Perry Township

Anti-Data Center Policies

Perry Township’s enacted ordinance requires setbacks from homes and other protected places, minimum site sizes, and cooling and water-use controls. Data centers can still seek approval, but these limits narrow where and how projects can operate.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Perry Township
The current rules are in Ordinance 09-2026, which the Supervisors adopted on September 8, 2026.Perry Township, Berks County — data-center ordinance (No. 09-2026)

What this means

The measure imposes setbacks from homes or other protected places, minimum site-size requirements and cooling and water-use rules. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements24
  • Section 410.5(A)(1) and (2) require all principal and accessory uses of the data center, including buildings, structures, and related impervious surfaces, to be at least 1,000 ft from a principal building occupied by an existing residential use, and Data Center Equipment is defined to include cooling, power, and other outdoor equipment.

  • 50 ft; no rooftop equipment limit, § 410.5(A)(1)(g)

  • Environmental impact assessment required, § 410.5(B)(1)

  • 67 dBA day and 57 dBA night at lot lines, § 410.5(B)(27)

  • Section 410.5(B)(12)(a), (c), (e), and (i) require preliminary, interim, and as-built sound studies using ANSI S1.4-2014 sound level meters, with the as-built study six months after the certificate of occupancy, but the as-built study is not required to be taken at full operating load.

  • Generators held to noise limits; no testing hours or cap, § 410.5(B)(27)

  • Public water required; on-lot water needs variance and hydrogeologic study with 72-hour drawdown tests, § 410.5(A)(5), (B)(7)

  • Closed-loop required; evaporative towers barred without waiver, § 410.5(B)(7)(f).

  • Continuity plan covers drought; no cap or usage reporting, § 410.5(B)(29)

  • Public sewer and utility impact report on sewage; no cooling discharge plan, § 410.5(A)(4), (B)(6)

  • Plan to mitigate community impacts including excessive heat, § 410.5(B)(23)(e)

  • Hazardous materials removed at decommissioning; general disposal rules, § 410.5(B)(14), (B)(28)(b)

  • Interconnection letter or power source evidence; no third-party inspection, § 410.5(B)(26)

  • Utility impact report on energy supply; solar only to be considered, § 410.5(B)(6), (B)(8)

  • 60 ft earthen berm or natural buffer, § 410.5(B)(23)

  • LEED Silver required, § 410.5(B)(9)

  • Substations concealed by landscaping where visible; no height or acoustic screening, § 410.5(B)(26)

  • Emergency plan approved by emergency agencies; no annual updates, § 410.5(B)(30)

  • Secondary containment for hazardous coolant; no storage setbacks, § 410.5(B)(7)(f)(3)

  • Annual containment certification only; no fire or electrical inspections

  • Section 410.5(B)(5) requires a traffic impact study in every case, evaluating trip generation for all hours of operation over a study area set with the Township Engineer, but the study is not required to cover construction traffic or to reach the nearest arterial or interchange.

  • 110% security and closure notice; removal within 12 months, § 410.5(B)(28)

  • One as-built sound study after opening, § 410.5(B)(12)(e)

  • Violations must be promptly remediated; no penalties, § 410.5(B)(12)(f)

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the CLI Commercial Light-Industrial District