Potter Township

Anti-Data Center Policies

Potter Township’s enacted ordinance allows data centers to seek approval but limits where they can be built and how they use cooling and water, including setbacks and minimum site sizes.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Potter Township
The rules are in Ordinance No. 2-2026, which the Board of Supervisors enacted on October 19, 2026, adding Section 220-83.A to the township zoning ordinance.Potter Township, Centre County — data-center ordinance (No. 2-2026)

What this means

The measure imposes setbacks from homes or other protected places, minimum site-size requirements and cooling and water-use rules. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements22
  • Prohibited in every district except PCI, so barred in agricultural districts; preserved farmland and agricultural security areas not addressed, Section 220-83.A

  • Environmental impact assessment covering wetlands, floodplains, and water, and Water Quality District restrictions apply; no riparian buffer, Section 220-83.A.C(2)(iv) and C(11)

  • 65 decibels from 7 a.m. to 10 p.m. and 60 decibels at night at adjoining property lines; not 50 and 45 dBA, Section 220-83.A.C(8)

  • Noise mitigation plan with predicted levels and supporting analysis filed with the application; no later studies, Section 220-83.A.C(8)

  • Backup energy plan must state testing duration; no testing hours limit, Section 220-83.A.C(10)

  • Vibration must only be identified with mitigation measures; no vibration standard, Section 220-83.A.C(8)

  • Drilling wells strictly prohibited for data centers, with water supplied by off-site waterline under a separate permit, Section 220-83.A.C(2)(iii) and (iv)

  • Only closed-loop liquid or water-free dry cooling allowed, and evaporative cooling prohibited, Section 220-83.A.B and C(9)

  • Erosion and sedimentation plan and stormwater effects evaluated in the environmental impact assessment; no added stormwater standards, Section 220-83.A.C(5) and C(11)

  • Generator emissions not addressed

  • Solid waste and by-product disposal must meet state and federal rules; no recycling plan, Section 220-83.A.C(3)

  • Backup energy plan required, and traditional chillers allowed only with on-site renewables offsetting 50% of demand, Section 220-83.A.C(9) and C(10)

  • Data Center Energy Substation for on-site generation defined and addressed; no separate approval, Section 220-83.A.B

  • Screening or 25-ft buffer strips may be required where adjacent land use dictates, Section 220-83.A.C(5)

  • Shielded full cutoff fixtures with a 1.0 footcandle night limit at adjoining boundaries; light trespass minimized but not barred, Section 220-83.A.C(4)

  • Emergency Preparedness Plan with written fire company approval of site development; no annual updates, radio coverage, or posted contacts, Section 220-83.A.C(7)

  • Inventory of hazardous materials and batteries provided to fire companies; no storage setbacks or containment, Section 220-83.A.C(7)

  • Environmental impact assessment must evaluate traffic effects; no separate traffic impact study, Section 220-83.A.C(11)

  • Driveway standards and PennDOT review only; no arterial road or secondary access requirement, Section 220-83.A.C(1)

  • Noise mitigation plan must include a monitoring and reporting protocol for ongoing compliance, Section 220-83.A.C(8)E

  • Section 220-83.A.C(13) deems a loss of required federal or state permits a revocation of the conditional use approval and makes operation without them a prima facie violation, but no notice or hearing precedes revocation.

  • Section 220-83.A.C(11) requires the applicant to pay the Township's reasonable costs for professional review of the Environmental Impact Assessment, but that review is part of the conditional use rather than land development review.

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the PCI District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data