City of Monessen

Pro-Data Center Policies

Monessen allows data centers in designated districts, including industrial districts, without special discretionary approval; in the B-3 business district, special approval is still required. Ordinary zoning, building, and permit rules continue to apply.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Monessen City
The rules are in the Zoning Ordinance of 2022, which City Council approved 4 to 0 on November 21, 2022 and eCode360 lists as Ordinance No. 1265, although the unsigned copy posted there still carries the label No. 1262, a number the city later gave to its 2023 appropriation ordinance.Monessen City, Westmoreland County — data-center ordinance (No. 1265)

What this means

The measure expressly allows data centers in designated districts without a special discretionary use approval. This gives developers a clearer approval route, while ordinary zoning and building rules still apply.

Restrictions & requirementsHide restrictions & requirements3
  • Permitted only in B-3, I-1, and I-2, use tables in §§ 802 and 902

  • Permitted by right in I-1 and I-2; special exception only in B-3

  • 80-ft height for industrial uses, § 905; no rooftop equipment limit

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Permitted by right in I-1 and I-2; special exception in B-3

Sources

current law · City of Monessen
Allows data centers by right in I-1 and I-2 industrial districts, but requires special approval in the B-3 Gateway Business District.Monessen Zoning Ordinance, Chapter 375

What this means

The measure would allow data centers as permitted uses in both industrial districts, making it easier to build them there. In the B-3 business district, they would need special approval and still have to follow applicable zoning and permit rules, so the overall benefit is modest.

Timing

Ends
when the proposed ordinance is enacted or rejected according to law

The temporary hold applies only to zoning permit applications for uses or matters the pending amendment would prohibit. All other provisions are not stated to expire.

People behind it

  • Introduced the ordinance.

  • Prepared the proposed zoning ordinance.

  • Prepared the proposed ordinance and recommended it to City Council.

Show 4 more peopleShow fewer people
  • Assisted in preparing the proposed ordinance.

  • Charged with administering and enforcing the zoning ordinance.

  • Authorized to take actions necessary to implement the ordinance.

  • Adopted the zoning chapter on August 10, 1998, by Ordinance No. 10-1998.

Restrictions & requirementsHide restrictions & requirements14
  • Data centers are allowed as a special exception in B-3 and permitted in I-1 and I-2; they are not listed as allowed in other districts, where unlisted uses are prohibited. Data Center

  • A B-3 data center requires Zoning Hearing Board special-exception approval after a public hearing and must meet the ordinance’s review criteria and use-specific standards. Special Exception

  • In I-1, a data center determined to be a heavy-industry or heavy-manufacturing use requires conditional-use approval by City Council. Heavy Industry

  • A zoning permit is required for new or changed uses and most construction, and a Zoning Certificate of Compliance is required before occupancy or use. A building permit cannot be issued until the zoning application is approved. Zoning Permit

  • Applications require a nonrefundable filing fee; procedures requiring public notice also require an advertising deposit. City Council sets the fees by resolution. filing fee

  • For new construction, applicants must submit a Parking Generation Management Plan prepared by a qualified professional at least 15 days before applying for a permit or approval. The approval authority reviews whether the plan meets parking demand without unreasonable burdens on the area. All new construction

  • Parking must meet projected demand. A data center of at least 5,000 square feet that receives or transmits goods by truck must provide loading facilities, with the required number increasing with floor area; loading is not required for uses without truck deliveries. 5,000 square feet or more

  • Industrial development requires a minimum lot size of 1.5 acres in I-1 and 3 acres in I-2. Industrial lots also have district-specific frontage and building-coverage limits, 50-foot front setbacks, 30-foot side and rear setbacks, and an 80-foot maximum building height. Minimum Lot Size

  • B-3 data-center development must meet business-district design standards, including a two-story minimum, a 120-foot maximum building height, façade and entrance requirements, and sidewalk standards. Minimum Building Height

  • A zoning permit involving physical improvements lapses if work is not substantially started within one year or construction is discontinued for a year or more. Conditional-use, special-exception, and variance approvals generally also lapse after a year without the required start of work or, for approvals without physical improvements, without a Zoning Certificate of Compliance; limited renewal is available within the stated period. within one (1) year

  • New industrial development must provide sidewalks along its lot frontage, at least five feet wide unless matching an existing incomplete sidewalk, and must control exterior-light glare onto adjoining property and public rights-of-way. Sidewalks shall be constructed

  • New nonresidential buildings abutting residential property require a 10-foot landscaped transitional buffer yard with specified trees and shrubs. Applicable development must submit landscaping plans and install the landscaping; a Zoning Certificate of Compliance generally cannot issue before approved landscaping is complete. minimum landscaped transitional buffer yard of ten (10) feet

  • Noise from a data center is limited to 68 dBA from 7 a.m. to 9 p.m. and 63 dBA from 9 p.m. to 7 a.m. at residentially used or zoned lots; the limit at other specified lot lines is 65 dBA at all times. Maximum Sound Level

  • Before earth disturbance, grading and erosion-control plans must be submitted for proposed development disturbing more than one-half acre, creating finished slopes steeper than 3:1, or altering land with a natural slope over 15%. Involves an area greater than one-half (½) acre

Benefits & exceptionsHide benefits & exceptions3
  • Data centers are permitted uses in the I-1 and I-2 industrial districts, subject to applicable zoning requirements. In I-1, conditional-use approval is required if the use is determined to be heavy industry. Data Center

  • Data centers may locate in the B-3 Gateway Business District by special exception, with Zoning Hearing Board approval. Data Center

  • A lawfully established data-center use that later becomes nonconforming may continue until abandoned. It may be expanded subject to ordinance limits, including a maximum aggregate increase of 50% over the life of the nonconformity and compliance with required setbacks. may only be expanded