Ontelaunee Township
Anti-Data Center Policies
Ontelaunee Township’s enacted ordinance requires setbacks from homes and other protected places, minimum site sizes, and cooling and water-use limits. It still allows an approval route for data centers, but narrows where and how they can operate.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Ontelaunee TownshipThe Board of Supervisors adopted Ordinance No. 2026-3 on October 1, 2026, according to the signed certificate of enactment, and it took effect five days after enactment.Ontelaunee Township, Berks County — data-center ordinance (No. 2026-3)
What this means
The measure imposes setbacks from homes or other protected places, minimum site-size requirements and cooling and water-use rules. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements31
90-ft maximum height, § 555.A(1)
Groundwater hydrological study only; no riparian buffer or environmental assessment, § 555.Q
Section 555.A(13) requires 1,000 ft from any data center on another property, but the definition in Section 1 only lets equipment on adjacent parcels in a single land development plan be counted with the data center and does not regulate commonly controlled lots as one use.
Three-building cap only; no new approval for expansion, § 555.A(4)
Section 555.H(1) sets 50 dBA day and 45 dBA night at residential and sensitive receiving properties as 5-minute Leq values measured with a Type 1 meter under ANSI/ASA S1.13 and S12.18 by a qualified acoustical consultant.
60 dBC day and 55 dBC night at residential and sensitive receiving properties, § 555.H(1)
Section 555.I requires preliminary, interim, as-built, and quarterly noise studies using ANSI S1.4 meters, but the as-built study is not required at full operating load.
Testing capped at 50 hours per year; no daytime limit, § 555.R(3)
Public water required and on-lot wells barred, with a water study by a hydrogeologist, § 555.N and P
Section 555.A(10) requires a closed-loop liquid cooling system and bars air cooling as the primary system, but the definitions allow cooling towers and no water-use rate or noise showing is set for any evaporative system.
Quantity of water required disclosed; no cap, reporting, or drought plan, § 555.P
Cooling fluids and condensate must be hauled off site and never discharged; no plan approval, § 555.A(10)
Cooling discharge barred from stormwater and battery fire runoff to be contained, § 555.A(10) and A(12)
Natural gas generators must meet state and federal air rules, with annual monitoring reports; no Tier 4, § 555.A(11) and R
Decommissioning removes electronic equipment, batteries, and generators, recycled where practical; no plan for refrigerants, § 555.W
Utility interconnection agreement with the application; no third-party electrical inspection, § 555.K.
On-site generation limited to temporary emergency use, § 555.M
Electrical service components concealed or screened when visible from homes; no line burial, § 555.M
Battery systems must meet applicable fire, building, and electrical codes, § 555.A(12)
Known impacts on electric rates or availability must be noted, § 555.K
Berm and dense planted buffer within the setback next to homes; width not set, § 555.V(3)
Facade articulation required every 100 ft, § 555.V(1).
Ground and rooftop equipment screened with noise mitigation; no 12-ft standard, § 555.V(2)
Emergency Response Plan approved by the fire chief; no annual updates, radio coverage, or posted contacts, § 555.B
Section 555.F and G require the data center to provide annual responder training at its expense and to supply specialized equipment to the fire company, but training is not required before occupancy and the equipment is given to responders rather than kept on site.
Secondary containment for cooling fluids and battery spills; no storage setbacks, § 555.A(10) and A(12)
Secondary emergency access required, § 555.D
Section 555.W requires decommissioning within 6 months with security of at least 125 percent of net cost, but the agreement is not recorded and the section does not address removal or lawful reuse of buildings.
Quarterly noise studies and an annual air quality report, § 555.I(4) and R
Remediation of noise violations and Township completion of decommissioning; no specific penalties, § 555.I and W
Applicant pays for its own noise studies; no Township expert review, § 555.I
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the GI General Industrial District