Maidencreek Township
Anti-Data Center Policies
Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.
Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Maidencreek Township.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
pending · Maidencreek TownshipThe unnumbered August 2026 draft, which the Supervisors authorized the solicitor to prepare as an amendment on September 10, 2026, is scheduled for a public hearing at the Supervisors' regular meeting on November 12, 2026 at 6:00 p.m. at the Township Building.Maidencreek Township, Berks County — proposed data-center ordinance (None Adopted)
What this means
The proposal would impose setbacks from homes or other protected places, minimum site-size requirements and cooling and water-use rules. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements29
Conditional use heard and decided by the Supervisors under § 220-111; no expiration of approval found
Hydrological study, groundwater protection, and § 220-63 standards stated as applying; no riparian buffer, § 220-81.1.I(1) and I(11)
Single 55 dBA limit at any lot line at all times, § 220-81.1.F
Ambient noise appears only as an option for reducing the setback, not as a cap, § 220-81.1.A(7)
Section 220-81.1.G requires a preliminary study with the conditional use application, an interim study at land development, and an as-built study within six months of occupancy, using ANSI S1.4-2014 meters and generally accepted criteria.
Testing and maintenance capped at 8 hours per month; no daytime limit, § 220-81.1.H(2)(c)
Public water connection required, with an engineer's supply study and hydrological study; no pump test, § 220-81.1.I(10)-(11)
Section 220-81.1.I(10) requires a closed-loop system that recirculates and reuses water, with water usage effectiveness consistent with industry standards.
Raw water needs for all capacity disclosed and DRBC approval above thresholds; no cap, reporting, or drought plan, § 220-81.1.I(10) and I(13)
Public sewer connection with a will-serve letter; no cooling discharge plan, § 220-81.1.I(12)
Diesel generators must meet EPA Tier 4; no annual emissions testing or reports, § 220-81.1.H(2)(a)
Heat mitigation plan identifying heat sources; no waste heat reuse review, § 220-81.1.I(3)(a)
Electronic Waste Plan for servers, batteries, hazardous materials, and electronic waste, § 220-81.1.L(1).
Interconnection agreement showing available capacity required; no third-party electrical inspection, § 220-81.1.I(9).
Rooftop solar on at least 65% of the main roof required; no energy usage plan, § 220-81.1.H(1)
Section 220-81.1.I(9) requires an interconnection agreement from the electric service provider stating available capacity and the grid upgrades required before service, with upgrade costs borne by the applicant.
50-ft landscaped buffer with a 15-ft berm along all lot lines, § 220-81.1.C
All rooftop and ground equipment enclosed or fully screened to its height; no 12-ft or acoustic standard, § 220-81.1.D
Project website must show maps and elevations or renderings; no visual impact study, § 220-81.1.M(2)
Emergency Response Plan accepted by the fire department; no annual updates, radio coverage, or posted contacts, § 220-81.1.E(1)
All first responders must receive adequate training; no funding, § 220-81.1.E(1)(d)
110% generator fuel containment and fenced outdoor fuel storage; no storage setbacks, § 220-81.1.H(2)(b) and I(6)
Annual fire safety inspection by a qualified professional, § 220-81.1.E(1)(e)
Secondary emergency ingress and egress required; no arterial or collector road access, § 220-81.1.E(2)
Financial security, 30-day notice, removal within 12 months; security amount not set at 110%, § 220-81.1.J
Section 220-81.1.J(4) and (5) require updated estimates after the first year and every fifth year, but tie the posted security to the plan and cost estimate approved at the conditional use hearing.
One as-built noise study within 6 months of occupancy, later studies on request, § 220-81.1.G(3)
Noise violations must be promptly remedied; no specific penalties, § 220-81.1.G(3)
Applicant public meeting before the first Planning Commission meeting and a project website kept through final approval, § 220-81.1.M
Benefits & exceptionsHide benefits & exceptions1
Proposed approval pathway: Proposed: conditional use in the I Industrial District