ordinance restricting parking on the south side of the 700 block of Penn Street.
- Councilor Baez
Drafted and sponsored or referred the data-center curative-amendment resolution; also drafted and referred the parking-moratorium ordinance.
- Acting Finance Director
Drafted and sponsored or referred the ordinance amending the 2026 Agency Fund budget.
- Deputy City Clerk
Drafted the resolutions reappointing members to the Code and License Appeals Board and Environmental Advisory Council.
- Nominations & Appointments Committee
Sponsored or referred the resolutions reappointing Barbara Waller and Stephan Thompson.
- Mayor
Sponsored or referred the resolutions confirming Joseph Famiglietti as Finance Director and establishing the Finance Director salary range.
Restrictions & requirementsHide restrictions & requirements29
Resolution 105-2026 declares portions of the zoning ordinance invalid because they do not regulate data centers and establishes a 180-day curative-amendment period.
During the 180-day curative-amendment period, the City is not required to consider zoning permits, zoning approvals, or landowner curative amendments for data centers, data-center accessory uses, or similar uses.
The review draft would allow data centers only in the H-M Heavy Manufacturing District and only through conditional-use approval by City Council.
The review draft would require a minimum lot size of five acres for a standard data center and eight acres for a major data center or data-center campus, with a minimum 200-foot lot width.
The review draft would limit building coverage to 50%, impervious coverage to 70%, and require at least 15% landscaped open space.
The review draft would impose minimum setbacks of 75 feet from public street rights-of-way and 50 feet from other lot lines.
The review draft would require principal buildings to be at least 200 feet from sensitive-receptor lot lines or residential zoning boundaries, and generators, battery systems, substations, fuel storage, chemicals, and exterior cooling equipment to be at least 300 feet away.
The review draft would generally limit principal building height to 50 feet; a height of up to 70 feet would require at least 15 acres, additional setbacks, screened rooftop equipment, and Fire Chief confirmation of adequate emergency access and fire suppression.
The review draft would require a data-center campus to submit a ten-year master plan covering anticipated phases, buildings, power, cooling, utilities, access, emergency facilities, buffers, and open space, and would aggregate affiliated parcels and shared infrastructure to prevent segmentation.
Before applying for conditional use approval for a major data center or campus, the review draft would require a pre-application conference and a public information meeting at least 30 days before filing, with notice to nearby property owners.
The review draft would require an environmental and community impact assessment addressing impacts including water and sewer capacity, electric-grid capacity, air emissions, noise, flooding, stormwater, heat, transportation, emergency services, and cumulative effects.
The review draft would prohibit conditional-use approval when a significant impact identified by the assessment remains unmitigated or proposed mitigation is not technically and financially enforceable.
The review draft would require certifications from the Reading Area Water Authority and the City wastewater utility confirming available water, fire-flow, sewer, treatment, drought, and discharge capacity, with the applicant paying for required project-attributable upgrades.
The review draft would require public water and sanitary sewer service and prohibit routine groundwater or surface-water withdrawals for data-center operations.
The review draft would prohibit once-through cooling and open-circuit evaporative cooling, and would generally require closed-loop or other low-water cooling systems.
The review draft would prohibit discharging cooling water, process water, chemicals, or heat to storm sewers, groundwater, or surface water; sanitary-sewer discharges would require written wastewater-utility approval.
The review draft would prohibit data centers and related equipment on Fritz Island or parcels used for wastewater, drinking-water, flood-control, or other specified critical public infrastructure.
The review draft would impose additional setbacks from the Fritz Island wastewater treatment plant, waterways, and floodplains, including a prohibition on principal buildings in the one-percent-annual-chance floodplain.
The review draft would cap normal operating noise at 55 dBA Leq at sensitive receptors, subject to specified ambient limits, and at 65 dBA Leq at other lot lines, with additional tonal and low-frequency limits.
The review draft would require preconstruction, interim, as-built, and periodic post-occupancy acoustic studies and monitoring, all paid for by the applicant or operator.
