Anti-Data Center Policies

Montgomery Township’s enacted ordinance requires setbacks from homes and other protected places, and sets cooling and water-use rules. Data centers can still seek approval, but these limits narrow where and how they can operate.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Montgomery Township
The current rules are in Ordinance No. 26-358Z, which the township code records as adopted on August 10, 2026.Montgomery Township, Montgomery County — data-center ordinance (No. 26-358Z)

What this means

The measure imposes setbacks from homes or other protected places and cooling and water-use rules. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements24
  • LI Limited Industrial District only, § 230-103.C(5)

  • Conditional use; no expiration of approval, § 230-103.C(5)

  • Buffers exclude wetlands and riparian buffers only; no assessment

  • 55 dBA day, 45 dBA night at residential, § 230-103.C(5)(9)(h)

  • 3 dBA over baseline only where baseline exceeds limits, § 230-103.C(5)(9)(d)

  • 70 dBC day, 60 dBC night tonal limits, § 230-103.C(5)(9)(h)

  • Study with application and within 180 days of operation, § 230-103.C(5)(9)(b)

  • Numeric vibration limits with study, § 230-103.C(5)(9)(b)

  • Public water only; wells and surface withdrawals prohibited, § 230-103.C(5)(7)(b)-(c)

  • Closed loop required; open loop and evaporative prohibited, § 230-103.C(5)(7)(a)

  • Projected water use documented, § 230-103.C(5)(7)

  • EPA Tier 4 generators with annual testing, § 230-103.C(5)(6)(a) and (10)

  • Thermal impact mitigation plan with waste heat reuse review, § 230-103.C(5)(8).

  • Electronic waste plan for servers, batteries, hazardous materials, § 230-103.C(5)(12).

  • Utility interconnection documentation; no third-party inspection, § 230-103.C(5)(4)(a)

  • Energy usage plan; rooftop solar efforts documented, not required, § 230-103.C(5)(4)

  • Substations side or rear and screened; lines 34.5 kV or less buried, § 230-103.C(5)(5)

  • Buffer yards 100 to 300 ft by footprint, § 230-103.C(5)(15)(j).

  • Equipment screened with acoustic barrier; no height standard, § 230-103.C(5)(15)(d)

  • Plan reviewed by fire department; no annual update, § 230-103.C(5)(11)

  • Disposal only; no storage setbacks or containment

  • Annual fire safety inspections, § 230-103.C(5)(11)(a)(v)

  • Regular energy efficiency and emissions reports, § 230-103.C(5)(4)(a)(v)

  • Applicant pays township review of decommissioning estimates only, § 230-103.C(5)(16)(e)

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the LI Limited Industrial district

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data