Point Township

Anti-Data Center Policies

Point Township’s enacted ordinance requires setbacks from homes and other protected places, minimum site sizes, and cooling and water-use rules. Data centers can still seek approval, but these limits narrow where and how they can operate.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Point Township
The standards were set by Ordinance No. 2026-05, which the Board of Supervisors adopted unanimously on September 8, 2026 after a public hearing, removing a full impact assessment trigger for buildings over 5,000 square feet before the vote.Point Township, Northumberland County — data-center ordinance (No. 2026-05)

What this means

The measure imposes setbacks from homes or other protected places, minimum site-size requirements and cooling and water-use rules. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements26
  • Conditional use decided by the Board of Supervisors; no approval expiration, Section 3 (§ 10.2.2.17)

  • 500-ft setback from all lot lines; no separate distances for schools, day care centers, hospitals or parks, § 15.23.f.i

  • Industrial district regulations stated as applying; generators may not be placed above the roof line, § 15.23.a and g.iv

  • Proximity to wetlands, Cold Water Fisheries and floodplains reviewed, and a full impact assessment with an environmental compatibility report required for sites over 1 MW or near sensitive lands, § 15.23.b.iii, l and m.v

  • Single 55 dBA limit at the property line, § 15.23.g.i

  • Noise and generator protocol with projected day and night levels at each boundary and the nearest home, before approval; no later study, § 15.23.m.iv

  • Vibration isolation required for HVAC, generator pads and mechanical systems; no property line standard, § 15.23.g.iii and m.iv

  • Stamped water use plan and a hydrogeological study where private wells, recharge areas or nearby wells are involved; no pump tests or well bar, § 15.23.h and m.iii

  • Closed-loop, hybrid or reclaimed-water cooling only, with open-loop cooling prohibited except reclaimed water with no thermal discharge, § 15.23.h.iv

  • Daily and peak water use and cooling method disclosed; no cap, reporting or drought plan, § 15.23.b.i and m.ii

  • Enhanced stormwater BMPs including bioretention, infiltration trenches and thermal filtering, with limits on unmitigated paved yards over 10,000 sq ft, § 15.23.j.

  • Heat island mitigation required and heat island contributions analyzed; no waste heat reuse review, § 15.23.j and m.v

  • Electrical demand, substation compatibility and redundant service confirmation before zoning approval; no third-party electrical inspection, § 15.23.b.i and m.ii.

  • Utility coordination plan documenting peak and base electrical demand; no on-site renewable requirement, § 15.23.m.ii

  • Required utility upgrades must be identified; cost not assigned to the applicant, § 15.23.b.i and m.ii

  • Section 15.23.f(ii) to (iv) require a 200 ft minimum buffer of native evergreens, berms, opaque fencing, and a gravel firebreak, but the ordinance does not require replacement of dead plants.

  • Long facades must include articulation, step-backs or landscaping, § 15.23.f.vi

  • Generators require acoustic shielding and baffled enclosures and buffers include opaque fencing; no all-sides or 12-ft equipment screening standard, § 15.23.f.iv and g.iii

  • Visual impact analysis of massing, facade articulation and sightlines in the full impact assessment; no renderings or study from historic sites, § 15.23.m.v

  • Fire protection and emergency operations plan with site maps for emergency services and annual walkthroughs; no radio coverage or 24-hour contact signs, § 15.23.e and m.i

  • Applicant must contribute to responder equipment and offset fire and emergency service needs with financial or in-kind contributions, § 15.23.m.i and m.vii.

  • Fuel and battery storage locations shown on site maps for emergency services; no storage setbacks or spill containment, § 15.23.m.i

  • Annual fire walkthrough; no third-party electrical inspection, § 15.23.e.v

  • Traffic circulation, trip generation and roadway capacity evaluated in the full impact assessment, required only above 1 MW or near sensitive lands and residential districts, § 15.23.l and m.vii

  • Two ingress and egress points with no reliance on residential streets; no arterial or collector road requirement, § 15.23.d

  • Removal and restoration within 180 days of Township notice, with bonding in an acceptable form; no security amount or notice of closure, § 15.23.k

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the Industrial District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data