Quincy Township

Anti-Data Center Policies

Quincy Township’s enacted ordinance sets setbacks, minimum site sizes, and cooling and water-use rules for data centers, substantially limiting suitable sites and project designs while retaining an approval route.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Quincy Township
The Board of Supervisors adopted Ordinance No. 176 unanimously on July 16, 2026, after a public hearing the same day, according to the township's posted minutes and the signed ordinance.Quincy Township, Franklin County — data-center ordinance (No. 176)

What this means

The measure imposes setbacks from homes or other protected places, minimum site-size requirements and cooling and water-use rules. The limits sharply reduce usable sites or workable project designs, making development substantially harder despite an available approval route.

Restrictions & requirementsHide restrictions & requirements27
  • Approval type set by Sections 1200 and 1201 of the base zoning ordinance, which could not be read; no lapse provision, Section 3

  • Rooftop equipment must meet the prevailing Township height limit and be screened, § 1217(2)(f)

  • Only BESS configuration changes require resubmission, § 1217(9)(p)(ii)

  • 55 dBA day and 45 dBA night at the property line with ANSI S1.4 meters; daytime limit above 50 dBA, § 1217(12)

  • Octave or one-third octave band frequency analysis required; no numeric dBC or band limits, § 1217(12)(a)

  • Preliminary study before preliminary approval and as-built study 6 months after occupancy, ANSI S1.4 and S1.11, § 1217(12)(a)-(c)

  • Vibration study showing vibration does not extend past the property line; no numeric limit, § 1217(13)

  • Water feasibility study, with hydrogeologic study and 8-hour pumping tests for private wells; public water not required, § 1217(11)

  • Water cooling systems must be closed loop, with at least 90% of drawn water reused, § 1217(14)

  • Peak water demand calculated in the water study; no metered reporting or drought plan, § 1217(11)(b)

  • Domestic and cooling wastewater disposal approved by the Sewage Enforcement Officer or DEP; timing not tied to a permit, § 1217(14)

  • All power must be self-generated on site with no grid power, so no utility capacity confirmation applies, § 1217(7)(a)

  • 100 ft of dense, 75% evergreen screening along all property lines, year-round, with dead plants replaced within 6 months and $30,000 security, § 1217(2)(d)

  • Shielded down-lighting with 0.5 footcandle limit at residential lines and 1 footcandle elsewhere, § 1217(5)

  • Facades facing roads must use at least two articulation or material elements; no separate material or color standard, § 1217(3)

  • Mechanical and electrical equipment inside a fully enclosed building unless infeasible, and rooftop equipment behind noise-absorbing screens, § 1217(2)(f)-(g)

  • ERP reviewed for approval by the fire department and Township, with 24-hour contact signs; no annual update, § 1217(9)(a) and (m)

  • Hazardous material tanks 200 ft from property lines with DEP-compliant spill containment; no spill plan filed, § 1217(6)

  • Annual fire safety inspections by a qualified professional; no report to the fire official, § 1217(9)(m)(xiii)

  • Traffic impact study in every case for operation and emergency access, plus a construction transportation plan; route reach not stated, § 1217(10)

  • Construction routes, joint road inspections, repair, and bond; construction hours not addressed, § 1217(10)(b)

  • Security of the estimate plus 25%, abandonment at 6 months, and full removal within 12 months under a Development Agreement; not recorded, § 1217(16)

  • Security reviewed 5 years after deposit and every 5 years; no first-year update, § 1217(16)(c)

  • Definition does not name cryptocurrency mining or AI, and the accessory exemption has no size limit, § 105

  • One as-built sound study 6 months after occupancy, with more on request, § 1217(12)(c)

  • Failure to replenish escrow is grounds for permit suspension; no revocation grounds or MPC enforcement reference, § 1217(18)

  • $50,000 applicant-funded escrow for independent engineering, acoustic, water, fire, and legal review, § 1217(18)

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data