The review draft would restrict routine generator testing to Monday through Friday from 9:00 a.m. to 5:00 p.m., generally limit simultaneous testing to 25% of generators, and prohibit normal-operation generator use unless separately approved.
The review draft would require emergency-response, hazardous-materials, spill-prevention, air-emissions, and battery-energy-storage plans, and would require the applicant or operator to fund project-specific first-responder training, drills, and specialized equipment.
The review draft would require a decommissioning and site-restoration plan and financial security equal to 125% of independently reviewed decommissioning and restoration costs before the first building permit.
Under the review draft, abandonment would occur after 12 consecutive months without principal data-center operations, generally requiring decommissioning to begin promptly and finish within 12 months.
The review draft would require annual compliance reports, seven-year record retention, City inspection rights, and written successor agreements when ownership or operation changes.
The review draft would require applicants to fund reasonable City professional-review costs and maintain an escrow deposit for independent engineering, acoustic, environmental, utility, fire-protection, and related reviews.
The review draft would require an impact-mitigation plan and agreement addressing project-related utility, transportation, monitoring, environmental, emergency-response, landscaping, and decommissioning obligations.
A data center receiving discretionary City assistance would have to enter into a City Council-approved Community Benefits Agreement before the assistance is approved or conveyed.
The review draft would require amended conditional-use approval for specified expansions or changes, including increases of more than 5% in floor area or more than 10% in electrical demand, water use, generator capacity, fuel storage, battery-storage capacity, or impervious coverage.
Benefits & exceptionsHide benefits & exceptions11
Creates a legal approval pathway for data centers by allowing Data Centers, Major Data Centers, and Data Center Campuses in the H-M Heavy Manufacturing District through conditional-use approval by City Council.
Allows data-center accessory equipment—including generators, battery energy-storage systems, substations, transformers, cooling systems, fuel storage, and telecommunications infrastructure—to be treated as accessory to the data center, subject to applicable safety and regulatory requirements.
Permits existing computer, server, telecommunications, and network equipment serving another lawful use to remain outside the data-center classification when it is secondary and customarily incidental to that use.
Allows data centers to be created through new construction, adaptive reuse or conversion of existing buildings, expansion, intensification, material modification, or phased campus development, provided the applicable standards are met.
Allows a principal data-center building to reach up to 70 feet in height, instead of the standard 50-foot maximum, if the site contains at least 15 acres, additional setbacks are provided, rooftop equipment is screened, and the Fire Chief confirms adequate emergency access and fire-suppression capability.
Allows City Council to approve a closed-circuit evaporative or hybrid cooling component when non-evaporative cooling is not reasonably feasible, water capacity is certified, reclaimed or nonpotable water is considered, enforceable water controls are imposed, and existing customers and wastewater capacity are protected.
Allows minor post-approval modifications to be approved by the Zoning Administrator without an amended conditional-use approval when they do not exceed specified expansion thresholds, reduce compliance, or materially increase impacts.
Permits emergency-generator operation during an actual utility outage or emergency to exceed the ordinary noise limits for the time reasonably necessary to protect life, safety, equipment, or data, subject to restoration of compliance after power returns.
Makes data-center projects eligible for discretionary City economic-development assistance, including City-owned land, grants, loans, loan guarantees, tax abatements, utility subsidies, fee waivers, and other financial or in-kind assistance, if the project enters into a City Council-approved Community Benefits Agreement.
Provides that broader community benefits connected to discretionary City assistance must be handled through a separate Community Benefits Agreement and may not be imposed as an unsupported zoning exaction.
Allows a data center to use underground utility, fiber-optic, telecommunications, and electrical distribution lines to the maximum extent practicable, while allowing aboveground installation when required by the utility or deemed more feasible or safer by the City Engineer.
