Municipality of Murrysville

Anti-Data Center Policies

Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.

Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Municipality of Murrysville.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

pending · Murrysville municipality
Council held its public hearing on September 2, 2026 and tabled advertising the ordinance for enactment, and on October 27, 2026 the chief administrator said the draft is being sent back to the Planning Commission for further revisions, with no new meeting dates scheduled.Murrysville Borough, Westmoreland County — proposed data-center ordinance (None Adopted)

What this means

The proposal would impose cooling and water-use rules, money set aside for eventual removal and noise limits and sound testing. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements22
  • Section 220-31 FF.O requires a new conditional use approval for any expansion, intensification, change in operational capacity or cooling technology, increase in water or energy demand, or added accessory infrastructure, but it states no exemption for like-for-like replacement.

  • Water feasibility study for nonpublic sources and no cooling make-up water from private potable wells; no pump test, § 220-31 FF.H(2) and I(3)

  • Closed-loop cooling required and open evaporative cooling towers prohibited unless Council grants an exemption, § 220-31 FF.I(1)-(2).

  • Projected water demands disclosed, with Municipal Authority review above 100,000 gpd; no cap, reporting, or drought plan, § 220-31 FF.H(1)-(3)

  • Section 220-31 FF.H(4) requires the applicant to demonstrate that disposal of domestic, cooling, and industrial wastewater has been provided and approved by the Franklin Township Municipal Sanitary Authority or DEP, as part of the conditional use showing that precedes the zoning permit.

  • Plan must show closed-loop heat recovery opportunities; no thermal impact plan, § 220-31 FF.J(1)

  • Decommissioning plan covers e-waste removal and disposal of batteries and refrigerants; no recycling requirement, § 220-31 FF.P(7)-(8)

  • Electric provider must certify available capacity; no third-party electrical inspection, § 220-31 FF.J(2).

  • Plan to minimize energy use with PUE targets and projected kWh; no required on-site renewable generation, § 220-31 FF.J(1) and (3)

  • Primary distribution lines buried and substations counted as accessory uses; substation screening and placement not set, § 220-31 FF.J(5) and § 220-8

  • Known impacts on electric rates must be disclosed; cost of grid upgrades not assigned, § 220-31 FF.J(3)(b)

  • Landscape buffer of at least 50 ft along all property lines, § 220-31 FF.D(1)

  • Building design must follow § 220-67.1, which was not reviewed, and screens must match building materials, § 220-31 FF.E(1)(e) and L

  • Equipment within 300 ft of roads, residential districts, or sensitive receptors enclosed or fully screened; no 12-ft or acoustic standard, § 220-31 FF.E(1)

  • Emergency Response Plan accepted by the fire department, with a posted 24-hour contact sign; no annual updates or radio coverage, § 220-31 FF.K(1) and (4)

  • Plan must ensure first responders receive system-specific training; cost not assigned, § 220-31 FF.K(1)(d)

  • Secondary containment and a response plan for hazardous coolants; no storage setbacks, § 220-31 FF.I(5)(a)

  • Annual fire safety inspections; no third-party electrical inspection before occupancy, § 220-31 FF.K(1)(e)

  • Section 220-31 FF.P(3) and (5) require removal of the data center and accessory equipment within 6 months of abandonment and 110 percent security posted before building permits, but no recorded decommissioning agreement is required and no two-year lawful reuse rule for buildings is stated.

  • Section 220-31 FF.P(6) requires decommissioning cost estimates after the first year of operation and every fifth year, and requires the financial security to be updated every five years.

  • Annual certification of coolant containment integrity; no noise, water, or power use reporting, § 220-31 FF.I(5)(b)

  • Municipality may require third-party validation of the closed-loop design, cost not assigned; decommissioning engineer paid by the owner, § 220-31 FF.I(4) and P(6)

Benefits & exceptionsHide benefits & exceptions1
  • Proposed approval pathway: Proposed conditional use in the B Business District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data