Penn Township

Anti-Data Center Policies

Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.

Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Penn Township.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

pending · Penn Township
The undated and unnumbered draft would amend Zoning Ordinance No. 2003-06, the township secretary sent it by email on October 21, 2026 and wrote that no hearings are scheduled, and the Perry County Planning Commission reported the same day that it has received a proposed data center ordinance from the township.Penn Township, Perry County — proposed data-center ordinance (None Adopted)

What this means

The proposal would impose setbacks from homes or other protected places, cooling and water-use rules and noise limits and sound testing. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements33
  • Conditional use before the Board of Supervisors, § 1660.B; no approval expiration

  • Environmental impact assessment covering surface waters, riparian buffer width, wetlands and steep slopes, § 1323.D; no fixed riparian buffer

  • Must comply with existing Section 1315 noise limits, which are not in the draft, § 1660.B(4)(a)

  • Sound study must address low-frequency tonal noise in the 40 Hz to 200 Hz range; no dBC limit, § 1660.B(4)(a)

  • Section 1660.B(4)(a)(1) to (3) of the draft requires preliminary, interim, and as-built sound studies using ANSI S1.4 sound level meters, with the as-built study six months after the certificate of occupancy, but covers routine and continuous operations and requires no study at full operating load.

  • Generators must be sound shielded; no testing hours or cap, § 1660.B(4)(b)

  • Vibration study showing no vibration perceptible beyond the property line, § 1660.B(4)(c).

  • Section 1660.B(5)(b) of the draft requires closed-loop cooling with all water brought in from outside the township, and Section 1323.D(4)(b)(10) requires a hydrogeologic report with an aquifer test for groundwater sources, but no provision requires cooling water to come from available public water.

  • All cooling must use a closed loop system, defined to exclude evaporative cooling, § 1660.B(5)(b) and Article II

  • Quarterly reports of daily groundwater withdrawals, § 1323.D(4)(b)(12)(d); no drought response plan

  • Section 1660.B(5)(d) of the draft requires the applicant to demonstrate that disposal of domestic, cooling, and industrial wastewater has been provided and approved by the Sewage Enforcement Officer or DEP, but does not state that the approval must be in hand before the zoning permit.

  • Stormwater management plan meeting the Township Stormwater Management Ordinance, § 1323.D(3)(l)

  • Evidence of compliance with state and federal regulations and analysis of generator and air emissions, § 1660.B(10)(b) and (d); no Tier 4

  • Heat island effects disclosed with mitigation, § 1660.B(10)(d); no thermal impact plan

  • Decommissioning plan for servers, batteries, UPS systems and cooling systems through certified recyclers; refrigerants not named, § 1660.B(6)(b)(3) and B(11)(a)

  • Utility certification of capacity and service; no third-party electrical inspection, § 1660.B(6)(a).

  • Energy Consumption and Sustainability Plan; 10% renewable offset only to the extent reasonably feasible, § 1660.B(6)(b)

  • Substations at the side or rear, screened from public view, and on-site lines of 34.5 kV and below buried, § 1660.B(6)(d)-(e)

  • Utility infrastructure impact assessment identifies required upgrades; cost not assigned, § 1660.B(6)(a)

  • 50 ft planted buffer next to residential uses, districts and sensitive receptors, § 1660.B(2)(a)

  • Accessory equipment visually and audibly screened, and fully enclosed within 400 ft of roads, homes or sensitive receptors; no 12 ft standard, § 1660.B(3)(a)

  • Visual resources identified in the CEIA only; no elevations or viewshed study, § 1323.C(12)

  • Emergency response plan accepted by the fire department with annual fire safety inspections; no annual update, radio coverage or posted contacts, § 1660.B(7)(a)

  • Plan must ensure first responders receive training; funding not assigned, § 1660.B(7)(a)(4)

  • Hazardous substances identified in the decommissioning plan, § 1323.F(2); no storage setbacks or containment

  • Annual fire safety inspections by a qualified professional, § 1660.B(7)(a)(5)

  • Section 1660.B(10) and Section 1323.C(1) of the draft require a CEIA for every data center that addresses existing and generated peak and nonpeak traffic volumes and the condition of the streets serving the site, under PennDOT study methods, but do not address construction traffic or set a study area reaching the nearest arterial or interchange.

  • Security of at least 110% and notice within 30 days of cessation, but decommissioning need only begin within 180 days, § 1323.F(4) and (7) and § 1660.B(11)(c)

  • Estimate and security updated every five years; no first-year update, § 1323.F(5)

  • Quarterly groundwater withdrawal and monitoring reports, § 1323.D(4)(b)(12)(d)

  • Failure to update decommissioning estimates or security may lead to permit revocation, § 1323.F(5); otherwise general enforcement

  • Section 1323.G(7)(d) of the draft has the applicant pay for expert review of the CEIA, which is reviewed by the Board of Supervisors or Zoning Hearing Board with the conditional use, and Section 1660.B(5)(e) has the applicant fund a Township-selected water study.

  • Only existing and proposed ownership of the tract, § 1323.B(2); developer, operator and end user not required

Benefits & exceptionsHide benefits & exceptions1
  • Proposed approval pathway: Proposed: conditional use in the Industrial District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data