Sources
current law · City of ReadingPauses consideration of data center-related zoning applications for 180 days while the City develops zoning rules for data centers and similar uses.Reading Ohio temporary data center moratorium (2026)
What this means
The measure would pause consideration of data-center-related zoning applications for 180 days while the City prepares new rules, creating a substantial short-term barrier to building or expanding data centers (applications would not be considered during the 180-day period). It is not a permanent ban and does not set ongoing operating restrictions, so its effect is severe but temporary.
Timing
- Ends
- 180 days from the date of the Resolution
During that period, the City is not required to consider zoning applications or approvals related to data centers, accessory uses, or similar uses. The City Council and Planning Commission are to initiate and enact a curative amendment within the same 180-day period.
People behind it
- City Engineer
Drafted and sponsored/referred the sewage enforcement officer resolution and Bill 52-2026; also co-sponsored the Penn Street parking ordinance with the Public Works Director. The agenda identifies the City Engineer as sponsor.
- Chief of Police
Recommended approval of the Axon body-camera and related equipment payment and the Motorola Flex system maintenance contract. The agenda memo recommends the Axon payment.
- Kyle Zeiber
As Public Works Director, co-sponsored the sewage planning module resolution with the Managing Director and co-sponsored the Penn Street parking ordinance with the City Engineer. The sewage module memo names the Public Works Director.
Show 22 more peopleShow fewer people
- Jack Gombach
As Managing Director, co-sponsored the sewage planning module resolution and recommended the youth-violence grant application and the Fair Housing coordinator salary measure. The sewage module memo identifies the co-sponsors.
- Finance Department
Prepared the youth-violence grant resolution and recommended approval of the grant application. The grant memo identifies the Finance Department.
- Lester Kissinger Jr.
As City Arborist, prepared the tree-plan change-order request. The memo identifies him as preparer.
- Grant Office
Recommended approval of the change order expanding the City-Wide Tree Master Plan. The memo identifies the Grant Office’s recommendation.
- City Clerk
Drafted Bills 53-2026, 54-2026, and 55-2026, as well as the new Penn Street parking ordinance. The agenda identifies the City Clerk as drafter.
- Code and License Appeals Board
Sponsored/referred Bill 53-2026, which adds nuisance-abatement appeals and extends the deadline for appeal decisions. The agenda names the Board as sponsor.
- Solicitor to the Code and License Appeals Board
Co-sponsored/referred Bill 53-2026 with the Code and License Appeals Board. The agenda identifies the Board and its solicitor.
- Public Art Review Committee
Sponsored/referred Bill 54-2026, establishing a banner-installation fee for qualifying organizations outside Reading. The agenda identifies the Committee as sponsor.
- Council President Reed
Sponsored/referred Bill 55-2026 concerning Council approval of no-parking zones. The agenda identifies the Council President as sponsor.
- City Solicitor’s Office
Drafted Bill 56-2026 concerning the Fair Housing Outreach and Education Coordinator’s salary. The agenda identifies the drafting office.
- Law Department
Drafted Bill 57-2026, allowing director salary ranges to be adjusted by resolution. The agenda identifies the Law Department as drafter.
- Community Development Department
Sponsored/referred Bill 58-2026 concerning removal of a portion of 730 North 3rd Street from the Centre Park Historic District. The agenda identifies the Department as sponsor.
- Historical Solicitor
Drafted Bill 58-2026 concerning the Centre Park Historic District boundary. The agenda identifies the drafter.
- Council Solicitor
Co-drafted the temporary parking-moratorium ordinance and the data-center curative-amendment resolution. The agenda identifies the Council Solicitor as a drafter.
- Councilor Miller
Co-sponsored/referred the temporary parking-moratorium ordinance with Councilor Baker. The agenda names both sponsors.
- Councilor Baker
Co-sponsored/referred the temporary parking-moratorium ordinance with Councilor Miller. The agenda names both sponsors.
- Acting Finance Director
Drafted and sponsored/referred the ordinance amending the 2026 Agency Fund budget for the purchase of 2040 Centre Avenue. The agenda identifies the Acting Finance Director.
- Councilor Baez
Drafted and referred the data-center curative-amendment resolution. The resolution identifies Councilor Baez as drafter and referrer.
