Borough of Olyphant

Anti-Data Center Policies

Olyphant’s enacted rules require setbacks from protected places and limit building height, increasing project costs without barring all data centers.

Incentives

Financial Incentive
2

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Olyphant Borough
The rules are in Ordinance No. 3 of 2026, whose text states that it was adopted on April 14, 2026, and Borough Council confirmed it through a June 9, 2026 settlement of the Triboro Commerce Park lawsuit, although news reports in April 2026 had described the April 14 vote as a rejection of the draft.Olyphant Borough, Lackawanna County — data-center ordinance (No. 3 of 2026)

What this means

The measure imposes setbacks from homes or other protected places and building-height limits. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements22
  • Conditional use; no approval expiration

  • 80 ft height limit

  • Must satisfy state riparian buffer rules, 25 Pa. Code 102.14

  • Base ordinance Section 809 limits apply; values not stated

  • Tonal adjustments only; no dBC limit

  • Preliminary study before approval and as-built study within 6 months

  • Generator testing hours not limited

  • Water feasibility study for nonpublic sources

  • Cooling method not required to be disclosed

  • Projected water needs disclosed

  • General description of water release; no cooling discharge plan

  • Stormwater management plan required

  • Must meet federal and state air quality rules

  • Utility verification before occupancy, with third-party electrical inspection

  • Substations counted as accessory uses with setbacks

  • Section J.a names Olyphant Borough Electric as the provider, requires the applicant to certify an end-user agreement and a service agreement to reimburse the borough, and makes the applicant pay all supply lines and the substation, while Section J.b requires utility verification of capacity before the certificate of occupancy.

  • 50 ft woodland buffer

  • Section D.a prohibits uninterrupted blank walls visible from a public right-of-way and requires walls longer than 200 ft to incorporate facade recession, offsets, and extrusions, with screening of roof-mounted equipment.

  • Rooftop equipment screened on four sides; fencing required

  • Radio coverage and posted 24-hour contacts; no emergency plan

  • Third-party electrical inspection before occupancy; no annual inspection

  • One as-built sound study after opening

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the CM-2 district

Sources

current law · Olyphant Borough
Council approved a resolution for a curative amendment to the zoning ordinance, and the solicitor reported the pending Triboro lawsuit.Olyphant Borough, Lackawanna County — data-center resolution unnumbered resolution 2026-05-12

What this means

The measure starts a protected period for local officials to fix gaps in their zoning rules. This can delay developers who need to challenge the old rules, but it does not by itself prohibit every data-center project.