Northampton Township
Anti-Data Center Policies
Bucks County’s Newtown-area ordinance allows data centers through an approval process but limits where and how they can operate, with setbacks, minimum site sizes, and noise controls.
Rating and summary from Bucks County as there are no scored current or future laws outside temporary restrictions for Northampton Township.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
pending · Northampton TownshipThe Board of Supervisors voted 4-0 on August 26, 2026 to advertise a hearing, the county Planning Commission reviewed the amendment on October 7, 2026, and the Board's October 28, 2026 agenda listed the public hearing, but no outcome had been posted as of October 29, 2026.Northampton Township, Bucks County — proposed data-center ordinance (None Adopted)
What this means
The proposal would impose technical studies and utility checks, noise limits and sound testing and setbacks from homes or other protected places. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements15
I-1 Planned Industrial/Office District only, § 27-602.1.B(7)
Conditional use; no approval expiration, § 27-602.1.B(7)
250-ft setback from all lot lines, not measured from homes, § 27-602.1.B(7)(a)3)
45-ft maximum height, § 27-602.1.B(7)(a)6)
Environmental and Community Impact Analysis required, § 27-602.1.B(7)(j)
Noise study before construction and post-construction study, § 27-602.1.B(7)(f)
Utility certification of water service, § 27-602.1.B(7)(g)
Cooling method not addressed
Certification from power utilities that use can be served; no inspection, § 27-602.1.B(7)(g).
100-ft side and rear yard buffer, not specified as planted, § 27-602.1.B(7)(d)
Lighting plan; shielded with no spillover, § 27-602.1.B(7)(h)
Facades must use variant texture and design, § 27-602.1.B(7)(e)
Perimeter fencing and security plan only, no equipment screening, § 27-602.1.B(7)(i)
One post-construction noise study, § 27-602.1.B(7)(f)
Developer, operator, and end user not required
Benefits & exceptionsHide benefits & exceptions1
Proposed approval pathway: Proposed: conditional use in the I-1 district
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data