North Huntingdon Township
Anti-Data Center Policies
Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.
Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for North Huntingdon Township.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
pending · North Huntingdon TownshipThe draft was sent to the Board of Commissioners with an October 9, 2026 cover memo and discussed at the October 15, 2026 work session, and no public hearing date has been posted.North Huntingdon Township, Westmoreland County — proposed data-center ordinance (None Adopted)
What this means
The proposal would impose setbacks from homes or other protected places, minimum site-size requirements and cooling and water-use rules. The limits sharply reduce usable sites or workable project designs, making development substantially harder despite an available approval route.
Restrictions & requirementsHide restrictions & requirements31
Building and impervious coverage limited to the underlying district limits only, § 832.3(B)
District height limit, but rooftop appurtenances and cooling towers may exceed it by up to 15 ft if screened, § 832.3(A)
Maximum buildout and per-phase backup generation and battery capacity stated; updated studies, not a new approval, for increases over 10%, § 832.4(Q) and § 832.5(O)
55 dBA day (text reads fifty (55)) and 45 dBA night at any property line, ANSI S1.4 meters; day limit above 50 dBA, § 832.5(A)(1)
Predictive sound study with the application by stated method; post-construction verification within 180 days not stated at full operating load, and further testing discretionary, § 832.4(E), § 832.5(A)(4), § 832.8(A)
Generator testing 10:00 a.m. to 2:00 p.m. Tuesday through Thursday, capped at 4 hours per generator per month except as required by law, § 832.5(A)(2)-(3)
Public water confirmation or water feasibility study showing sustainable yield; public water not required and no pump test, § 832.4(O) and § 832.5(F)(3)-(4)
Cooling technology disclosed and potable-water-dependent cooling prohibited unless alternatives infeasible; no closed-loop requirement or evaporative use rate, § 832.4(O) and § 832.5(F)(5)-(6)
Projected average, peak, and annual water demand disclosed; no metered reporting or drought plan, § 832.5(F)(2)
Wastewater and blowdown quantities and destinations identified, approvals to be obtained, but not required before the zoning permit, § 832.4(O) and § 832.5(F)(7)-(8)
Equipment yards and fuel storage designed to prevent releases, fuel tank secondary containment; no added runoff treatment required, § 832.5(G)(3) and (H)(2)
Must comply with federal and state air quality requirements, § 832.5(E)(1)
Electronic waste and battery management plan for servers, batteries, and cooling components; no disposal contract, § 832.4(P)
Utility impact statement and evidence of coordination with the electric utility; no capacity confirmation before the zoning permit, § 832.4(C) and § 832.5(N)(1)
Accessory substations approved as part of the use; transformer yards screened and placed to the side or rear; no line burial, § 832.3(C), § 832.5(D)(3), § 832.5(N)(3)
Battery systems enclosed with fire detection and suppression and must meet the fire code and NFPA standards, § 832.5(H)(1), (4)
Utility impact statement must say whether new transmission or substation improvements are anticipated; no cost or tariff disclosure, § 832.4(C)
50 ft planted buffer with year-round screening along roads, residential districts, and off-site dwellings, § 832.5(D)(1)-(2)
Shielded and aimed lighting with 0.1 footcandle limit at residential property, § 832.5(C)
Wall offsets at intervals of 150 ft or less and limits on untreated tilt-up panels facing roads; color and materials general, roads only, § 832.5(M)
Equipment yards visible from roads or adjacent property screened to the maximum extent practicable, § 832.5(D)(3)
Emergency Response Plan accepted by the fire department, annual certification or revision, posted 24-hour contacts; no annual walk-through, § 832.5(I), § 832.5(L)(3), § 832.8(B)
Operator must offer and fund responder training before occupancy and periodically; no annual requirement or specialized equipment, § 832.5(I)(1)(iv)
Hazardous materials summary and fuel tank secondary containment; no storage setbacks, § 832.4(I) and § 832.5(H)(2)
Annual fire safety inspections by a qualified professional; no report to a municipal fire official or correction deadline, § 832.5(I)(1)(v)
Traffic impact study required; scope not stated, § 832.4(D)
Recorded decommissioning plan, 110% security before construction, discontinuance after 12 months and decommissioning or lawful conversion within 180 days, removal of all structures, § 832.7
Cost estimate updated every 3 years with security adjusted within 30 days; no update after the first year, § 832.7(E)(iii) and (H)
One post-construction compliance report within 180 days per phase, § 832.8(A)
Consultant review at applicant expense for the water utilization report only; other studies reviewable but cost not assigned, § 832.4(O) and § 832.6(F)
Operator type in the narrative and a posted sign naming the entity controlling the data center; end user not required, § 832.4(A) and § 832.5(I)(3)
Benefits & exceptionsHide benefits & exceptions1
Proposed approval pathway: Proposed conditional use in the Industrial, PEDD-1, and PEDD-2 districts