Penn Township

Anti-Data Center Policies

Penn Township requires data centers to meet noise limits, undergo sound testing, observe setbacks from homes and other protected places, and meet water-supply requirements, increasing costs without preventing approval.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Penn Township
The Board of Supervisors enacted Ordinance 183, which amends Zoning Ordinance No. 166, on October 13, 2026 after a public hearing, according to the posted meeting minutes.Penn Township, Butler County — data-center ordinance (No. 183)

What this means

The measure imposes noise limits and sound testing, setbacks from homes or other protected places and water-supply requirements. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements27
  • I-L Limited Industrial only, use table, § 2.07

  • 60 ft height limit, § 18.55(3)

  • 300-ft stream and wetland setback and impact analysis, § 18.55(5)(f), (15)

  • CNEL 55 dBA day and 45 dBA night at the boundary of sensitive receptor properties; daytime limit above 50 dBA, § 18.55(7)(a)

  • CNEL 55 dBC day and 45 dBC night at sensitive receptor boundaries, § 18.55(7)(a)

  • Preliminary and as-built studies; none at building permit, § 18.55(7)(d)

  • Public water required, private wells barred as primary source; no hydrogeologic study, § 18.55(16)

  • Least water-use cooling required; closed loop not mandated, § 18.55(16)(b).

  • NPDES evidence for cooling discharge, may be deferred to land development, § 18.55(1)(c)

  • Tier 4 generators; no emissions testing or reports, § 18.55(12)(b)

  • Disposal of materials must comply with regulations, § 18.55(15)(c)

  • Utility interconnection agreement and approval before construction; no electrical inspection, § 18.55(10)

  • Own generation or interconnection, solar-ready roofs; no required renewables, § 18.55(10), (12)

  • Substations screened, side or rear placement, 34.5 kV lines buried, § 18.55(11)

  • Residential cost offsets, utility financial security; grid upgrades not expressly assigned, § 18.55(10)(b), (c)

  • Buffers of 75 to 200 ft by size; the 200-ft planted berm applies only to large sites next to sensitive receptors, § 18.55(14)(c)

  • Ground and rooftop equipment screened; no 12-ft or acoustic standard, § 18.55(14)(b)

  • Line-of-sight siting only; no study or renderings required, § 18.55(2)(b)

  • Emergency plan reviewed by fire department and 24-hour contact; no annual update or radio coverage, § 18.55(17)

  • Plan must ensure responder training; no funding, § 18.55(17)(a)(ii)

  • Materials stored must be described; no containment or setbacks, § 18.55(15)(a)

  • Annual fire safety inspections; no electrical inspection, § 18.55(17)(a)(iii)

  • Vehicle trips described; no traffic impact study, § 18.55(15)(a)

  • Plan with security of at least 100 percent of net cost; no notice or removal timeline, § 18.55(20)

  • As-built sound study six months after occupancy, further studies at Township option, § 18.55(7)(d)(ii)

  • As-built noise exceedance is an ordinance violation; no specific penalties, § 18.55(7)(d)(ii)

  • Third-party validation allowed and review fees paid by applicant, § 18.55(1)(b), (d)

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the I-L Limited Industrial District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data