North Londonderry Township

Anti-Data Center Policies

Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.

Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for North Londonderry Township.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

pending · North Londonderry Township
Would allow data centers in North Londonderry’s I-1 industrial districts, subject to requirements for site size, noise, utilities, emergency response, ongoing reporting, and decommissioning.North Londonderry Township Ordinance amending Chapter 150 (Zoning) to define data centers and permit them in I-1 Industrial Districts

What this means

The draft would allow data centers in I-1 industrial districts, but development and operation would carry meaningful burdens: large lots and setbacks, extensive technical and emergency-safety studies, ongoing noise and resource reporting, and costly decommissioning funds. These conditions could add substantial time and expense, though the proposal does not ban data centers outright. The draft sets site and application requirements

People behind it

  • Assistant township manager who worked with the township solicitor to prepare and revise the initial draft.

  • Township solicitor who developed the ordinance framework and worked with Troup on the draft.

  • Received and is expected to review and revise the draft before making a recommendation to the Board of Supervisors.

Restrictions & requirementsHide restrictions & requirements21
  • The draft would allow data centers as a permitted use in the I-1 industrial district, rather than generally throughout the township. Permitted use in the I-1 Industrial Districts

  • A data center must be on a lot of at least 10 acres. Minimum lot area

  • Front, side, and rear setbacks must be at least 200 feet; when adjoining a residential zone or use, the setback must be at least 250 feet. Setback requirements

  • The principal building may be no taller than 75 feet, including roof-mounted equipment; accessory uses may not exceed the principal building’s height. Height limits

  • Impervious coverage may not exceed 50%, and landscaping, parking, and loading must comply with specified existing zoning-code articles. Coverage, landscaping, parking, and loading standards

  • An application must include a sketch plan and a traffic impact study meeting the Lebanon County SALDO requirements. Application requirements

  • Applicants must submit noise studies by an acoustical professional at application, during building-permit review, and six months after the certificate of occupancy; the township may request further as-built studies. The studies must address the limits of 67 dB(A) during weekday days and 57 dB(A) at night and on weekends. During power outages, those limits do not apply, but the studies must report anticipated sound with emergency generators running. Noise limits and study phases

  • Applicants must provide a qualified professional’s vibration study showing that vibration will not be perceptible to people beyond the property line. Vibration study requirement

  • The project must use public water, with documentation that the authority can and will supply the needed amount; it must also document approved wastewater disposal for domestic, cooling, and industrial wastewater. Closed-loop cooling is encouraged, not required. Water and sewer requirements

  • If connecting to the electric grid, the applicant must document available capacity and the provider’s willingness to serve, and note known project impacts on electric rates or availability for other uses. Power supply documentation

  • Any energy-generation system intended to supply the data center during normal operations is treated as a separate use and must be approved under the zoning rules applicable to that use. Separate approval for normal-operation generation

  • Applicants must submit an emergency response plan for review and acceptance by local fire and emergency-management services during land development. It must address emergency procedures and show adequate second access; written fire-department approval of emergency access, truck turning, fire suppression, and hydrant availability is also required. Emergency response plan and access requirements

  • The data center must fund annual training for Citizens Fire Company #1 firefighters and leadership and Penn State Health Life Lion EMS personnel on responding to emergencies involving electrical equipment, battery storage, natural gas, and backup generators. Annual responder training at the data center’s expense

  • Projects with battery storage or other energy-storage devices must demonstrate compliance with NFPA 855 or similar standards and install fire-suppression systems designed for battery storage. Energy-storage safety requirements

  • Approval is barred unless the applicant demonstrates that fire suppression, containment, ventilation, and evacuation procedures sufficiently protect public health, safety, and welfare. Safety demonstration required for approval

  • Operators must conduct and submit a noise study each year by July 1. If it shows the limits are exceeded, they must submit and implement a mitigation plan within six months. Annual noise study and mitigation deadline

  • Generator testing and routine maintenance are limited to weekdays from 9 a.m. to 6 p.m., for no more than one hour per unit per week. Generator testing and maintenance limits

  • Operators must report the previous calendar year’s water use and electricity use by July 1 each year. Annual water and electricity reporting

  • Operators must maintain approved landscaping and promptly replace screening trees or shrubs that die or become diseased; they must also provide emergency responders and the township an emergency contact list and update it within 10 days of any change. Ongoing landscape and contact-list duties

  • Decommissioning must be completed at the data center’s expense within six months after the facility’s useful life ends. A drop in electricity use of more than 75% from peak for 12 continuous months creates a presumption that useful life has ended, and the township must be notified within 30 days of such a drop. Decommissioning includes removing electronic equipment, battery storage, and backup generators. Decommissioning trigger and deadline

  • Applicants must submit decommissioning-cost estimates for township review by the zoning-permit date and every five years thereafter, and maintain financial assurance of at least 125% of net decommissioning costs in a form and institution acceptable to the township. Decommissioning estimates and financial assurance

Benefits & exceptionsHide benefits & exceptions2
  • Data centers are added as a permitted use in I-1 industrial districts, subject to the ordinance’s site, application, and operating requirements. “Data Centers as a permitted use”

  • A data center may include accessory facilities on the same tract or a unified development of adjacent parcels, including substations, utility lines, cooling and water facilities, and generators for temporary power interruptions. Energy generation intended to power the center during normal operations is excluded from this accessory-use provision. “A Data Center may include Data Center Accessory Uses”

Sources

pending · North Londonderry Township
The planning commission received the draft on August 17, 2026, and will review and revise it before recommending it to the supervisors, who must hold a public hearing before adoption.North Londonderry Township, Lebanon County — proposed data-center ordinance (None Adopted)

What this means

The proposal would impose money set aside for eventual removal, technical studies and utility checks and noise limits and sound testing. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements23
  • Permitted use with standards, § 150-61

  • 67 dBA day, 57 dBA night at property line, Sec. II.C

  • Section II.C requires preliminary, interim, and as-built studies, the last six months after occupancy, using ANSI S1.4 meters.

  • Section III.E limits generator testing to weekdays from 9 a.m. to 6 p.m. and to one hour per week per unit.

  • Imperceptible beyond property line, vibration study, Sec. II.C.3.

  • Must be served by public water with certification, Sec. II.D

  • Closed-loop cooling only encouraged, Sec. II.D

  • Annual water use report, no drought plan, Sec. III.F

  • Section II.D.2 requires the applicant to show that domestic, cooling, and industrial wastewater disposal is approved by the Sewage Enforcement Officer or DEP, with no stated timing.

  • Removal of electronics, batteries, generators; recycling encouraged, Sec. IV

  • Utility capacity certification; no electrical inspection, Sec. II.E.1.

  • Electricity use reported but no energy plan, Sec. III.G

  • Rate impacts must be noted, Sec. II.E.1

  • Landscaping per Article XVI, no buffer width, Sec. I.1.F

  • Sketch plan only

  • Emergency plan accepted by fire department, Sec. II.F.1

  • Annual fire safety inspections, Sec. II.F.1.e

  • Section II.B requires a traffic impact study in every case in accordance with the Lebanon County SALDO.

  • Second emergency access required, Sec. II.F.1.c

  • Section IV requires security of 125 percent of net cost, 30-day notice, and removal of equipment, batteries, and generators within six months, with consent to Township action given by the zoning permit.

  • Estimate at zoning permit and every fifth year, Sec. IV

  • Annual noise study and water and electricity reports, Sec. III

  • Township may set a fee to defray its review costs, Sec. III.D