North Annville Township
Anti-Data Center Policies
North Annville Township’s enacted ordinance sets setbacks from homes and other protected places, water-supply requirements, and building-height limits, increasing costs while still allowing data-center approval.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · North Annville TownshipThe rules are in Data Center Ordinance No. 1-2026, which the supervisors adopted on September 14, 2026.North Annville Township, Lebanon County — data-center ordinance (No. 1-2026)
What this means
The measure imposes setbacks from homes or other protected places, water-supply requirements and building-height limits. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements22
Environmental impact study of stream flow and temperature changes, Section 2.G.f
60 dBA day and 55 dBA night at the property line, Section 2.F.a
Section 2.F.a requires preliminary, interim, and as-built sound studies using ANSI S1.4 sound level meters, with the as-built study six months after the certificate of occupancy, but the as-built study is not required at full operating load.
60 dBA cap for up to 24 hours during outages; no testing limits, Section 2.F.a
Vibration study showing none perceptible past the property line, Section 2.F.a.5.
Section 2.G.a and b require public authority certification when public water is used, bar groundwater and wells as a water source, and require a water feasibility study for other nonpublic sources, but cooling water is not required to come from available public water.
Projected demand disclosed and use beyond the planned amount is a violation; no drought plan, Section 2.G
Section 2.G.e requires the applicant to demonstrate that adequate means of disposal for domestic wastewater and wastewater used for cooling or industrial purposes have been provided and approved by the sewage enforcement officer and/or DEP, with written approval from the public authority if public facilities are used.
Study of stream temperature impacts required; no heat reuse review, Section 2.G.f
Decommissioning plan covers disposal or recycling and lawful disposal of batteries and refrigerants, Section 2.3
Utility certification of capacity; no electrical inspection, Section 2.H.a.
Solar panels required on 25% of the roof; no energy usage plan, Section 2.H.c
Generation for normal operations is a separate use with its own approval, Section 2.H.c.
Section 2.H.a and b require a provider certification of capacity and a note of known rate impacts, and assign all utility cost increases and infrastructure costs to the owner with financial security, but the applicant is not required to disclose the needed upgrades and their cost, the tariff terms, or an executed service agreement before a zoning permit.
Section 2.C requires a 300 ft landscape strip along all property lines with a permanent two-row evergreen buffer at least six feet tall at planting and 15 feet at maturity, plus a maintenance bond for maintenance and replacement of the evergreen buffer.
Emergency plan accepted by the fire department; no annual update, radio, or 24-hour contacts, Section 2.I.a
Plan must ensure responder training; no funding, Section 2.I.b
Annual fire safety inspections, Section 2.I.c
Section 2.A requires a qualified traffic impact report under the SALDO and Township ordinances, but it does not state coverage of construction traffic or a study area reaching the nearest arterial or interchange.
Decommissioning plan and closure notice without financial security; completion within 18 months, Section 2.3
One as-built sound study after opening, Section 2.F.a.3
Sections 2.G.d.3 and 2.3.e allow the Supervisors to vote to shut down a data center that exceeds its planned water use and end the approval on an unreported ownership change, but no notice and hearing precede these actions and Sections 616.1 and 617.2 of the Municipalities Planning Code are not cited.
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the Manufacturing District
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data