Borough of McClure

Anti-Data Center Policies

McClure borough requires technical studies and utility checks, noise limits and testing, and setbacks from homes and other protected places. Data centers may still be approved, but these requirements can increase costs.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · McClure Borough
The standards are Chapter 15 of the Code of Ordinances, which the posted copy shows Borough Council adopted on August 12, 2026, with no ordinance number given.McClure Borough, Snyder County — data-center ordinance (Code Chapter 15 (Adopted August 12, 2026))

What this means

The measure imposes technical studies and utility checks, noise limits and sound testing and setbacks from homes or other protected places. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements26
  • 150 ft from all property lines for buildings, accessory structures, and substations, with ground-mounted equipment barred from required setbacks, Sections 2.C.1 and 2.O.2.a.iii

  • Only the 150 ft property line setback, Section 2.C.1; buffer yard widths increase within 500 ft of schools, day care centers, hospitals, and parks, Section 2.O.3

  • 20 ft maximum building height, Section 2.B; rooftop equipment counted in the height limit under Section 2.O.2.b.iv, which controls over the conflicting Section 2.O.2.b.iii under the most restrictive rule in Section 2

  • 100 ft riparian forest buffer on each side, widened on slopes over 10% and by 25 ft at wetlands and vernal ponds, Section 2.X

  • Data center campus defined and accessory uses limited to one unified development, Section 1 and Section 2.A.3; no separation distance

  • Single CNEL limit of 60 dBA at sensitive receptor property boundaries and 70 dBA at other developed property, Section 2.F.1; no separate night limit

  • Impact analysis must show noise impacts fall within acceptable levels, Section 2.P.5; no stated method or post-opening study

  • Section 2.F is titled Noise/Vibration but sets no vibration standard

  • Public water connection and an approved hydrology study required, Sections 2.A.4 and 2.Z; on-site wells not addressed

  • Study of water usage required before approval, Section 2.Z.3; no cooling method rule

  • Projected water usage determined in a required study, Section 2.Z.3; no metering or drought plan

  • Public sewer required and a study of discharge and public discharge capacity, Sections 2.Z.1 and 2.Z.3; no approvals before permit

  • Stormwater management plan required, Section 2.S.3; no added treatment or containment

  • Air sources must be identified with best management practices, Section 2.S.1; no generator emission standard

  • Heat not perceptible at the property line and heat island impacts disclosed, Sections 2.G and 2.P.5; no thermal plan

  • Utility capacity verification required only before the certificate of occupancy, Section 2.I

  • Solar-ready roofs, reflective roofing, and rooftop solar on buildings over 400,000 sq ft, Section 2.Y; no energy plan

  • Generation for normal operation excluded from accessory uses, Section 1; no separate approval standards

  • Substations screened by 15 ft opaque landscaping or wall and placed to the side or rear; on-site lines of 34.5 kV and below buried, Section 2.L

  • Battery storage must meet NFPA 855 with dedicated fire suppression, Section 2.H

  • 100 to 300 ft buffer yards by footprint with evergreen screening 12 ft high within 3 years, Section 2.O.3; no dead plant replacement rule

  • Ground and rooftop equipment screened, Section 2.O.2; screening reduced to road views near industrial districts and sound barriers only at Council discretion, Section 2.F.2

  • Line-of-sight study for service area screening, Section 2.O.1; no renderings or historic site views

  • Posted 24-hour emergency contact signage only, Section 2.M; no emergency plan

  • Third-party final electrical inspection before occupancy only, Section 2.I.5

  • Narrative of vehicle trips only, Section 2.P.1; no traffic study