Pittston Township

Anti-Data Center Policies

Pittston Township allows data centers only by conditional approval in its I-3 district, with costly energy, water, safety, noise, and cleanup requirements; approved plans receive some protection from later zoning changes.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Pittston Township
Restricts data centers to conditional-use approval in the I-3 industrial district and sets requirements for site design, emergency planning, water use, noise, solar power, parking, and decommissioning.Pittston Township Ordinance No. 7-01 of 2026 — Data Center Ordinance (Updated)

What this means

The measure would allow data centers only as a conditional use in the I-3 district and impose demanding requirements for energy, water, safety, noise, and cleanup funding, creating significant costs and approval hurdles (conditional use in the I-3 Industrial District; 150% of estimated gross cost). Approved campus plans would get some protection from later zoning changes, but that benefit does not outweigh the barriers to building and operating a center (not subject to changes in zoning).

People behind it

  • Moved the motion to enact Ordinance 7-01 of 2026.

  • Seconded the motion to enact Ordinance 7-01 of 2026.

  • Enacted the ordinance.

Restrictions & requirementsHide restrictions & requirements18
  • Data centers and data center campuses require conditional-use approval in the I-3 Industrial District and are prohibited in every other zoning district, including as accessory uses. Conditional use in I-3

  • The ordinance imposes dimensional limits: front, rear, and each side yard must be at least 100 feet; lot coverage is capped at 55%; and buildings may not exceed three stories or 75 feet. Dimensional regulations

  • A data center campus requires a master plan; a data center developed outside a master plan requires a land development plan. Individual site plans and applicable third-party permits must be submitted before a building permit, and major master-plan modifications follow the procedure for a new master plan. After master-plan approval, identified lots may be developed by right, subject to these requirements. Master-plan and site-plan requirements

  • To receive the ordinance’s stated protection from later zoning or subdivision changes and avoid further approvals for phased development, campus development must commence within five years of master-plan approval. Five-year commencement condition

  • Applicants must provide a qualified-professional emergency response plan accepted by the local fire department and emergency management services. It must address emergency procedures, access for emergency equipment, first-responder training, inspections and fees, annual fire-safety inspections, displayed emergency contacts, and at least quarterly fire drills. Emergency response plan requirements

  • A data center with battery storage or another energy-storage device must demonstrate compliance with NFPA Standard 855 or similar standards and provide fire-suppression systems specifically designed for battery storage. Energy-storage safety requirements

  • Approval is barred unless the applicant demonstrates that fire suppression, containment, ventilation, and evacuation procedures sufficiently protect public health, safety, and welfare and comply with applicable fire-safety codes. Fire-safety approval condition

  • A campus master plan must include an environmental impact statement. It must establish a township-approved baseline air-quality standard, with testing paid for by the data center annually or as directed by the township; the stated baseline air quality may not increase. Environmental impact and air-quality requirements

  • Data centers must meet sound limits at the property line: no more than 60 dB(A) from 7:00 a.m. to 9:00 p.m. or 55 dB(A) from 9:00 p.m. to 7:00 a.m. A qualified acoustic engineer must provide a sound analysis before the final certificate of occupancy for each applicable phase. Sound limits and analysis

  • Data centers and campuses must use closed-loop or recirculating cooling and water-conservation technologies. For public water, applicants must submit written confirmation that the provider has capacity and intends to supply projected demand for each phase. Cooling and public-water requirements

  • If any water comes from nonpublic sources, the applicant must submit a qualified professional’s water-feasibility study demonstrating adequate, sustainable supply and no unmitigated adverse effects on nearby wells, groundwater, or surface waters. The study must include specified demand, source, yield, water-use, and nearby-water-resource information. Nonpublic-water study requirements

  • Proof of review and approval from the Delaware River Basin Commission and the Susquehanna River Basin Commission is required for withdrawals of at least 50,000 gallons per day averaged over 30 days, or consumptive use of at least 10,000 gallons per day averaged over 30 days. Water-agency approval thresholds

  • Each data center must provide at least 40 parking spaces. For a campus, parking other than security parking may not be within 100 feet of a property line abutting a district with residential use. Parking requirements

  • Each data center must provide at least one off-street loading or unloading space measuring at least 12 feet by 50 feet. Loading-space requirement

  • Data centers must install roof-mounted solar photovoltaic systems capable of generating at least 80% of monthly electricity use averaged over the year; ground-mounted solar is prohibited. If roof size or structural limits prevent the 80% target, on-site generation must still reach 60%, with the shortfall offset through qualifying renewable-energy credits and/or approved green-energy purchases and documented in annual reports. Solar-generation and offset requirements

