Pulaski Township
Anti-Data Center Policies
Pulaski township’s enacted ordinance requires data centers to follow cooling and water-use rules, fund eventual removal, and meet noise limits with sound testing. Projects can still be approved, but these requirements add costs and review.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Pulaski TownshipThe Supervisors enacted Ordinance No. 2 of 2026, adding Section 307.46 to the zoning ordinance, on June 29, 2026, after a public hearing, and it took effect five days after enactment.Pulaski Township, Lawrence County — data-center ordinance (No. 2 of 2026)
What this means
The measure imposes cooling and water-use rules, money set aside for eventual removal and noise limits and sound testing. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements30
Conditional use approved by the Supervisors; no approval expiration stated, § 307.46(1) and (21)(b)
Allowed only in the I district and set back 550 ft from Agricultural districts; no preserved farmland or agricultural security area bar, § 307.46(2)(c)
59 dBA daytime and 50 dBA nighttime at receiving residential and sensitive receptor property lines, § 307.46(6)(a)
Section 307.46(6)(a)(1) to (3) requires preliminary, interim, and as-built studies, and Section 307.46(6)(i) requires ANSI S1 and S12 practice with Type 1 or Type 2 integrating meters.
Public water connection and water feasibility study; no well bar or pump test, § 307.46(8)(a) and (d)
Closed-loop cooling required unless an alternative uses less water and energy, § 307.46(8)(c).
Projected water demand disclosed and state approval for consumptive use of 20,000 gpd or more, § 307.46(8)(d)-(e)
Cooling wastewater disposal approved by the SEO or DEP before building permit, § 307.46(8)(b).
Stormwater plan only in the assessment above 100,000 sq ft, § 307.46(15)(a)(3)
Diesel generators must meet EPA Tier 4 with annual testing reports, § 307.46(9)(e)(1)-(2)
Thermal Impact Mitigation Plan including waste heat reuse evaluation, § 307.46(10).
Decommissioning plan for removal of battery systems, e-waste, and hazardous materials, and e-waste taken to an approved site, § 307.46(11)(a)(17) and (19)(a).
Utility capacity certification and third-party electrical inspection before occupancy, § 307.46(9)(a) and (c)
Power systems identified only; no energy usage plan, § 307.46(9)(b)
Principal solar energy systems must be on a separate parcel under the solar ordinance; other generation not addressed, § 307.46(16)
Substations screened and placed at the side or rear; on-site lines of 34.5 kV and below buried, § 307.46(3)
Known impacts on electric rates must be noted, § 307.46(9)(a)
Buffer of at least 100 ft along lines within 500 ft of homes, with berms and plantings, § 307.46(4)(b).
Full cut-off fixtures and 0.1 footcandle limit at residential uses, § 307.46(7)
Equipment within 300 ft of roads or homes enclosed or screened; plantings reach 12 ft, but not all equipment covered, § 307.46(4)(n) and (5)(a)
ERP accepted by the fire department and county, radio coverage, and 24-hour contact signage; no annual plan update, § 307.46(11)(a), (e), and (f)
First responders must receive training; cost not assigned, § 307.46(11)(a)(5)
Spill control and neutralization in areas with hazardous materials; no storage setbacks, § 307.46(11)(a)(14)
Section 307.46(11)(a)(6) requires the emergency plan to provide for annual fire safety inspections by a qualified professional on behalf of the data center, and Section 307.46(9)(c)(5) requires a third-party electrical inspection before occupancy.
Traffic and infrastructure impacts must be identified; no formal traffic impact study, § 307.46(13)(b)
Secondary emergency access required; no arterial or collector requirement, § 307.46(14)(b)(2)
Construction traffic coordinated with school districts and construction noise limited to daytime; no haul route bond, § 307.46(6)(h)(6) and (13)(b)
Security of 85% of cost, notice within 30 days, removal within 12 months, § 307.46(19)(b)
One as-built sound study, with later studies at township discretion, § 307.46(6)(a)(3)
Section 307.46(21) makes noncompliance grounds for revoking the conditional use approval and authorizes civil enforcement under the Zoning Ordinance.
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the I Industrial District