North Coventry Township

Anti-Data Center Policies

Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.

Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for North Coventry Township.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

pending · North Coventry Township
The Planning Commission discussed the draft in September 2026 and no hearing or vote has been scheduled, while the applicants for a data center at the Coventry Mall withdrew their Zoning Hearing Board application on October 6, 2026, which canceled the October 22, 2026 hearing.North Coventry Township, Chester County — proposed data-center ordinance (None Adopted)

What this means

The proposal would impose setbacks from homes or other protected places, minimum site-size requirements and cooling and water-use rules. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements28
  • Conditional use by Board of Supervisors; no approval expiration

  • Section C(3) applies a 1,000-foot setback to the data center, accessory uses, and associated equipment only where an existing dwelling abuts the site, while the Section E(1)(g) 1,000-foot Sensitive Receptor separation is measured from the nearest wall of a Data Center building.

  • Section C(1) caps height at 40 feet including rooftop equipment and accessory uses, but the draft leaves the district references blank and states no height limit for other principal buildings.

  • Comprehensive environmental assessment required, § I(2)

  • Section E(1)(g) requires 1,000 feet from any data center on another property, but the draft does not regulate a campus on commonly owned or controlled lots as one use beyond allowing accessory structures on a unified development.

  • Single 45 dBA limit at property lines, § F(1)(f)

  • Single 60 dBC limit, § F(1)(f)

  • Baseline study with application and post-construction study, § F(1)

  • Below human perception at property lines, with study, § F(1)(e).

  • Public water and provider capacity letter; groundwater not primary cooling source, § E(1)

  • Section E(1)(e) requires a closed-loop or air-cooled system and Section E(1)(d) bars groundwater and surface water as the primary cooling source, but evaporative systems are not expressly barred or limited to a stated water-use rate shown to meet the noise limits.

  • Daily and annual use estimates; no drought plan, § E(1)(b)

  • Cooling fluids hauled off site, no discharge; wastewater analysis with application, § E(1)(e), E(2)

  • Thermal impacts in required assessment; no reuse review, § I(2)-(3)

  • Electronic waste plan for servers and batteries; refrigerants not named, § N(1)

  • Energy usage plan; renewables only documented, § E(3)(a)

  • On-site systems part of use; later additions need amended approval, § E(3)(c)

  • 8-ft planted berm along homes and roads; no width set, § D(2)

  • Equipment screened on all sides; no height or acoustic standard, § E

  • Emergency response plan accepted by fire department; annual inspections, § F(1)

  • Section F(6) requires the data center to provide or cause to be provided annual responder training at its expense, and Section F(7) lets the Board require specialized equipment or funding, but training is not required before occupancy and equipment is not required to be kept on site.

  • Containment for battery electrolyte and glycol; no storage setbacks, § E(1)(e)-(f)

  • Annual fire safety inspections, § F(1)(e)

  • Secondary emergency access required, § F(4)

  • Construction plan for times and access; no road bond, § H

  • Section N requires decommissioning funds of at least 125% of net cost and removal of equipment, batteries, and generators within 6 months after the end of useful life, but no recorded agreement is required and the draft does not address building removal or a 2-year lawful reuse period.

  • Annual generator and community benefits reports, § E(3)(b)(7), M(3)

  • Violation and cease and desist for lapsed decommissioning funds, § N(2)

Benefits & exceptionsHide benefits & exceptions1
  • Proposed approval pathway: Not listed; draft would allow conditional use in one district

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data