Penn Township

Anti-Data Center Policies

Penn Township’s enacted ordinance allows data centers but requires cooling and water-use measures, noise limits and testing, and setbacks from homes and other protected places, adding construction and compliance costs.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Penn Township
The rules are in Ordinance 2026-02, which the Board of Supervisors adopted on June 8, 2026.Penn Township, Lancaster County — data-center ordinance (No. 2026-02)

What this means

The measure imposes cooling and water-use rules, noise limits and sound testing and setbacks from homes or other protected places. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements21
  • Limited Commercial (LC) District only, Table 27-202.4

  • Setback also applies to properties used for community purposes, Ordinance 2026-02, § 27-402

  • 60 dBA day and 50 dBA night at residential lot lines, 65 dBA commercial, Ordinance 2026-02, § 27-402

  • Acoustic study by an acoustical engineer before approval; no later study, Ordinance 2026-02, § 27-402

  • Generator testing weekdays 9 a.m. to 5 p.m.; no hours cap, Ordinance 2026-02, § 27-402

  • Public water required and wells barred outright, with provider capacity letter, Ordinance 2026-02, § 27-402

  • Any water cooling must be closed-loop; evaporative cooling not expressly restricted, Ordinance 2026-02, § 27-402

  • Daily intake volume disclosed in water utilization report; no drought plan, Ordinance 2026-02, § 27-402

  • Discharge volumes and destinations reported, Ordinance 2026-02, § 27-402

  • EPA Tier 4 generators with annual testing reported to the Township, Ordinance 2026-02, § 27-402

  • Thermal impact mitigation plan including waste heat reuse, Ordinance 2026-02, § 27-402.

  • E-waste plan for servers, batteries, and hazardous materials; refrigerants not named, Ordinance 2026-02, § 27-402

  • Capacity letter for water only; no electric utility letter

  • Energy management plan; renewables encouraged but not required, Ordinance 2026-02, § 27-402

  • On-site generation mentioned only as an energy plan option

  • 100 ft buffer yard along residential and community properties, Ordinance 2026-02, § 27-402.

  • Ground equipment enclosed or screened by a solid barrier; no height or acoustic standard, Ordinance 2026-02, § 27-402

  • Emergency response plan given to emergency responders for comment, Ordinance 2026-02, § 27-402

  • Hazardous materials named only in the e-waste plan

  • Annual generator emissions test reports only; no noise, water, or power reports, Ordinance 2026-02, § 27-402

  • Only an emergency contact must be named

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Special exception in the Limited Commercial (LC) District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data