Newberry Township’s enacted ordinance allows data centers but requires cooling and water-use controls, funds for eventual removal, and noise limits and sound testing, adding construction and compliance costs.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Newberry TownshipThe rules are in Ordinance No. 442, which the Board of Supervisors adopted on October 14, 2026 according to the signed copy posted on eCode360.Newberry Township, York County — data-center ordinance (No. 442)
What this means
The measure imposes cooling and water-use rules, money set aside for eventual removal and noise limits and sound testing. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements36
Conditional use decided by the Board of Supervisors under § 380-84, § 380-59A(65)A(1); no provision makes the approval lapse
50 ft inclusive of roof-mounted equipment and cooling towers, which may rise to 65 ft by conditional use, § 380-59A(65)C(1)(d)-(e); the text does not tie the limit to the district limit for other principal buildings, so only part of the standard is met
Environmental and Community Impact Analysis covering groundwater, stream, wetland, and aquifer impacts, § 380-59A(65)P(2)(b); no riparian buffer
A campus of buildings on adjacent parcels developed as a unified development is one Data Center, Section 1 definition; no separation distance or combined performance limits
Conditional use approval required for increases over 25 percent in footprint, electrical demand, generator capacity, or battery capacity, or a material change determined by the Zoning Officer, § 380-59A(65)Q(1); new approval is not required for any added capacity
Single limits of 50 dBA at any Sensitive Receptor and 60 dBA at nonresidential boundaries, with no separate night limit or stated measurement method, § 380-59A(65)F(2)
Noise Impact Study with pre-construction modeling and a post-construction acoustical study before occupancy, with no stated measurement method or full-load condition, § 380-59A(65)B(6) and F(3)-(4)
Routine testing limited to 7:00 a.m. to 7:00 p.m., Monday through Saturday; no hours cap, § 380-59A(65)J(2)
Vibration analysis showing compliance with industry standards identified in the report and no nuisance to adjoining properties; no numeric limit, § 380-59A(65)F(6)
Public water where available and required, with a water feasibility and hydrogeologic study for wells and other nonpublic sources; cooling water is not required to come from public water and pump tests are not required, § 380-59A(65)H(1)-(4)
Water-based cooling must use a Closed-Loop Cooling System and once-through cooling is prohibited, § 380-59A(65)H(5); evaporative systems are not limited to a stated water-use rate
Projected water demand and use disclosed in the water feasibility study; no metered reporting or drought plan, § 380-59A(65)B(10) and H(4)(a)-(e)
Cooling discharge methods must be identified, and the applicant must demonstrate that disposal of cooling and industrial wastewater has been provided and approved by the appropriate agency as part of conditional use review, § 380-59A(65)B(19) and H(7); agency approvals are also required before Township construction permits, § 380-59A(65)H(6)
Stormwater Management chapter compliance and stormwater impacts evaluated; fuel storage needs secondary containment but no added runoff treatment for fuel, generator, or transformer areas, § 380-59A(65)B(24), J(3), and P(2)(d)
Generator emissions information required with the application; no emission standard, § 380-59A(65)B(17)
Decommissioning Plan covers removal and recycling of servers, batteries, and electronic waste through licensed facilities; no plan for storage and removal during operation or disposal contract, § 380-59A(65)S(2)(d)(ii) and S(4)(h)
Written certification from the electric service provider that adequate capacity is available is required with the conditional use application, before a zoning permit, § 380-59A(65)I(2)(a)
Electrical demand analysis with peak and projected annual demand required; no design efficiency, demand by phase, or on-site renewable requirement or incentive, § 380-59A(65)B(9) and I(1)
Energy Generation System supplying normal operations is a separate principal use unless the Board finds it incidental, § 380-59A(65)I(9); no setbacks or noise and emission standards equal to other generation uses
Substations set back 200 ft from property lines and 300 ft from dwellings and fully screened, § 380-59A(65)C(2) and E(1); no side or rear placement or line burial requirement
NFPA 855, 75, and 76 and the International Fire Code, with suppression and thermal runaway mitigation, § 380-59A(65)K(1)-(2); battery setbacks apply from property lines and dwellings, § 380-59A(65)C(2), but not from wells, and no large-scale fire test data or hazard mitigation analysis is required
Required upgrades must be identified by the electric provider, and improvements are paid by the applicant or the utility provider, as applicable, § 380-59A(65)I(2)(c), I(2)(e), and I(3); no cost estimate, tariff terms, or executed service agreement
100-ft landscaped buffer next to residential districts, dwellings, and Sensitive Receptors with at least 50 percent evergreen material for year-round screening, reducible by up to 25 percent, § 380-59A(65)C(5) and D(2) and D(5); no replacement of dead plants is stated
All ground and roof equipment fully screened from view from roads, residential properties, and Sensitive Receptors, § 380-59A(65)E(1)-(3); no height standard or sound enclosures tied to the noise limits
Building elevations and renderings required and visual impacts evaluated, § 380-59A(65)B(3) and P(2)(g); no visual impact study from historic sites
Emergency Response Plan submitted to the fire company for comment, posted 24-hour contact sign, and annual certification that the plan is current, § 380-59A(65)M(1), M(3), and R(1); no acceptance by a municipal official or annual walk-through
Applicant pays the costs of facility-specific first responder training, § 380-59A(65)M(1)(e); no training schedule or specialized equipment requirement
Hazardous Materials Management Plan covering storage, containment, spill prevention, and emergency response filed with the application, and fuel storage set back 200 ft from property lines with secondary containment, § 380-59A(65)B(14), C(2), J(3), and L; no setbacks from wells or streams
Annual fire safety inspection with the report provided to the Township, § 380-59A(65)M(4); no deadline to correct deficiencies
Traffic Impact Study required under § 380-57 and the SALDO, § 380-59A(65)B(15) and N(1); the study is not required to cover construction traffic or reach the nearest arterial or interchange
Construction Traffic Management Plan with truck routes and hours of construction traffic, and road surveys and security if the Board requires them, § 380-59A(65)B(16) and I(7)-(8); no construction days and hours or required excess maintenance agreement
110 percent security posted before the building permit, § 380-59A(65)S(3)(a)-(b); no six-month removal deadline, and principal buildings may remain, § 380-59A(65)S(4)(b)
Security reviewed and adjusted at least every five years; no update after the first year, § 380-59A(65)S(3)(d)
One post-construction acoustical study before occupancy; annual reports cover contacts and plans, not noise, water, or power use, § 380-59A(65)F(4) and R(1)
Board may require independent review by Township consultants, with cost that may be charged to the applicant, § 380-59A(65)P(3)
Owner and operator information reported annually and responsible parties named in the Decommissioning Plan; end user not required, § 380-59A(65)R(1) and S(2)(d)(viii)
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the General Industrial (I) and Rural Industrial (RI) districts
Sources