  • Before any building permit, the applicant must post cash escrow or an irrevocable letter of credit equal to 150% of the estimated gross cost of demolition, equipment and infrastructure removal, site restoration, and soil and groundwater remediation. The estimate excludes salvage value, must be prepared by a qualified professional, and must be updated annually; the security amount is reviewed every five years. Decommissioning security requirements

  • Every ten years during operation, or when equipment replacement exceeds 25% of installed capacity, the owner must fund a Phase I/II environmental site assessment and submit its results within 60 days. Detected contamination requires immediate remediation at the owner’s expense and an increase in financial security to cover estimated cleanup costs. Environmental assessments and remediation

  • Twelve consecutive months without active data-processing operations constitutes abandonment and authorizes the township to use the financial security to restore the site to greenfield condition. Removing or deactivating more than 50% of installed computing capacity triggers a mandatory review of decommissioning obligations. Abandonment and capacity-reduction triggers

Benefits & exceptionsHide benefits & exceptions6
  • Data centers and data center campuses may be proposed as conditional uses in the I-3 Industrial District; they are not permitted in other zoning districts. The ordinance also recognizes supporting accessory uses on the same tract or unified adjacent parcels, but excludes energy-generation systems intended to supply normal operations. conditional use in the I-3 Industrial District

  • A campus can use a master plan, after which development of each lot, parcel, or building identified in the plan is permitted by right. Individual site plans and applicable third-party permits are still required before building permits. development of each lot, parcel or building identified in the Master Plan shall be permitted by right

  • Phased campus development consistent with an approved master plan needs no further approvals and is not subject to later municipal zoning or subdivision ordinance changes, provided development commences within five years of master-plan approval. Provided that development commences within five (5) years

  • An individual site plan may be treated as consistent with the approved master plan if identified in it or found to be a minor modification, allowing some changes to proceed without the major-modification process. clearly identified in the approved Master Plan

  • The Board may waive or modify master-plan implementation requirements when it finds a provision unreasonable, unduly burdensome, or an alternative standard provides equal or better outcomes. Waivers or Modifications

  • Under a master plan, a developer may aggregate lots under common ownership when calculating the lot-coverage limit. aggregate one or more lots under common ownership

Sources

current law · Pittston Township
Restricts data centers to the I-3 industrial district and sets requirements for their site plans, emergency safety, noise, solar power, parking, and other development standards.Pittston Township Ordinance No. 12-01 of 2025 — Data Center Ordinance

What this means

The ordinance would allow data centers only in the I-3 district, which supervisors said has no available space, and it adds demanding solar, safety, noise, and environmental requirements (the only I-3 area is now full). Master-plan approval would make planned development easier to phase and protect it from later zoning changes, but that benefit does not outweigh the practical barriers.

People behind it

  • Enacted Ordinance 12-01 of 2025.

  • Moved the motion to enact Ordinance 12-01 of 2025.

  • Seconded the motion to enact Ordinance 12-01 of 2025.

Show 1 more peopleShow fewer people
  • Responsible for enforcing the ordinance.

Restrictions & requirementsHide restrictions & requirements15
  • Data centers and campuses are permitted only in the I-3 Industrial District; they are prohibited in all other zoning districts, including as accessory uses. “In all other zoning districts, they are not permitted”

  • Normal-operation energy generation for a data center is excluded from the definition of a data center accessory use. “shall not include energy generation systems”

  • Facilities must meet minimum front, rear, and side yards of 75 feet; lot coverage is capped at 55%; and buildings are limited to three stories or 75 feet. Lot area and lot width have no minimums. “seventy-five (75) feet”

  • A data center campus requires a Master Plan subject to the township’s subdivision and land development rules; a data center not included in a Master Plan requires a Land Development Plan under those rules. “A Master Plan shall be submitted”

  • Before a building permit, the applicant must submit an individual site plan for each center or campus phase, along with applicable third-party permits, such as highway occupancy, NPDES, and ESCGP permits. “prior to issuance of a building permit”

  • A campus Master Plan must include an Environmental Impact Statement addressing environmental consequences and subjects including water quality and supply, erosion, pollution, flooding, and waste disposal. “shall require an Environmental Impact Statement”

  • Applicants must provide an Emergency Response Plan prepared by a qualified professional and accepted by local fire and emergency services during land development. It must cover emergency procedures, access for responders, responder training, township inspections, emergency contacts, annual fire-safety inspections, and at least quarterly fire drills. Applicants pay inspection fees, and failed inspections may result in penalties. “submit an Emergency Response Plan”

  • A data center cannot be approved unless its fire-suppression, containment, ventilation, and evacuation procedures sufficiently protect public health, safety, and welfare and comply with applicable fire-safety codes. “No Data Center shall be approved unless”

  • If a data center proposes battery storage or another device capable of storing energy for later use, it must show compliance with NFPA 855 or similar standards and install fire-suppression systems designed specifically for battery storage. “capable of storing energy”

