Borough of Moosic
Anti-Data Center Policies
Moosic borough’s enacted ordinance requires data centers to meet setbacks from homes and other protected places and minimum site-size rules, narrowing where projects can go while retaining an approval route.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Moosic BoroughBorough Council unanimously adopted the rules as Ordinance No. 4 of 2026 on August 10, 2026.Moosic Borough, Lackawanna County — data-center ordinance (No. 4 Of 2026)
What this means
The measure imposes setbacks from homes or other protected places and minimum site-size requirements. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements19
Environmental impact statement required, Section II
65 dBA Leq day, 55 dBA Leq night, Section II.F.1
50 dBC at any hour, Section II.F.1.D
Section II.F requires a pre-construction noise study, an interim study at building permit, and a post-construction study of existing operations one to six months after the first certificate of occupancy, using ANSI S1.4 meters at a stated microphone height and weather limits.
Closed-loop cooling required; evaporative not restricted, Section II.G
Drought contingency plan only if shortage declared, Section II.G.11
Wastewater disposal plan with HVAC discharge analysis, Section II.G
EPA Tier 4 with annual testing reports, Section II.H.5 and II.O
Thermal impact and heat dissipation study, no reuse review, Section II.J
E-waste plan for servers and batteries; refrigerant disposal, Section II and II.P.
Energy management plan and solar within 12 months, Section II.H.
Known rate impacts must be disclosed, Section II.H.2
100 ft landscape buffer, Section II.D.1.
Equipment enclosed or screened, Section II.E
Plan reviewed by fire chief, 24-hour contact sign, Section II.I.1
Annual fire safety inspections, Section II.I.1
Plan, closure notice, 18 month completion, no security, Section II.P
One post-occupancy noise and water study, Section II.F and II.G
Borough may require supplemental reports, cost not assigned, Section II
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Special exception in the Manufacturing (M) district