Manchester Township
Anti-Data Center Policies
Manchester Township’s enacted ordinance limits data-center noise and building height, requires sound testing and setbacks from homes and other protected places, and adds costs; approval remains possible.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Manchester TownshipThe current rules are in Ordinance 2026-04, which the Board of Supervisors adopted by a 5 to 0 vote on June 9, 2026, following a public hearing held that evening.Manchester Township, York County — data-center ordinance (No. 2026-04)
What this means
The measure imposes noise limits and sound testing, setbacks from homes or other protected places and building-height limits. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements23
Conditional use; no approval expiration, § 27-1301.A
Agricultural districts protected only by the 400-ft setback, § 27-1301.B.4
Single 67 dBA limit at the property line, § 27-1301.E.1
Sound study by an acoustical expert plus an as-built study six months after occupancy, § 27-1301.E.1
Generators must be fully enclosed; no testing hours or hours cap, § 27-1301.E.2
Vibration study showing none perceptible beyond the property line, § 27-1301.E.1.b.
Water feasibility study for nonpublic sources; no bar on wells for cooling, § 27-1301.G.2
Projected water demand and use by purpose, including cooling, disclosed, § 27-1301.G.2
Cooling and industrial wastewater disposal must be approved by the sewage officer or DEP, § 27-1301.G.2.k
Hazardous materials removed and disposed of under law at decommissioning, § 27-1301.K.4.e
Utility certification of capacity and service; no electrical inspection, § 27-1301.H.1.
Substations are accessory uses, and power equipment within 300 ft of roads or homes must be enclosed or screened, § 27-105 and § 27-1301.D.1
Known electric rate impacts must be noted; no cost assignment, § 27-1301.H.1
100-ft planted buffer next to residential districts, sensitive receptors, homes, and roads, § 27-1301.C.1.
Cutoff luminaires with 0.1 footcandle limit at homes and 3000K cap, § 27-1301.F
Equipment within 300 ft of roads, residential districts, or sensitive receptors enclosed or screened; 8-ft fence cap, § 27-1301.D
Emergency plan accepted by the fire department and 24-hour contact signage; no annual update or radio coverage, § 27-1301.I.1 and I.4
Plan must ensure first responders are trained; no funding, § 27-1301.I.1.d
Annual fire safety inspections; no electrical inspection, § 27-1301.I.1.e
Security of 110% of cost, but no closure notice and no removal deadline after 24 months of inactivity, § 27-1301.K
Security adjusted every 5 years; no first-year update, § 27-1301.K.3.c
One as-built sound study, with more only if the township requires, § 27-1301.E.1.a
Noise found by the as-built study is a violation; no specific penalty, § 27-1301.E.1.a
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the Industrial and Heavy Industrial Districts
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data