Radnor Township
Anti-Data Center Policies
Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.
Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Radnor Township.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
pending · Radnor TownshipThe Board of Commissioners took up the ordinance for introduction on October 26, 2026 and advanced it for comment from the public and township boards, according to the agenda and The Philadelphia Inquirer, and no hearing date has been set and no data center is proposed in the township.Radnor Township, Delaware County — proposed data-center ordinance (None Adopted; Ordinance 2026-24 Introduced)
What this means
The proposal would impose cooling and water-use rules, noise limits and sound testing and setbacks from homes or other protected places. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements32
Conditional use only in the PLO Planned Laboratory-Office District, § 280-63.B(5)(a)
PLO district area requirements apply, including the 10-acre minimum lot, § 280-63.B(5)(c) and § 280-64A
Data Center Technology Area capped at 5% of building floor area and PLO 30% building area limit apply; no footprint or megawatt cap, § 280-63.B(5)(c)-(e)
200 ft front, side, and rear setbacks to any structure in the R-1 through R-6 and PA districts, § 280-63.B(5)(c)
Water study must map surface waters, wetlands, and threatened or endangered species habitats; no riparian buffer, § 280-63.B(5)(j)[3][b]
Testing required after expansion, but no new approval or phasing plan, § 280-63.B(5)(h)[1]
Single limit of 3 dBA over the seven-day baseline Leq; no separate day and night limits, § 280-63.B(5)(h)[2][a]
Section 280-63.B(5)(h)[2][a] bars the post-construction seven-day Leq from exceeding the seven-day baseline Leq by more than 3 dBA at any monitoring location, with continuous monitoring by a stated method, but the baseline is a Leq rather than an L90 and no floor sets a level below which the cap does not apply.
Low-frequency and infrasound testing from 1 Hz required; no dBC limit, § 280-63.B(5)(f)[1][e] and (h)[2]
Ambient and modeling studies in the conditional use process and post-construction testing; no study at building permit, § 280-63.B(5)(f) and (h)
Section 280-63.B(5)(g) bars vibration discernible without instruments at the property line and any vibration over 0.002 g peak measured at or beyond the property line with seismic or electronic vibration measuring equipment, and Section 280-63.B(5)(g)[1] and [2] require a vibration study and vibration modeling with the application.
Any withdrawal of groundwater or surface water barred and public utility service required, § 280-63.B(5)(j)[1]-[2]
Only air-based or closed-loop cooling that cannot release water or vapor, § 280-63.B(5)(r)
Projected water needs disclosed; no use cap, reporting, or drought plan, § 280-63.B(5)(j)[3][a] and § 280-135.G(2)(p)
Section 280-63.B(5)(j)[1] to [3] require will-serve letters from each public sanitary sewer provider with the application and a Water and Wastewater Feasibility Study describing wastewater disposal methods that must be approved before conditional use approval, and Section 280-63.B(5)(r) requires the coolant disposal method to be shown with the application.
Tier 4 Final generators with SCR and DPF required; no annual emissions testing or reports, § 280-63.B(5)(s)[1][c] and (x)[1]
Thermal Impact Mitigation Plan including waste heat reuse evaluation, § 280-63.B(5)(s)[2].
Electric will-serve letter and approved Power Feasibility Study before approval; no electrical inspection before occupancy, § 280-63.B(5)(j)[1] and [4].
Section 280-63.B(5)(v) requires solar on 100 percent of unshaded roof area, all parking and loading areas, and 40 percent of facing facades, but the energy-use plan in Section 280-135.G(2)(l) states only average and peak demand and needed infrastructure, not peak demand by phase, annual use, or design efficiency.
On-site generation addressed with a Safety Plan and behind-the-meter design; not a separate use, § 280-63.B(5)(w)
Applicant provides at its own expense all utility improvements the studies identify, before zoning approval, § 280-63.B(5)(j)[5].
PLO 50 ft buffer planting strip next to residential districts applies, § 280-63.B(5)(n) and § 280-65.1B
Equipment located, screened, or enclosed to minimize noise and visual impacts; no height standard, § 280-135.G(2)(o)
Emergency Response Plan reviewed by the Township Engineer, with fire company help optional, and posted emergency contact; no annual updates or radio coverage, § 280-63.B(5)(l) and (q)
Plan must ensure first responders receive system-specific training, § 280-63.B(5)(l)[1][a][v]
Hazardous material handling and disposal addressed; no storage setbacks or containment, § 280-63.B(5)(w)[3] and (y)
Annual fire safety inspections, § 280-63.B(5)(l)[1][a][vi]
Second means of emergency ingress and egress required; no road class standard, § 280-63.B(5)(l)[1][a][iv]
Construction hours set; no haul routes or road bond, § 280-63.B(5)(u)
MPC Section 509 security posted only when the use is discontinued, 3 months notice, removal within 12 months, § 280-63.B(5)(aa)
Annual third-party certified compliance report and real-time data to the Township Engineer, § 280-63.B(5)(h)[3][b]
Section 280-63.B(5)(bb) allows the Township to retain independent acoustical, engineering, planning, legal, environmental, or other consultants to review any application, study, mitigation plan, or monitoring report, and requires the applicant or operator to reimburse the Township for that review.
Benefits & exceptionsHide benefits & exceptions1
Proposed approval pathway: Proposed: conditional use in the PLO Planned Laboratory-Office District