Pocopson Township’s enacted ordinance requires data centers to meet setbacks, minimum site sizes, and cooling and water-use rules. Approval remains possible, but these limits narrow where and how projects can operate.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Pocopson TownshipThe current rules are in Ordinance No. 1 of 2026, which the Board of Supervisors adopted on July 27, 2026.Pocopson Township, Chester County — data-center ordinance (No. 1-2026)
What this means
The measure imposes setbacks from homes or other protected places, minimum site-size requirements and cooling and water-use rules. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements27
LI Limited Industrial district only, § 250-43.B(10)
Conditional use before Board of Supervisors; no approval expiration, § 250-49.D
Base height limit with rooftop equipment included; accessory 20 ft, § 250-49.D(6).
55 dBA day, 45 dBA night at residential receptors, Table 2
Section 250-49.D, Table 6, treats an increase of 3 dBA or more above the baseline ambient level documented before construction as a violation, measured with a Type 1 or Type 2 ANSI meter, but the baseline is not defined as L90 and no floor is set below which the cap does not apply.
70 dBC day, 60 dBC night, Table 3
Studies with application and within 180 days of operation, § 250-49.D(11)
65 VdB human perception limit, with study, § 250-49.D(11)(c)
Public water required; no groundwater or surface water for cooling, § 250-49.D(12)
Section 250-49.D(12)(e) requires air-cooled or closed-loop water circulation systems and Section 250-49.D(12)(d) bars groundwater and surface withdrawals for cooling, but evaporative systems are not expressly barred or limited to a stated water-use rate shown to meet the noise limits.
Usage estimates and drought response plan; no cap or reporting, § 250-49.D(12)
Cooling discharge analysis with application; no discharge to streams, § 250-49.D(13).
EPA Tier 4 diesel generators with annual testing reports, § 250-49.D(14)(g)
Electronic waste plan for servers, batteries, hazardous materials, § 250-49.D(18).
Energy usage plan; solar only suggested, § 250-49.D(10)
On-site generation a separate principal use with own approval, § 250-49.D(14)(a).
Substations at side or rear and screened; lines 34.5 kV and below buried, § 250-49.D(14)
100-ft buffer yard next to Sensitive Receptors and residential districts, § 250-49.D(9)(c).
Equipment screened on all sides; no height or acoustic standard, § 250-49.D(7)
Elevations and renderings required, § 250-49.D(8)
Plan accepted by fire department, 24-hour signage, radio coverage; no annual update, § 250-49.D(15)
Annual fire safety inspections, § 250-49.D(15)(a)
Section 250-49.D(16) requires a traffic impact study with every conditional use application covering access, road capacities, and off-site flow on the Township network and surrounding areas, but it does not cover construction traffic or set a study area reaching the nearest arterial or interchange.
Construction plan for times and access; no road bond, § 250-49.D(17)
Security for full cost, closure notice, completion within 18 months, § 250-49.D(19)
One post-construction noise study; annual generator reports, § 250-49.D(11), (14)
Traffic consultant chosen from Township list; cost not assigned, § 250-49.D(16)
Benefits & exceptionsHide benefits & exceptions1