Milford Township
Anti-Data Center Policies
Milford Township’s enacted ordinance allows data centers but imposes cooling and water-use rules, noise limits, and sound testing, adding construction, compliance, or review costs.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Milford TownshipThe current rules are in Ordinance No. 2026-01, the Data Center Ordinance, enacted by the Board of Supervisors on July 30, 2026 and effective immediately.Milford Township, Juniata County — data-center ordinance (No. 2026-01)
What this means
The measure imposes cooling and water-use rules and noise limits and sound testing. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements22
Reviewed as a land development plan under the SALDO, Sec. 7.A(4)-(5); no conditional use hearing
Agricultural and conservation land are sensitive receptors with a 1,000 ft setback, Sec. 4 and 5.C(2); not barred on preserved farmland
Section 5.C(2) applies the 1,000-foot setback from existing residential structures and sensitive receptors to principal buildings, accessory structures, and substations, and the Data Center Accessory Use definition includes generators, cooling towers, and environmental control equipment.
35 ft maximum with waiver, Sec. 5.B; no rooftop equipment height cap
100 ft riparian forest buffer each side, wider on slopes and at wetlands, Sec. 5.Y(6)-(8)
Single 57 dBA CNEL limit at property boundaries, Sec. 5.F(1)
Water feasibility study required for non-public sources, Sec. 5.S(2)
Closed-loop cooling without direct exposure to the atmosphere required, Sec. 5.S(3)
Projected water demand disclosed in feasibility study, Sec. 5.S(2)a
Stormwater plan per local ordinance and DEP rules, Sec. 5.U(3)
Tier 4 or greater generators required, Sec. 5.M; no annual emissions testing
Utility capacity verification and third-party final electrical inspection, Sec. 5.I
Solar Energy Plan with consumption estimate and solar installed within 12 months, Sec. 5.M.
On-site generation permitted subject to safety and interconnection standards, Sec. 5.M
Substations screened, side or rear placement, lines of 34.5 kV and below buried, Sec. 5.L
100 to 300 ft planted buffer yards near homes by footprint, Sec. 5.P(3).
Ground and rooftop equipment screened, Sec. 5.P(2); no 12 ft or acoustic screening standard
Emergency Response Plan to county and fire company, radio coverage, 24-hour contact signs, Sec. 5.N and 5.T; no annual updates
Third-party final electrical inspection, Sec. 5.I(5)
Decommissioning plan with security of at least 100 percent of cost, Sec. 6; no closure notice or removal deadline
Section 7.A(2) revokes approval if the facility is moved or altered out of conformity, and Section 7.C provides judgments of up to $500 per day through the magisterial district judge, but no notice or hearing is required before revocation.
Applicant pays land development and engineer review fees; no independent review of its studies, Sec. 7.B