North Strabane Township

Anti-Data Center Policies

Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.

Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for North Strabane Township.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

pending · North Strabane Township
The unnumbered draft, last revised October 16, 2026, has not been adopted, and although the township had set the public hearing for November 24, 2026, the Board of Supervisors' October 27, 2026 agenda listed a vote on rescheduling it, with no new date posted.North Strabane Township, Washington County — proposed data-center ordinance (None Adopted)

What this means

The proposal would impose setbacks from homes or other protected places, minimum site-size requirements and cooling and water-use rules. The limits sharply reduce usable sites or workable project designs, making development substantially harder despite an available approval route.

Restrictions & requirementsHide restrictions & requirements22
  • Allowed only in I-1 and set back 2,000 ft from A-1 and A-2 district property lines; no preserved farmland or agricultural security area bar, § 27-1303.61.C

  • Section 27-1303.61.C requires the principal data center building, data center support equipment, and power generation facilities to be at least 2,000 ft from any sensitive receptor, which Section 27-201 defines to include existing residences, and from A-1 and A-2 district property lines.

  • Environmental impact assessment required, § 27-1303.61.K

  • Township noise limits of 60 dBA at residential lot lines apply through required noise modeling; no separate day and night limits, § 27-1401.C and § 27-1303.61.K(2)(l)

  • Added 70 dBC limit at residential lot lines, above 60 dBC, and low-frequency noise analysis required, § 27-1401.C(1) and § 27-1303.61.K(2)(l)

  • Noise modeling with the environmental impact assessment before approval; no later studies, § 27-1303.61.K(2)(f) and (l)

  • Water feasibility study with hydrogeologic modeling where public water is unavailable; no well ban or pump tests, § 27-1303.61.G

  • Cooling equipment using water must be closed loop, and closed loop excludes evaporative cooling, § 27-1303.61.E and § 27-201

  • Projected daily and annual demand disclosed and a drought contingency plan for public supply; no cap or ongoing reporting, § 27-1303.61.F and G

  • Sewer provider certification and pretreatment plan for industrial wastewater; no cooling discharge plan, § 27-1303.61.H and I

  • Decommissioning requires removal and proper disposal of equipment, § 27-201 and § 27-1303.61.N

  • Utility written verification that adequate power is available; no third-party electrical inspection, § 27-1303.61.J.

  • Power supply narrative, grid impact study, and load-shedding plan; renewable integration only analyzed, § 27-1303.61.J and K(2)(k)

  • On-site power generation regulated as a separate principal use and subject to the 2,000-ft setback, § 27-1303.61.J(5) and C.

  • Substations counted as data center support equipment subject to the setback; no screening or burial rule, § 27-201

  • Buffer Yard A around the site under § 27-1402; width not stated in the amendment, § 27-1303.61.D

  • Plan accepted by the fire department, updated annually, with 24-hour contacts; no in-building radio coverage, § 27-1303.61.L

  • Spill containment procedures; no storage setbacks, § 27-1303.61.L(7)

  • Annual fire safety inspections, § 27-1303.61.L(4)

  • 125% security and removal within 180 days of the final abandonment determination; no operator notice of closure, § 27-1303.61.M and N

  • Security updated every 3 years or at transfer; not after the first year, § 27-1303.61.N(4)

  • Decommissioning plan reviewed by the Township Engineer; cost not assigned, § 27-1303.61.N(1)

Benefits & exceptionsHide benefits & exceptions1
  • Proposed approval pathway: Proposed: conditional use in the I-1 Industrial District