Mifflin Township

Anti-Data Center Policies

Mifflin Township’s enacted ordinance requires setbacks from homes and other protected places. Data centers can still be approved, but the limits significantly narrow where they can be sited or how they can operate.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Mifflin Township
The rules are in the ordinance the Board of Supervisors enacted on May 11, 2026, headed Ordinance No. 2026-5-11 and listed by the township as Ordinance No. 1 of 2026.Mifflin Township, Columbia County — data-center ordinance (No. 2026-5-11)

What this means

The measure imposes setbacks from homes or other protected places. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements21
  • Technological infrastructure, including data centers, permitted only in an Industrial zone, § 436.02.A

  • Conditional use approved by the Board of Supervisors, § 436.02.B; no approval expiration

  • 1,000 ft from residential buildings, reduced to 350 ft where the setback crosses I-80, § 436.03.C

  • Environmental impact assessment required with the conditional use application, § 436.04.A

  • 70 dB from 7 a.m. to 8 p.m. and 55 dBA at other times at the property line, § 436.05.A

  • Pre-construction sound study and post-construction study within 90 days of operation, § 436.05.A

  • Generator testing counted in noise measurements; no time or hours limits

  • EIA covers groundwater and must include utility approvals to connect to public water and sewer, § 436.04.A

  • Sewer authority approval to connect required; no cooling discharge plan, § 436.04.A

  • Stormwater management systems required, § 436.04.B

  • Air emissions assessed in the EIA only; no generator emission standard

  • Decommissioned structures must have all hazardous materials removed; no recycling plan, § 436.06.A

  • Data center substations included in the regulated use with a 50-ft buffer, § 436.05.D

  • Only a 50-ft unoccupied safety buffer around substations and lines; no planted buffer

  • 30 lux limit at the property line but no shielding requirement, § 436.03.D

  • EIA addresses visual character, screening, and viewsheds; no renderings, § 436.04.A

  • Safety audits at least twice per year reported annually, § 436.07.C

  • Section 436.04.A(3)(n) requires the environmental impact assessment in every case to analyze trip generation, road capacity, and safety, distinguishing construction from operation, but no study area reaching the nearest arterial or interchange the trucks will use is stated.

  • Decommissioning plan, bond sufficient to cover costs, notice, and removal within 6 months; security not set at 110%, § 436.06

  • One post-construction sound study and annual maintenance and safety reports, § 436.05.A and § 436.08.C

  • Pre-application public meeting encouraged but not required, § 436.08.A

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the Industrial zone

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data