Borough of Phoenixville

Anti-Data Center Policies

Phoenixville Borough’s enacted ordinance limits data-center height and requires setbacks from homes and other protected places, adding construction and review costs while still allowing approval.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Phoenixville Borough
The current rules are in Ordinance No. 2025-2415, which Borough Council adopted on October 14, 2025.Phoenixville Borough, Chester County — data-center ordinance (No. 2025-2415)

What this means

The measure imposes setbacks from homes or other protected places and building-height limits. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements5
  • 40-ft height limit; no rooftop equipment limit, § 27-301.2B(2)(l)(1)(c)

  • Acoustic soundproofing required; no numeric limit, § 27-301.2B(2)(l)(1)(e)

  • Generators for backup or emergency only; no testing limits, § 27-301.2B(2)(l)(1)(d)

  • General showing of water access; no feasibility study, § 27-301.2B(2)(l)(1)(f)

  • External equipment partially or fully screened, § 27-301.2B(2)(l)(1)(a)

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Special exception in the Industrial (I) district