Middle Paxton Township
Anti-Data Center Policies
Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.
Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Middle Paxton Township.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
pending · Middle Paxton TownshipThe township posted the final revised draft, with pages dated September 17, 2026, on October 6, 2026 for the Planning Commission's final review; it has not been adopted, and no Board of Supervisors hearing date has been announced.Middle Paxton Township, Dauphin County — proposed data-center ordinance (None Adopted)
What this means
The proposal would impose noise limits and sound testing, setbacks from homes or other protected places and building-height limits. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements20
Conditional use with a Board of Supervisors hearing; no approval expiration, § 1418 and § 1441.C
Section 1418.A.5 caps total gross building size at 100,000 square feet including all accessory buildings on the tract, but outdoor equipment such as generators, cooling equipment, and substations does not count toward the cap.
Environmental impact assessment covering riparian buffers, wetlands, and steep slopes, § 1418.Q
General limits of 55 dBA by day and 45 dBA at night at residential lot lines apply, § 1418.J.2 and § 1300.C
Noise study reports dBC only where the township requires it; no dBC limit, § 1418.J.1(b)
Noise impact study at land development where required, and a township post-occupancy study, § 1418.J.1 and J.6
Water feasibility study for nonpublic sources; no well bar or pump test, § 1418.I.1
Closed-loop cooling required for any water cooling system, without exposure to the atmosphere, § 1418.I.3
Projected demand disclosed in the feasibility study; no cap, reporting, or drought plan, § 1418.I.1(b)
Section 1418.I.2 requires the applicant to show that disposal of domestic, cooling, and industrial wastewater has been provided for and approved by the Sewage Enforcement Officer or DEP, but the approval is not required before the zoning permit.
Stormwater plan under the local ordinance and DEP rules, § 1418.Q(c)
Utility capacity letter required only before occupancy, § 1418.K.1
Generation supplying power in normal operations is a separate use with its own approval, § 1418.K.1(f).
Above-ground utility boxes and equipment co-located and screened, § 1418.K.1(c)
30-ft landscape buffer next to residential uses and sensitive receptors, § 1418.G
General facade treatments and color limits, § 1418.F
Equipment within 50 ft of a property line enclosed or screened, § 1418.H
Traffic study above 50,000 sq ft, § 1418.D.4
Bond of at least 100% of the cost; no notice or removal deadline, § 1418.R
Township may hire its own sound expert for a post-occupancy study at the owner's expense, § 1418.J.6
Benefits & exceptionsHide benefits & exceptions1
Proposed approval pathway: Proposed: conditional use in the C-I District
Sources
- www.middlepaxtontwp.org
- www.middlepaxtontwp.org
- www.middlepaxtontwp.org
- www.middlepaxtontwp.org
- www.middlepaxtontwp.org
- www.middlepaxtontwp.org
- www.middlepaxtontwp.org
- www.middlepaxtontwp.org
- www.middlepaxtontwp.org
- www.middlepaxtontwp.org
- www.middlepaxtontwp.org
- www.middlepaxtontwp.org
- padatacenterordinances.org
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data