Pine Grove Township
Anti-Data Center Policies
Pine Grove Township’s enacted ordinance limits eligible locations and requires minimum site sizes for data centers, narrowing where projects can proceed while retaining an approval route.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Pine Grove TownshipThe current rules are in Ordinance No. 99, a full zoning ordinance update that the Board of Supervisors adopted on December 16, 2025, after a public hearing on November 12, 2025.Pine Grove Township, Schuylkill County — data-center ordinance (No. 99 (December 16, 2025))
What this means
The measure imposes minimum site-size requirements and limited eligible locations. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements20
90-ft height, more by conditional use, § 663.1
Wetland, riparian, and floodplain work must meet DEP and floodplain rules, § 663.1.C
Data center campus defined and permitted as one use, § 202 and § 546
Township noise limits apply, 80/75 dBA day and 68/64 dBA night in industrial districts, § 634 and § 663.1.C
Section 663.1.C.ii(c) to (e) caps project sound at 5 dBA above the pre-construction ambient level, measured by a long-term survey under ANSI S12.9 Part 2.
Preliminary and as-built studies; no building permit study, § 663.1.C
Generator testing 7 am to 8 pm only; no hours cap, § 663.1.C
Water feasibility study if not on public water, § 663.1.C
Projected water needs required for non-public supply, § 663.1.C
Public sewer required; no wastewater plan
Generators must meet state and federal permitting standards, § 546
Utility letter confirming capacity; no electrical inspection, § 663.1.C.
Full-time generators addressed; nuclear, coal, and oil prohibited, § 546
50-ft buffer with berms next to residential districts, § 663.1.B
Must meet the lighting section and IESNA guidelines, § 606 and § 663.1.B
Rooftop equipment screened; ground equipment kept out of front yards, § 663.1.B and C
Emergency plan for buildings over 90 ft; campus security plan, § 663.1.A and C
One as-built sound study after opening, § 663.1.C
Section 663.1.C.i(c) says failure to remedy a noise violation may result in permit revocation, in addition to other penalties.
Township acoustical expert approves studies; cost of review not assigned, § 663.1.C
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the Data Center Overlay District
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data