Perry Township

Anti-Data Center Policies

Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.

Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Perry Township.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

pending · Perry Township
The draft is unnumbered and undated and has not been posted, and the Supervisors' October 8, 2026 agenda listed a vote to advertise it for adoption, but no hearing or adoption date has been announced.Perry Township, Lawrence County — proposed data-center ordinance (None Adopted)

What this means

The proposal would impose setbacks from homes or other protected places, minimum site-size requirements and cooling and water-use rules. The limits sharply reduce usable sites or workable project designs, making development substantially harder despite an available approval route.

Restrictions & requirementsHide restrictions & requirements35
  • Data Center Permit decided after a public hearing before the Supervisors; not a conditional use and no approval expiration, §§ 3.B, 8

  • Section 10.B(3)(b) sets Data Center primary and accessory use buildings, structures, and truck idling areas 1,500 feet from any adjacent residential or agricultural use or Sensitive Receptor, and the accessory use definition includes backup generators and other equipment.

  • Data centers barred from the 100-year and 500-year floodplains; no riparian buffer or environmental impact assessment, § 6.A

  • Section 3.C requires a permit modification for any physical change that materially alters the size, type, or number of buildings, structures, or uses, and Section 3.D exempts like-kind replacement, but increases in electrical demand or added generator, cooling, battery, or substation capacity are not stated triggers.

  • Section 10.Q(2)(a) and (b) set 45 dBA from 7 a.m. to 7 p.m. and 40 dBA at night at all property lines, measured at 6 and 15 feet above ground, but no metric, meter class, or measurement procedure is stated.

  • Where baseline exceeds the limits, no increase over baseline; no cap above background otherwise, § 10.Q(2)(c)-(d)

  • 60 dBC by day and 50 dBC at night, with full spectrum modeling, § 10.Q(1)-(2)

  • Pre-construction study with the application and post-construction studies 6 to 18 months after occupancy and annually; no building permit study, § 10.Q(1)(a)-(b)

  • ISO 2631-2 residential limit of 200 micrometers per second on nearby property, with pre- and post-construction vibration studies, § 10.Q(1), (3)

  • Wells barred for cooling where public water is available, and a water feasibility plan with safe yield is required for nonpublic sources; no pump test requirement, § 10.I

  • Closed-loop cooling required unless an alternative uses less water and energy, § 10.I(3).

  • Quarterly groundwater usage reports; no drought response plan, § 10.J

  • Wastewater plan covering HVAC discharge, and untreated discharge prohibited, § 10.N

  • Stormwater management plan complying with existing regulations, § 10.E

  • Annual diesel generator testing with reports showing emissions within permitted limits; no Tier 4 standard, § 10.H(2)

  • Thermal Impact Mitigation Plan including waste heat reuse evaluation, § 10.P.

  • Decommissioning plan covers disposal or recycling of materials; no specific electronic waste plan, § 10.S(1)

  • Utility interconnection application, security agreement, and energization date documented; no third-party electrical inspection, § 10.F(2)(e)

  • Energy Usage Plan, LEED data center design, and 10% renewable procurement above 50 MW; no on-site renewable requirement, § 10.F

  • Energy generation for normal operations is a separate primary use with separate approval, with the data center placed between it and homes, § 10.G(1).

  • Substations at the side or rear and screened, set back 1,500 ft from homes, and on-site lines of 34.5 kV and below buried, § 10.G(2)-(5)

  • Landscape buffer next to roads, residential and agricultural uses, and sensitive receptors; no minimum width, § 10.D(2)

  • Building elevations and fence material limits only; no facade standards, § 10.D(1), (10)

  • Equipment within 300 ft of roads or 1,500 ft of homes enclosed or fully screened, partly to reduce noise; no 12 ft standard, § 10.D(11)

  • Elevations and renderings of facades visible from off site required, § 10.D(1)

  • Emergency plan reviewed by the fire departments, radio coverage, and 24-hour contact signs; no annual plan update, § 10.R(1)-(3)

  • Annual hazardous materials inventory given to the fire company; no storage setbacks or containment, § 10.R(5)

  • Annual fire safety inspections; no third-party electrical inspection, § 10.R(1)(f)

  • Section 6.A(3) requires a traffic study with every application covering existing, construction phase, and day-to-day traffic and the off-site routes, Section 10.A(1) repeats the requirement, and Section 10.A(3) requires all public roads used during construction and operation to be identified.

  • Haul routes identified and road bonding may be required; no work hours, § 10.A(3)

  • Decommissioning plan, six months notice, and completion within 18 months after a one-year start; no financial security for removal, § 10.S

  • Plan revised every five years, but no removal cost estimate, § 10.S(2)

  • Quarterly groundwater usage reports and annual post-construction noise and vibration studies, §§ 10.J, 10.Q(1)(b)

  • Section 5.B and C require a $25,000 deposit and reimbursement of engineering, legal, and consultant review fees for the Data Center Permit application, but that review is a separate permit process, not land development review.

  • Public meeting before first presentation to the Supervisors or County Planning Commission, and a project website kept current until one month after the final certificate of occupancy, § 7

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data