Newport Township

Anti-Data Center Policies

Newport Township’s enacted ordinance requires setbacks from homes and other protected places, plus noise limits and sound testing; approval remains possible, but these restrictions limit where and how data centers can operate.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Newport Township
The current rules are in Ordinance No. 1 of 2026, the Zoning Ordinance of 2026, which the Board of Commissioners adopted on April 21, 2026.Newport Township, Luzerne County — data-center ordinance (No. 1 Of 2026)

What this means

The measure imposes setbacks from homes or other protected places and noise limits and sound testing. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements26
  • Permitted only in the Mixed Use (MU) District, § 517.2.A

  • Permitted by right, § 517.2.A

  • Barred within 400 ft of permanently preserved farmland; no agricultural security area bar, § 517.2.B(3)

  • 500-ft structure setback plus 100-ft buffer (600 ft) from residential districts and uses, § 517.2.B(2) and 5.F(1)

  • Height under 70 ft or as limited by emergency apparatus, § 517.5.H(1)

  • Barred in floodplains, wetlands, and riparian buffers and within 150 ft of Cold Water Fishery streams; environmental impact analysis required, § 517.2.B and 4.A(5)

  • Single 65 dBA limit at any property line, § 517.5.E(1)

  • Noise and generator management plan with predicted levels submitted with the zoning application, § 517.4.A(4)

  • Generator testing 9 a.m. to 5 p.m. on weekdays only; no hours cap, § 517.4.A(4) and 5.E(2)

  • Hydrologic impact study where groundwater or surface water is withdrawn; no bar on wells for cooling, § 517.4.A(3) and 5.D(4)

  • Cooling system type must be identified, § 517.5.D(1)

  • Private wells metered with quarterly reports; no drought plan, § 517.5.D(3)

  • Discharges must meet state and federal permits, § 517.4.A(3) and 5.D(1)

  • Bioretention, bioswales, infiltration, and permeable or shaded staging surfaces required, § 517.5.I.

  • Material disposal in the decommissioning plan and annual battery and coolant inventories, § 517.6.A and 8.D

  • Utility coordination plan required; no capacity confirmation, § 517.4.A(2)

  • Substation compatibility addressed; no screening or placement rule, § 517.4.A(2)

  • 100-ft vegetative buffer next to residential uses, § 517.2.B(2) and 5.F(1).

  • Rooftop equipment screened and full perimeter screening with berms or opaque fencing, § 517.5.A(5), 5.F(3) and 5.H(4)

  • Fire protection and emergency operations plan with annual coordination; no radio coverage or posted contacts, § 517.4.A(1) and 5.C(3)

  • Annual walkthrough only; no training requirement, § 517.5.C(3)

  • Annual independent third-party safety audit; no electrical inspection before occupancy, § 517.8.C

  • Two points of ingress and egress required; no arterial or collector access rule, § 517.5.B(1)

  • Bond equal to total cost (at least $250,000) and removal within six months of abandonment; not 110% and no closure notice, § 517.6

  • Bond renewed annually; no stated cost estimate update schedule, § 517.6.B

  • Annual reports on energy and water use and quarterly well reports, § 517.5.D(3) and 8.B

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Permitted by right in the Mixed Use (MU) District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data