Borough of Perkasie
Anti-Data Center Policies
Bucks County’s Newtown-area ordinance allows data centers through an approval process but limits where and how they can operate, with setbacks, minimum site sizes, and noise controls.
Rating and summary from Bucks County as there are no scored current or future laws outside temporary restrictions for Borough of Perkasie.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
pending · Borough of PerkasieProposes to allow data centers in Perkasie’s industrial districts only with conditional-use approval and requirements for noise, water and power use, emergency response, and decommissioning.Perkasie Borough proposed Data Center Ordinance amendment (Planning Commission discussion)
What this means
The draft creates a path for data centers in industrial districts, but requires conditional-use approval and extensive studies and operating safeguards, including public water and sewer service (public water and public sewer). These requirements could add substantial cost and delay, and limits on noise, water, power generation, and site design could make some projects or expansions impractical.
People behind it
- Judith Stern Goldstein
Co-prepared the June 5 draft zoning ordinance amendment.
- Stacy Yoder
Co-prepared the June 5 draft zoning ordinance amendment.
- Cassandra L. Grillo
Zoning Officer who administered the ordinance review process and circulated the draft for Planning Commission review.
Show 2 more peopleShow fewer people
- Perkasie Borough Council
Authorized the Planning Commission to discuss data-center regulations and make recommendations; received the draft ordinance for review.
- Perkasie Borough Planning Commission
Was tasked with discussing data-center regulations and making recommendations on the draft ordinance.
Restrictions & requirementsHide restrictions & requirements13
Data centers would require conditional-use approval by Borough Council and could be located only in the I-1 Industrial District. Conditional use in the I-1 district
The minimum lot area would be 3 acres; buildings would be limited to 45 feet and three stories, including rooftop equipment and accessory uses. Minimum lot area
Data centers and their accessory uses and equipment would need 50-foot setbacks from adjoining properties and road rights-of-way, increased to 100 feet where adjoining a residential district or use. Required setbacks
Perimeter buffers and visual screening would be required; accessory mechanical equipment would need a visually solid screen on all sides. Barbed wire, razor wire, electrified fences, fence spikes, and other hazardous fencing would be prohibited. Screening and fencing requirements
Applicants would have to submit pre-construction and post-construction noise and vibration studies. The post-construction study would be due within 180 days after operations begin, test specified operating conditions, and show compliance with noise limits, including residential limits of 55 dBA by day and 45 dBA at night. Violations would require a corrective-action plan within 30 days of Borough notice and remediation within 90 days, unless extended for good cause. Noise-study and compliance requirements
Facilities would have to use public water and public sewer, provide water-use estimates and evidence of adequate public-water capacity, and use air-cooled, closed-loop, or similar high-efficiency cooling systems. Water and sewer requirements
For a grid connection, applicants would have to document that the utility has sufficient capacity and will serve the facility, and submit plans showing how power will be provided. A ratepayer-impact analysis would be required if feasible and reasonably obtainable. Power-supply documentation
Power-generation systems serving a data center during normal operations would be treated as a separate principal use and require approval under applicable regulations. Nuclear generation would not be permitted as part of the data-center use. Separate approval for power generation
Substations would have to meet applicable zoning setbacks; those abutting a non-Limited-Industrial district or a parcel containing a sensitive receptor would need an 800-foot setback. On-site power lines of 34.5 kV or less would have to be buried. Substation setbacks and buried lines
Backup generators would be limited to Tier IV units and use during power outages, similar emergencies, or testing. Testing would require at least 24 hours’ advance notice to the Borough and public notice on the operator’s website. Backup-generator limits and notice
An emergency response plan would require acceptance by local fire and emergency-management services, annual fire-safety inspections, and compliance with NFPA 855 or similar standards for battery storage. Applicants would have to reimburse costs for specialized fire and EMS training, including future ongoing training. Emergency planning and training costs
Applicants would have to submit a decommissioning plan. The Borough could require financial security to cover decommissioning and site-restoration costs if the operator or owner fails to complete the work promptly. Decommissioning plan and possible security
The draft would require one off-street parking space per 8,000 square feet of floor area designed for regular employee access. Parking requirement
Benefits & exceptionsHide benefits & exceptions8
The Perkasie draft allows data centers as a conditional use in the I-1 Industrial District, creating a defined approval route for development there. permitted when authorized as a conditional use
The Perkasie draft sets a 3-acre minimum lot size, a 45-foot height limit, and a 50-foot setback from most adjoining properties and road rights-of-way, with a 100-foot setback where abutting residential uses or districts. These dimensional standards allow development on smaller lots and establish clear siting limits. minimum lot area shall be 3 acres
The Perkasie draft requires one parking space per 8,000 square feet of employee-accessible floor area, rather than a higher general industrial parking standard. one off-street parking space per 8,000 s.f.
The Perkasie draft provides a path to connect to the public electric grid if the utility provider certifies that capacity is available and it can serve the data center. It also requires the applicant to plan with the provider for possible future energy technologies. necessary capacity is available
The East Rockhill and West Rockhill examples permit data-center accessory uses and equipment by right in support of an approved data center, allowing related support facilities without a separate principal-use approval. permitted by right in support of a data center
The East Rockhill and West Rockhill examples allow data-center projects to be built in one or more phases, with a site plan required for each phase before building permits are issued. may be developed in one or more phases
The West Rockhill example allows on-site electric or sewer methods to be considered if necessary public-system improvements are found infeasible by the Township Engineer and the utility provider, subject to Township ordinances. on-site utility methods for electric and/or sewer may be considered
The Lower Southampton example permits data centers and their accessory uses in the Industrial District, subject to its stated procedures and standards, rather than requiring a conditional-use or special-exception approval. permitted by right in the Industrial Zoning District
Sources
pending · Perkasie BoroughThe Planning Commission recommended approval on August 26, 2026, Borough Council authorized advertisement of a public hearing on September 8, 2026, and the borough office reported on October 19, 2026 that the public hearing is scheduled for November 16, 2026.Perkasie Borough, Bucks County — proposed data-center ordinance (None Adopted)
What this means
The proposal would impose cooling and water-use rules, money set aside for eventual removal and noise limits and sound testing. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements19
800 ft substation setback from sensitive receptors only, (12)[e]
55 dBA day, 45 dBA night at residential, (f)[9] Table 2
Section (f)[9], Table 6, treats an increase of 3 dBA or more above the baseline ambient level documented before construction as a violation, measured with a Type 1 or Type 2 ANSI meter, but the baseline is not defined as L90 and no floor is set below which the cap does not apply.
70 dBC day, 60 dBC night, (f)[9] Table 3
Study with application and within 180 days of operation, (f)[1] and [3]
PPV and 65 VdB limits, (f)[3][f]
Public water required with provider capacity letter, (10)[a] and [c]
Air-cooled or closed-loop non-evaporative cooling required, (10)[d]
Daily and annual water estimates, (10)[b]
Public sewer required, (10)[a]
Tier IV generators only, no reports, (13)
Substations side or rear and screened, lines of 34.5 kV or less buried, (12)[b] and [d]
Ratepayer impact analysis required, (11)[b]
Base perimeter buffer applied, G(14)(d)
All mechanical equipment screened on all sides, G(14)(d)
Annual fire safety inspections, (14)[a][v]
Security for full cost and closure notice, removal within 1 year, (15)
One post-construction noise study, (f)[3]
Website only for generator testing notice, (13)
Benefits & exceptionsHide benefits & exceptions1
Proposed approval pathway: Conditional use in the I-3 Industrial district (draft)
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data