  • Major changes to an approved campus Master Plan are subject to land-development rules; a change producing more stormwater discharge or runoff than the approved Stormwater Management Plan allows is a major modification and follows the new-Master-Plan procedure. “greater than the rates identified”

  • A phased campus must commence development within five years of Master Plan approval to avoid further approvals for phases consistent with that plan and to retain protection from later zoning or subdivision ordinance changes. “development commences within five (5) years”

  • A data center or campus must keep sound at or below 60 dB(A) from 7 a.m. to 10 p.m. and 55 dB(A) from 10 p.m. to 7 a.m., measured at the property line; a qualified professional acoustic engineer must provide a sound analysis before the final certificate of occupancy for each applicable phase. “will not exceed”

  • Except for security purposes, campus parking cannot be within 50 feet of a property line abutting a district with residential use. “within fifty (50) feet”

  • Each data center must provide at least 40 parking spaces and one off-street loading or unloading space measuring at least 12 by 50 feet. “A minimum of 40 spaces”

  • Data centers must install rooftop solar photovoltaic systems capable of generating at least 80% of monthly electricity use averaged over the year, including winter. Ground-mounted solar is prohibited. If roof area or structural limits prevent the 80% target, on-site generation must still reach 60%, with the shortfall offset by qualifying renewable-energy credits or approved green-energy purchases and documented in annual reporting. “at least 80% of their monthly electricity usage”

Benefits & exceptionsHide benefits & exceptions7
  • Data centers and campuses are permitted uses in the I-3 Industrial District, though not in other zoning districts. permitted use in the I-3 Industrial District

  • The ordinance sets no minimum lot area or lot width for data centers or campuses. Minimum Lot Area: None

  • For lot-coverage calculations under a Master Plan, a developer may aggregate lots under common ownership. aggregate one or more lots

  • The definition of accessory uses allows supporting facilities such as electrical substations, utility lines, cooling-water and wastewater treatment facilities, and pump stations, if located on the same tract or adjacent parcels developed as a unified data-center project. It excludes energy-generation systems intended to supply the center during normal operations. electrical substations

  • After a Master Plan is approved, development of each lot, parcel, or building identified in it is permitted by right. shall be permitted by right

  • A campus may be built in phases without further approvals if development begins within five years of Master Plan approval and follows the approved plan; qualifying phased development is protected from later municipal zoning or subdivision ordinance changes. development commences within five (5) years

  • The Board may waive or modify Master Plan implementation requirements if a provision is unreasonable, causes undue hardship, or an alternative standard provides equal or better outcomes. approve waivers or modifications

Sources

current law · Pittston Township
The current rules are in Ordinance 7-01 of 2026, which the Board of Supervisors adopted on July 20, 2026, updating Ordinance 12-01 of 2025.Pittston Township, Luzerne County — data-center ordinance (No. 7-01 Of 2026)

What this means

The measure imposes cooling and water-use rules, money set aside for eventual removal and noise limits and sound testing. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements19
  • Conditional use; master plan valid 5 years, no 1-year expiration, Section 2 and Article 8F.I

  • Environmental Impact Statement for a campus master plan, Article 8F supplemental I

  • Data center campus defined and developed under one master plan, Section 1 and Article 8F supplemental A

  • Phases under the master plan need no further approval; major modifications need new review, Article 8F supplemental I and J

  • 60 dBA day and 55 dBA night at the property line, Article 8F supplemental K

  • Water feasibility study for nonpublic sources; no bar on wells for cooling, Article 8F supplemental L

  • Closed-loop or recirculation cooling required; evaporative cooling not restricted, Article 8F supplemental L

  • Projected water demand disclosed, Article 8F supplemental L

  • Stormwater plan referenced only for master plan changes

  • Annual air quality testing against a baseline; no Tier 4 generator rule, Article 8F supplemental I

  • Removal of batteries, substations, and all equipment on decommissioning; no recycling plan, Section 6

  • Rooftop solar for at least 80% of monthly electricity, or 60% plus credits, with annual reporting, Article 8F supplemental O and P.

  • Emergency response plan accepted by the fire department with posted contacts and quarterly drills; no annual update or radio coverage, Article 8F supplemental F

  • Plan must ensure responder training; no funding, Article 8F supplemental F.1.d

  • Annual fire safety inspections; no electrical inspection, Article 8F supplemental F.1.g

  • Security of 150% of removal cost before building permit; no notice or 6-month removal deadline, Section 6

  • Cost estimate updated annually and security reviewed every 5 years, Section 6.A.1.c and 6.B

  • Annual reporting of renewable energy purchases and annual air quality testing, Article 8F supplemental I and P

  • Failed inspections result in penalties; general enforcement by the Zoning Officer, Article 8F supplemental F.1.f and Section 7

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the I-3 Industrial District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data