Loading map…

Borough of Manheim

Anti-Data Center Policies

Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.

Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Borough of Manheim.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

pending · Manheim Borough
The unnumbered draft, with blank enactment lines, was provided by the Borough Manager on October 26, 2026, while it was under review by the Lancaster County Planning Commission, and no public hearing or enactment vote appears on the October 27, 2026 Council agenda.Manheim Borough, Lancaster County — proposed data-center ordinance (None Adopted)

What this means

The proposal would impose cooling and water-use rules, noise limits and sound testing and setbacks from homes or other protected places. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements27
  • Section 220-59B(7)(D) caps height at 35 feet inclusive of rooftop appurtenances and accessory equipment, but the Industrial District height limit for other principal buildings is not in the amending text.

  • Environmental Impact Analysis identifying riparian buffers, wetlands, steep slopes, and floodplains, § 220-59A(13)

  • Section 220-59A requires a conditional use application to establish or expand a Data Center, but it lists no expansion triggers such as added generators, cooling, or electrical demand, and it does not address like-for-like replacement.

  • 60 dBA day and 50 dBA night next to residential and agricultural uses, above the 50 and 45 dBA standard, § 220-59B(6)

  • 67 dBC day and 62 dBC night, above the 60 and 55 dBC standard, § 220-59B(6)

  • Noise plan with the application, pre-construction baseline study, and post-construction study within 12 months of occupancy; none at building permit, § 220-59A(6) and B(6)

  • Testing limited to 10:00 a.m. to 4:00 p.m. weekdays and 100 hours per year, § 220-59B(2)

  • Public water only, with wells and surface water barred for consumptive use and cooling, § 220-59B(15)(1)

  • Section 220-59B(15)(2) requires any water cooling system to be closed loop, and Section 220-59A(2) requires disclosure of the cooling type and projected water use, but evaporative systems are not barred or limited to a stated water-use rate and shown to meet the noise limits.

  • Section 220-59B(19) requires quarterly reports of water usage to the Borough for the first three years and semiannual reports after, Section 220-59B(15)(3) requires annual reporting, and Section 220-59A(3) requires a Drought Response Plan with tiered restrictions for each drought stage declared by DEP, the river basin commission, the water supplier, or the Borough.

  • Generators must meet EPA Tier 4 with annual testing reports, § 220-59B(1)

  • Thermal Impact Mitigation Plan including waste heat recovery, § 220-59A(10).

  • Electronic Waste Management Plan for servers, batteries, and hazardous materials, § 220-59A(8).

  • Energy Management Plan and 10% renewable procurement above 25 MW; no required on-site renewable generation, § 220-59A(4)

  • Accessory electrical substations must be screened, § 220-59B(12)

  • Energy storage must meet applicable fire safety standards; NFPA 855 not named, § 220-59B(4)

  • Section 220-59A(4) requires the Energy Management Plan to identify any necessary transmission, distribution, and substation upgrades, and Section 220-59B(2) makes the owner bear their full cost, but no cost estimate, tariff terms, or executed service agreement before the zoning permit is required.

  • 100-ft buffer next to residential and agricultural uses and districts, § 220-59B(11).

  • Ground equipment enclosed or screened to absorb noise and rooftop equipment screened on all sides; no height standard, § 220-59B(12)

  • Emergency Response Plan submitted to emergency service providers and emergency contact given to the Borough; no annual update or radio coverage, § 220-59A(5) and B(4)

  • Operator must consult annually and provide training to emergency responders on request, § 220-59B(4).

  • Section 220-59A(9) requires a Hazardous Materials Safety Plan with the application and Section 220-59B(5) requires SPCC compliance for diesel storage and a 50-foot tank setback from property lines, but no storage setback from wells and streams is stated.

  • Vehicle trip generation described in the Community Impact Analysis; no traffic study, § 220-59A(12)

  • Secondary emergency access required; public street frontage but no road class requirement, § 220-59B(9)

  • Decommissioning bond of 100% of cost, not 110%, and restoration if not reused within one year, § 220-59A(11) and B(18)

  • Bond recalculated every five years; no first-year update, § 220-59A(11)

  • Quarterly reports for three years and semiannual reports after on water and energy use, § 220-59B(19)

Benefits & exceptionsHide benefits & exceptions1
  • Proposed approval pathway: Proposed: conditional use in the Industrial Zone

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data