- Councilor Ventura
Co-sponsored/referred the Penn Street parking ordinance with Councilor Baker. The meeting record identifies the motion sponsors.
- Deputy City Clerk
Drafted the resolutions reappointing members to the Code and License Appeals Board and Environmental Advisory Council. The resolutions identify the Deputy City Clerk as drafter.
- Nominations & Appointments Committee
Sponsored/referred the resolutions reappointing Barbara Waller and Stephan Thompson. The resolutions identify the Committee.
- Mayor
Sponsored/referred the resolutions confirming Joseph Famiglietti as Finance Director and amending the Finance Director salary range. The agenda identifies the Mayor as sponsor.
Restrictions & requirementsHide restrictions & requirements1
For 180 days from adoption, the City is not required to consider zoning permit applications, zoning approvals, or landowner curative amendments for data centers, data-center accessory uses, or similar uses. During the aforementioned 180-day period, the City Council and Planning Commission must also initiate and enact a curative zoning amendment addressing these uses.
Sources
current law · City of ReadingPauses data center-related zoning applications for 180 days while Reading updates its zoning rules.Reading City Council Resolution 105-2026 (curative-amendment resolution under MPC § 609.2)
What this means
The measure would pause consideration of data-center applications for 180 days while the city writes zoning rules, creating a major but temporary barrier to building or expanding facilities. It is not a permanent ban, but the rules adopted afterward could add further limits. Applications would not be considered during the 180-day period.
Timing
- Ends
- 180 days after adoption
The temporary bar applies to data-center-related applications during the curative-amendment period; applications may be considered once a zoning amendment is enacted. The sources do not state an extension condition. 180-day period
People behind it
- Jaime Baez
Proposed a zoning amendment regulating data centers and worked with the city solicitor on a resolution to initiate the curative-amendment process.
- Michael Gombar
City solicitor who proposed the curative-amendment approach and assisted with the related resolution.
Restrictions & requirementsHide restrictions & requirements3
The adopted curative-amendment resolution creates a 180-day period during which Reading does not have to consider zoning-permit applications for data-center-related uses or development (applications would not be entertained during the 180 days).
A draft zoning amendment would allow data centers only in the heavy manufacturing district and only as a conditional use requiring City Council consideration at an evidentiary hearing (the draft allows data centers only in the HM district).
The draft zoning amendment would require a process involving reviews and studies for data-center proposals (requires a process for various reviews and studies).
Sources
pending · Reading CityCity Council's Committee of the Whole reviewed the revised draft (bill number not yet assigned) on October 5, 2026, when the agenda listed it as scheduled for county planning review the following week, and the work group's timeline calls for two county review periods before the ordinance is introduced and a public hearing is held.Reading City, Berks County — proposed data-center ordinance (None Adopted)
What this means
The proposal would impose cooling and water-use rules, noise limits and sound testing and setbacks from homes or other protected places. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements31
Same 200-ft and 300-ft setbacks from schools, day care, hospitals, and parks, § 600-1110.C(1) and § 600-2202
50 ft, up to 60 ft on 20 acres; roof equipment screened but no height limit, § 600-1110.C(1) and C(8)
500 ft from perennial streams, wetlands, and floodplain, 1,000 ft from named waterways, steep slopes barred, § 600-1110.F(3) to (5) and .J(3)
Section 600-1110.U(1) requires an amended conditional use for more than 5 percent added floor area, more than 10 percent added electrical demand, generator, fuel, or BESS capacity, a cooling change that adds water use, added normal-operation generation, or another parcel, and U(2) lets the Zoning Administrator approve minor modifications below those thresholds that do not reduce compliance.
Section 600-1110.K(5) sets 50 dBA on weekdays from 8:00 a.m. to 5:00 p.m. and 40 dBA at all other times at the property line, and K(3) requires ANSI S1.4 Class 1 instruments and ANSI/ASA S12.9 procedures with field calibration.
