North Manheim Township
Anti-Data Center Policies
North Manheim Township’s enacted ordinance requires data centers to follow cooling and water-use rules, set aside money for eventual removal, and meet noise limits with sound testing. Approval remains possible, but these requirements add costs.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · North Manheim TownshipRegulates where and how data centers may be built and operated in North Manheim Township.North Manheim Township Data Center Ordinance (public hearing copy)
current law · North Manheim TownshipThe current rules are in Ordinance 157, which the Board of Supervisors adopted on July 7, 2026.North Manheim Township, Schuylkill County — data-center ordinance (No. 157)
What this means
The measure imposes cooling and water-use rules, money set aside for eventual removal and noise limits and sound testing. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements25
35-ft height limit; no rooftop equipment limit, § 518.3
Environmental and community impact analysis required, § 518.13
70 dBA day and 60 dBA night at the property line, § 518.5
Same 70/60 limits also in dB(C), above rubric levels, § 518.5
Section 518.5 requires preliminary, interim, and as-built sound studies using ANSI S1.4-2014 sound level meters, with the as-built study six months after the certificate of occupancy, but the measurements cover normal operations and testing and no study is required at full operating load.
Testing covered by noise limits; no hours cap or daytime rule
Vibration study showing none past the property line, § 518.6.
Public water required with authority certification; no well study, § 518.7
Closed-loop required; open evaporative towers prohibited without exemption, § 518.12.
Impact on water supply must be evaluated; no cap or drought plan, § 518.13
Sewer authority must certify treatment; no cooling discharge plan, § 518.7
Heat island impacts must be disclosed, § 518.13
Batteries, fuel, and refrigerants disposed per law at decommissioning, § 518.17
Utility certification of capacity; no electrical inspection, § 518.10.
Power generation is a separate use with its own approval and setbacks, § 518.10 and § 518.15.
Section 518.9 requires a change in material, pattern, texture, color, or accent every 150 horizontal feet and fenestration of at least 30 percent of each facade, but addresses materials and color only through general high-quality design language.
Ground and roof equipment screened, § 518.4
Elevations, sketches, or sight line studies, § 518.9
Emergency plan accepted by Fire Marshal and EMA with 24/7 hotline; no annual update or radio, § 518.11
Plan must ensure responder training; no funding, § 518.11
Annual fire safety inspections, § 518.11
Bond or letter of credit for actual cost; 18-month removal, not 110% or 6 months, § 518.17
Bond reviewed every five years; no first-year update, § 518.17
Semi-annual sound studies after the as-built study, § 518.5
Independent acoustical expert; Township may require cooling validation, § 518.5 and § 518.12
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Special exception in the Industrial District