Loading map…

North Middleton Township

Neutral Data Center Policies

North Middleton Township allows data centers in designated districts through special or conditional-use review, providing a permitting route but potentially adding time and uncertainty.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · North Middleton Township
The current rules are in Ordinance 2025-06, which the Board of Supervisors adopted on October 16, 2025.North Middleton Township, Cumberland County — data-center ordinance (No. 2025-06)

What this means

The measure provides a route for data centers through a special permit or conditional-use review in designated districts. That offers legal certainty, but the extra approval step can add time and uncertainty.

Restrictions & requirementsHide restrictions & requirements20
  • Conditional use before Board of Supervisors, no expiration of approval, Tables 204-19A and 204-20A

  • 100-ft setback from residential use or district, § 204-49ZZ(2)(a)

  • Water resources impact study covering streams within 1/4 mile, § 204-49ZZ(2)(k)

  • 55 dBA day, 45 dBA night at property line, § 204-49ZZ(2)(l)

  • Section 204-49ZZ(2)(l) bars sound more than 10 dBA above pre-development ambient, with 55 dBA day and 45 dBA night maximums at the property line, but the ambient is not defined as L90, no method for measuring it is stated, and no floor is set below which the cap does not apply.

  • Octave band frequency analysis required, no dBC limit, § 204-49ZZ(2)(l)

  • Section 204-49ZZ(2)(l) requires preliminary (before preliminary approval), interim (building permit), and as-built studies six months after occupancy using ANSI S1.4-2014 meters, but the as-built study is not required at full operating load.

  • Generators must meet sound limits; no testing hours limit

  • Vibration study against § 204-37(B)(1) standard, § 204-49ZZ(2)(m)

  • Hydrogeologic feasibility study with pump tests; no ban on wells for cooling, § 204-49ZZ(2)(k)

  • Peak water demand calculations required, § 204-49ZZ(2)(k)

  • Section 204-49ZZ(2)(n) requires disposal of domestic, cooling, and industrial wastewater to be approved by the Sewage Enforcement Officer or PA DEP, but it does not state that the approval must be shown before the zoning permit.

  • Utility service approval before preliminary plan approval; no electrical inspection, § 204-49ZZ(2)(g).

  • Base buffer rules of § 204-26 stated as applying; no width set, § 204-49ZZ(2)(c)

  • Screening per § 204-26 stated as applying, § 204-49ZZ(2)(c)

  • Emergency plan accepted by fire department and EMS; no annual update, § 204-49ZZ(2)(i)

  • First responder training required, no funding, § 204-49ZZ(2)(i)

  • Emergency plan for data centers or BESS must provide for annual fire safety inspections, § 204-49ZZ(2)(i)

  • Traffic study only when required by SALDO § 180-44, § 204-49ZZ(2)(j)

  • As-built sound study six months after occupancy, § 204-49ZZ(2)(l)

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the C/LI and IND zones

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data