Section 600-1110.K(6) caps project sound at the lowest valid hourly L90 plus 5 dBA, measured under the K(3) method, but the more restrictive of this cap and the fixed limit always governs, so no floor is set below which the cap does not apply.
dBC and octave-band low-frequency analysis required; no numeric dBC limit, § 600-1110.K(2) and K(7)
Section 600-1110.K(2) and K(13)(a) require a predictive study with the application modeled at full operational load, and K(13)(b) to (e) require as-built studies at interim and full representative load within 3 months of occupancy and annually for 5 years, all under the ANSI methods in K(3).
RAWA written capacity certification; no well limits or pump tests, § 600-1110.I(4)
Closed-loop required unless Council permits otherwise; water-consuming systems excluded from closed-loop, § 600-1110.I(2) and § 600-2202.
Section 600-1110.I(6) requires continuously recording meters for water supplied, used for cooling, reused, and discharged, Section 600-1110.Q(1) requires an annual certified report of water use to the City, and I(6) requires a drought and emergency curtailment plan under the Reading Area Water Authority requirements and all mandatory restrictions.
Section 600-1110.I(3) and I(5) require a wastewater flow report, bar cooling discharge to storm sewers and waters, and require sewage planning modules to be submitted for approval as part of the conditional use or land development application, but the DEP or sewer authority approval is not required to be in hand before the zoning permit.
Generators must meet the most stringent state and federal standards; no Tier 4, § 600-1110.L(2)
Thermal impact plan, with waste heat reuse feasibility for major data centers, § 600-1110.N(1) and N(2).
Electronic waste plan for servers, batteries, and cooling equipment, § 600-1110.O(1).
Utility confirmation letter with the application; no third-party electrical inspection, § 600-1110.H(2).
Energy management plan; on-site alternative energy optional, § 600-1110.H(1) and H(7)
Normal-operation generation is a separate use needing its own approval, § 600-2202 and § 600-1110.U(1).
Substations screened and lines underground; no substation placement rule, § 600-1110.E(5) and .H(8)
Section 600-1110.H(1) requires the Electric Utility Impact Plan to state the proposed utility upgrades and point of interconnection, and H(4) requires the applicant to fund them, but their estimated cost, the tariff terms that assign the cost, and an executed service agreement before the zoning permit are not required.
40-ft buffer, 60 ft for major data centers, § 600-1110.C(1)
Equipment screened from streets and sensitive receptors, § 600-1110.E(5)
Storage setbacks of 200 ft to 1,000 ft with 110% containment, § 600-1110.C(1), .J(2), .J(3), and .J(7).
Annual fire safety inspections; no third-party electrical inspection, § 600-1110.M(5)
Section 600-1110.G(1) and G(3) require a Traffic Impact Study with every conditional use application, scoped by the City Engineer, that evaluates construction traffic, delivery routes, and pavement and bridge constraints, which carries the study along the truck routes.
Haul routes and work hours in a plan; no road damage bond, § 600-1110.G(4)
125% security, but 12-month removal, § 600-1110.P(2) and P(3)
Section 600-2202 defines a data center to include cryptocurrency mining, blockchain processing, and artificial intelligence computing, and excludes equipment secondary and customarily incidental to another use, but the exclusion sets no stated size or power limit.
Annual reports on power, water, and noise, § 600-1110.Q(1)
Section 600-1110.H(6) and K(10)(c) revoke the use and occupancy permit after three energy supply or noise violations in a year, and Section 600-1110.V(1) allows enforcement under the Municipalities Planning Code generally, but no notice and hearing precede revocation and Sections 616.1 and 617.2 are not cited.
Section 600-1110.R(3) requires the applicant to reimburse the City's reasonable professional review costs through escrow, and Section 600-1110.T(3) establishes that escrow for both the conditional use application and the land development plan application.
Benefits & exceptionsHide benefits & exceptions1
Proposed approval pathway: Proposed: conditional use in the M-C and H-M manufacturing districts
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data