Borough of Northampton
Anti-Data Center Policies
Northampton Borough’s enacted rules require data centers to manage cooling and water use, meet noise limits and testing requirements, and keep setbacks from homes and other protected places; approval remains possible, but compliance and review can cost more.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Northampton BoroughBorough Council adopted the rules in Ordinance No. 1244 on October 14, 2026, according to the signed ordinance posted on eCode360, before the Lehigh Valley Planning Commission meetings that listed its October 9, 2026 review of the amendment.Northampton Borough, Northampton County — data-center ordinance (No. 1244)
What this means
The measure imposes cooling and water-use rules, noise limits and sound testing and setbacks from homes or other protected places. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements29
50 ft including roof-mounted equipment, but the I-2 district limit for other buildings is not shown in the text, § 250-30.1.B.a
Environmental impact assessment covering critical impact areas, including riparian buffers and streams, required with the application, § 250-30.1.H
Any change to the approved cooling method or closed-loop system that increases water, wastewater, or utility demand requires prior Borough approval and may require a new conditional use; no other expansion triggers, § 250-30.1.M.b
55 dBA weekday daytime and 50 dBA nighttime and weekends at the property line, with ANSI S1.4 meters; higher than 50 and 45 dBA, § 250-30.1.E.a
Preliminary, interim, and as-built sound studies six months after occupancy using ANSI S1.4 meters, but the as-built study is not required at full operating load, § 250-30.1.E.a
Vibration study and pre- and post-construction studies showing no vibration perceptible beyond the property line; perception standard with no numeric limit, § 250-30.1.E.d
Utility will-serve letter or water resources impact study with 48-hour pumping tests and six monitoring wells; public water for cooling not required, § 250-30.1.F
Cooling method disclosed and water-cooled systems must be closed-loop; evaporative systems not limited to a stated rate, § 250-30.1.M.b
Projected average and peak water demand disclosed in the water resources impact study; no metered reporting or drought plan, § 250-30.1.F.d
Evidence of adequate sewage disposal and a utility adequacy letter with the application; no cooling or process wastewater route with permits, § 250-30.1.F.a-b
Stormwater management plan complying with Chapter 137 and a system to contain fuel, grease, and oil spills; no added treatment for runoff from equipment areas, § 250-30.1.H.b and M.a
Energy generation equipment must meet EPA Tier 4 or equivalent, with annual testing and reports to the Borough, § 250-30.1.I.e-f
Electronic Waste Plan for servers, hazardous material, and batteries; refrigerants and a disposal contract not named, § 250-30.1.M.c
Electric provider capacity certification and an interconnection agreement required with the conditional use application, before a zoning permit, § 250-30.1.I.b-c
Energy Management Plan with annual demand certified by an engineer; rooftop solar only encouraged, § 250-30.1.I.a and I.g
On-site generation for normal operation is a separate use approved under its own zoning rules; equal noise and emission standards not stated, § 250-30.1.I.d
Substations are a data center accessory use subject to the buffer and screening rules; no line burial standard, Section 205-7 and § 250-30.1.C
Battery storage must comply with NFPA 855 with battery-specific fire suppression, § 250-30.1.J.b
Only known impacts on electric rates must be noted; grid upgrades and their costs not addressed, § 250-30.1.I.b-c
50-ft evergreen buffer yard on all property lines with dead plants replaced; smaller than 100 ft, § 250-30.1.C
Equipment within 400 ft of roads, residential districts, or sensitive receptors enclosed or screened, with an 8-ft perimeter fence; not all equipment screened to its own height, § 250-30.1.D
Architect or engineer elevations required; no visual impact study, § 250-30.1.K.a
Emergency Response Plan reviewed and accepted by the fire department, with radio coverage; no annual update, walk-through, or 24-hour contacts, § 250-30.1.J
Plan must ensure responders receive system-specific training; no annual training or equipment at applicant cost, § 250-30.1.J.a.5
Spill containment for fuel and oils and fuel storage safety specifications; no storage setbacks or spill plan filed, § 250-30.1.M.a and I.e
Annual fire safety inspections by a qualified professional; no report to a municipal fire official, § 250-30.1.J.a.6
One as-built sound study and an initial post-construction vibration study after opening; no ongoing reports, § 250-30.1.E.a.3 and E.d.1
Borough may revoke zoning permits when an owner fails to remediate a sound or vibration violation, with no notice and hearing stated and no citation to MPC Sections 616.1 and 617.2, § 250-30.1.E.c and E.d.4
All studies by independent professionals at applicant cost, and the Borough may require peer review by a professional it selects at the applicant's expense, § 250-30.1.E.e
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the I-2 Industrial District
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data