Monroe Township

Anti-Data Center Policies

Monroe Township’s enacted ordinance requires data centers to follow cooling and water-use rules, noise limits and sound testing, and setbacks from homes and other protected places; projects remain approvable but face added costs.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Monroe Township
The current rules are in Ordinance 2025-03, which the Board of Supervisors enacted on December 15, 2025, while the Planning Commission drafts revisions.Monroe Township, Cumberland County — data-center ordinance (No. 2025-03)

What this means

The measure imposes cooling and water-use rules, noise limits and sound testing and setbacks from homes or other protected places. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements16
  • Conditional use, Table 3.01; no approval expiration

  • Underlying district height applies; no data center height limit, § 3.05(I)(10)(f)

  • Section 3.05(I)(10)(a) requires multi-phase data center developments to be shown on a master plan, but the ordinance states no electrical demand for each phase and no trigger that requires a new approval for added capacity.

  • Single limit of 60 dBA or preexisting levels at the property line, § 3.05(I)(10)(i)

  • Ambient noise study by the applicant before approval; no later study, § 3.05(I)(10)(i)

  • Public water connection required, with a hydrogeologic water supply study if private supplies are proposed; no pump tests, § 3.05(I)(10)(m)

  • Section 3.05(I)(10)(m)(2) requires data centers to use air-cooled or closed-loop mechanical cooling, and Section 3.05(I)(10)(m)(3) requires SRBC approval above stated withdrawal and consumptive use thresholds.

  • Peak and average demand disclosed and SRBC approval above thresholds; no cap or reporting, § 3.05(I)(10)(m)

  • Will-serve letter from the wastewater supplier and DEP approval for any surface discharge before Township approval, § 3.05(I)(10)(m)

  • Interconnection agreement confirming capacity; no electrical inspection, § 3.05(I)(10)(l).

  • Assessment of utility rate impacts with required mitigation; grid upgrade costs not assigned, § 3.05(I)(10)(l)(3)

  • 100-ft vegetated buffer yard between parking and accessory uses and adjacent homes, § 3.05(I)(10)(h).

  • Mechanical equipment fully screened on all sides with acoustical barriers near homes and 5-ft berms; no 12-ft standard, § 3.05(I)(10)(g) and (i).

  • Emergency response plan reviewed by the Fire Chief with a 24-hour contact; no annual updates or radio coverage, § 3.05(I)(10)(n)

  • Plan must identify specialized first-responder training needs; cost not assigned, § 3.05(I)(10)(n)

  • Annual fire safety inspections, § 3.05(I)(10)(n)

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the I Industrial and HC Highway Commercial districts

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data